| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹4.9 LAdmitted-Finance | L1 | Admitted-Finance | ||
| 2 | L2₹4.9 L+₹1,816.22 (0.37%)Admitted-Finance 21 KBM CHAKDAH P O P S CHAKDAH DIST NADIA PIN 741222 | CHAKDAH | NADIA | WEST BENGAL | 741222 | L2 | Admitted-Finance | ||
| 3 | L3₹5.0 L+₹5,105.06 (1.04%)Admitted-Finance U D M A GOVT OF W B | KOLKATA | WEST BENGAL | 700061 | L3 | Admitted-Finance |
Tender Value
₹4.9 L
EMD Value
₹10,000
Closing Date
8 Sept 2026, 12:00 pmClosed
E.E (ROADS)
OFFICE OF THE DIRECTOR GENERAL (ROADS) ROADS DEPARTMENT KOLKATA MUNICIPAL CORPORATION CHAPLIN BHAVAN, 2ND FLOOR, 5/2, CHOWRINGHEE PLACE, KOLKATA-700013
REPAIRING OF ROADS (PORTION) OF RAJA SANTOSH ROAD, NATIONAL LIBRARY AVENUE (IN PATCHES) ETC. UNDER BR-IX.
2026_KMC_1039232_1
KMC/ROADS/2026-2027/50
Open Tender
CIVIL WORKS
Percentage
180 days
KOLKATA
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹10,000
Yes
25 Sept 2026
29 Aug 2026
10 Sept 2026
29 Aug 2026
8 Sept 2026
29 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Picking up and removing old bituminous layer or sand sealing coat from old black topped surface and cleaning the exposed surface by scraping and stacking the material as directed. (a) By manual means : (ii) From 50 mm to 100 mm thick. ( Ref :PWD (Rds & Brdgs)-2018, It. No. 18.02 Page No.331) | 1,328.41 | SQM | 30.4 | ₹40,383.66 |
| 2 | Tack Coat Providing and applying tack coat with Cationic Bitumen Emulsion of approved grade conforming to IS:8887-1978 on the prepared surface cleaned with Hydraulic broom, moistening the surface including cost and carriage of emulsion, hire charges of machinery and labour,cost of fuel and lubricants all complete as per Clause 503 of Specifications for Road & Bridge Works of MoRT&H (5th Revision). (i) On Bituminous Surface (Using Bitumen Emulsion at the rate of 0.20 to 0.30 kg per sqm.)(Rate as per PWD(WB) schedule of rates 2018 (Roads & Bridge Work), page-213(table-3.3-1) & 251 (item-5.02)) | 1,328.41 | SQM | 9.36 | ₹12,433.92 |
| 3 | Transportation and laying 40 mm thick hot asphaltum mixture from kmc plant to the work site including rolling but excluding the cost of tack coat (covered area- 1250 square meter per 100 mt hot-mixture)a) without paver finisheri) Night Time ( Ref :As per KMC Rates, taxes, fees & Charges for the year 2019-2020, As per present market Price, Rate appvd. By D.G.(Civil) Circular No-21 of 2016-17 dtd-25.10.16 vide resolution MIC meeting (Item no-M-29.22 dtd-21.09.16), Mpl. Secretary Circullar no-02 of 2018-19 dtd.04.04.2018 ) | 664.2 | SQM | 45 | ₹29,889 |
| 4 | Transportation and laying 40 mm thick hot asphaltum mixture from kmc plant to the work site including rolling but excluding the cost of tack coat (covered area- 1250 square meter per 100 mt hot-mixture)a) without paver finisheri) Day Time ( Ref :As per KMC Rates, taxes, fees & Charges for the year 2019-2020, As per present market Price, Rate appvd. By D.G.(Civil) Circular No-21 of 2016-17 dtd-25.10.16 vide resolution MIC meeting (Item no-M-29.22 dtd-21.09.16), Mpl. Secretary Circullar no-02 of 2018-19 dtd.04.04.2018 ) | 664.2 | SQM | 41 | ₹27,232.2 |
| 5 | Liquid Seal Coat (Type A) Providing and laying Liquid Seal Coat (Type A) with approved quality stone chips and bitumen binder on thoroughly cleaned black top surface, spreading screened & cleaned stone aggregates (100 % passing through 11.2 mm sieve and retained on 2.36 mm sieve) uniformly @ 0.09 m3 of dry aggregate per 10 m2 of area using suitable means, brushing the chips, if necessary, to ensure uniformity, followed by rolling with power roller including the cost and carriage of binder and stone chips, cost of heating the binder and all other incidental charges, cost of fuel and lubricants, including hire charges of machineries, tools & plants required for construction and quality control complete as per Clause 511 of Specifications for Road & Bridge Works of MoRT&H (5th Revision). (ii) With Cationic Bitumen Emulsion (@ 15.00 kg / 10 sqm.)((Ref. - Item No. - 5.13(A)(II), P-258 of P.W(R)D Schedule 2018, Format-B, P-220 of P.W(R)D Schedule 2018, TABLE No. T-1, Item no.-4/A, P-230 of P.W(R)D Schedule 2018, TABLE III-2, ROW-16, P-226 of P.W(R)D Schedule 2018, Ref-TABLE No. T-1, Item no.-3/A, P-230 of P.W(R)D Schedule 2018, 1.03 A (C), P-227 of P.W(R)D Schedule 2018, TABLE No. T-1, Item no.-3/A, P-230 of P.W(R)D Schedule 2018)) | 4,651.6 | SQM | 64.91 | ₹3,01,935.3 |
| 6 | Sub Total | - | - | - | - |
| 7 | GST 18% | 1 | Nos. | - | - |
| 8 | CESS 1% | 1 | Nos. | - | - |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.86 MB
BOQ_2552371.xls
BOQ • 0.24 MB
TFORM50.pdf
Tender Documents • 0.84 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .