| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹6.4 CrAccepted-AOC | ₹6.4 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹6.5 Cr+₹12.9 L (2.02%)Rejected-Finance | ₹6.5 Cr+₹12.9 L (2.02%) | L2 | Rejected-Finance L2 |
| 3 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
| Sl No | Description | Qty | Unit | Priya Construction L1 | M/s Nirbhay Constructions L2 |
|---|---|---|---|---|---|
| 1.00 | Providing and constructing one span service road to reach island location from one pier location to another pier location for span length 30 m, width of service road 10m and depth of water 1m including cost of material, all labour, T&P etc required for proper completion of the work as per E./I. and also GST and cess (Morth Specification 1200, Data Book Sl. No. 12.9C) | 40 | mtr | 6,800 ₹2,72,000 Lowest | 6,889.9 ₹2,75,596 |
| 2.00 | Providing and Constructing Temporary Island 11.0 m diameter and 1.80m height for Construction of Well Foundation for 5.50 m dia. Well including placing of cutting age under water portion providing 40 cm. above platform from water lavel and its protection by suitable mean and also making plateform for Machinaries including etc. reqd for proper completion of the work. and also including all type of taxes but excluding GST and Labour cess as per specification 12.9B (Morth Specification 1200, Data Book Sl. No. 12.9) | 2 | No. | 68,000 ₹1,36,000 Lowest | 68,861 ₹1,37,722 |
| 3.00 | Providing and Laying Cutting Edge of Mild Steel for Well Foundation complete as per Drawing and Technical Specification and including cost of material, all labour, T&P etc required for proper completion of the work as per E./I. and excluding GST and cess (MoRTH Specification No. 1200 &1900 Data Book Sl. 12.10 ) | 2.84 | M.T. | 88,000 ₹2,49,920 Lowest | 88,300 ₹2,50,772 |
| 4.00 | Reinforced Cement Concrete, in Well curb of M30 Grade complete as per Drawing and Technical Specification. including cost of grit, coarse sand from butwal quarry, all labour, T&P etc reqd. for proper completion of the work..excluding GST and Cess (MORTH Specification 1200, 1500 & 1700 Data Book Sl. No. 12.11A (iii)) | 38.94 | Cum | 13,140 ₹5,11,671.6 Lowest | 13,145 ₹5,11,866.3 |
| 5.00 | Reinforced Cement Concrete, in Well steining of M30 Grade complete as per Drawing and Technical Specification. including cost grit and coarse sand from Dala quarry including all labour, T&P etc reqd. for proper completion of the work, and also Excluding GST and cess (12.11B (vii)) | 497.17 | Cum | 11,700 ₹58,16,889 Lowest | 11,712 ₹58,22,855.04 |
| 6.00 | Sinking of 5.50 m external diameter well (other than pneumatic method of sinking) through all type of Strata namely sandy Soil as shown againts each case complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level upto 20.00 m depth including required all machinary, other devices, all labour, T&P etc reqd. for proper completion of the work including all taxes but excluding GST and and cess (MORTH Specification Section 1200, Data Book Sl. No.12.12A MORTH Section 1200) | 9.6 | Rmt | 4,490 ₹43,104 Lowest | 4,493 ₹43,132.8 |
| 7.00 | Beyond 3.00 to 10.00 mtr | 28 | Rmt | 6,355 ₹1,77,940 Lowest | 6,360 ₹1,78,080 |
| 8.00 | Beyond 10.00 to 20.00 mtr | 20 | Rmt | 8,350 ₹1,67,000 Lowest | 8,400 ₹1,68,000 |
| 9.00 | Plain Cement Concrete, in Bottom Plug OPC Grade M25 complete including cost grit and coarse sand from Dala quarry all labour, T&P etc reqd. for proper completion of the work, and also including all type of taxes but excluding GST and cess as per Drawing and Technical Specification.(12.11C (ii)) | 162.01 | Cum | 11,280 ₹18,27,472.8 Lowest | 11,282 ₹18,27,796.82 |
| 10.00 | Plain Cement Concrete, in Intermediate Plug OPC Grade M25 complete including cost grit and coarse sand from Dala quarry all labour, T&P etc reqd. for proper completion of the work, and also including all type of taxes but excluding cess as per Drawing and Technical Specification. (12.11D (i)) | 16.63 | cum | 11,280 ₹1,87,586.4 Lowest | 11,282 ₹1,87,619.66 |
Tender Value
₹6.1 Cr
EMD Value
₹12.2 L
Closing Date
16 Dec 2025, 12:00 pmClosed
SE GONDA CIRCLE PWD GONDA
SE GONDA CIRCLE PWD GONDA
Construction work of 3 x 18.75 m span RCC minor bridge on Jhinne drain at Km-9 of Hariharganj Laliya Bankatwa road (ODR) in Distt Balrampur
2025_CEDPW_1097694_1
4665/2Com(B)-Gonda Circle/25-26 Dt. 03.11.25
Open Tender
Civil Works - Bridges
Item Wise
365 days
BALRAMPUR
Please refer Tender documents.
2 documents required · 2 mandatory
₹11,800
Yes
₹12.2 L
Yes
GONDA
11 Aug 2026
9 Dec 2025
16 Dec 2025
9 Dec 2025
16 Dec 2025
9 Dec 2025
10 Dec 2025
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Providing and constructing one span service road to reach island location from one pier location to another pier location for span length 30 m, width of service road 10m and depth of water 1m including cost of material, all labour, T&P etc required for proper completion of the work as per E./I. and also GST and cess (Morth Specification 1200, Data Book Sl. No. 12.9C) | 40 | mtr | 6,500 | ₹2,60,000 |
| 2 | Providing and Constructing Temporary Island 11.0 m diameter and 1.80m height for Construction of Well Foundation for 5.50 m dia. Well including placing of cutting age under water portion providing 40 cm. above platform from water lavel and its protection by suitable mean and also making plateform for Machinaries including etc. reqd for proper completion of the work. and also including all type of taxes but excluding GST and Labour cess as per specification 12.9B (Morth Specification 1200, Data Book Sl. No. 12.9) | 2 | No. | 77,000 | ₹1,54,000 |
| 3 | Providing and Laying Cutting Edge of Mild Steel for Well Foundation complete as per Drawing and Technical Specification and including cost of material, all labour, T&P etc required for proper completion of the work as per E./I. and excluding GST and cess (MoRTH Specification No. 1200 &1900 Data Book Sl. 12.10 ) | 2.84 | M.T. | 84,000 | ₹2,38,560 |
| 4 | Reinforced Cement Concrete, in Well curb of M30 Grade complete as per Drawing and Technical Specification. including cost of grit, coarse sand from butwal quarry, all labour, T&P etc reqd. for proper completion of the work..excluding GST and Cess (MORTH Specification 1200, 1500 & 1700 Data Book Sl. No. 12.11A (iii)) | 38.94 | Cum | 12,200 | ₹4,75,068 |
| 5 | Reinforced Cement Concrete, in Well steining of M30 Grade complete as per Drawing and Technical Specification. including cost grit and coarse sand from Dala quarry including all labour, T&P etc reqd. for proper completion of the work, and also Excluding GST and cess (12.11B (vii)) | 497.17 | Cum | 10,900 | ₹54,19,153 |
| 6 | Sinking of 5.50 m external diameter well (other than pneumatic method of sinking) through all type of Strata namely sandy Soil as shown againts each case complete as per drawing and technical specifications. Depth of sinking is reckoned from bed level upto 20.00 m depth including required all machinary, other devices, all labour, T&P etc reqd. for proper completion of the work including all taxes but excluding GST and and cess (MORTH Specification Section 1200, Data Book Sl. No.12.12A MORTH Section 1200) | 9.6 | Rmt | 4,300 | ₹41,280 |
| 7 | Beyond 3.00 to 10.00 mtr | 28 | Rmt | 6,100 | ₹1,70,800 |
| 8 | Beyond 10.00 to 20.00 mtr | 20 | Rmt | 8,100 | ₹1,62,000 |
| 9 | Plain Cement Concrete, in Bottom Plug OPC Grade M25 complete including cost grit and coarse sand from Dala quarry all labour, T&P etc reqd. for proper completion of the work, and also including all type of taxes but excluding GST and cess as per Drawing and Technical Specification.(12.11C (ii)) | 162.01 | Cum | 10,500 | ₹17,01,105 |
| 10 | Plain Cement Concrete, in Intermediate Plug OPC Grade M25 complete including cost grit and coarse sand from Dala quarry all labour, T&P etc reqd. for proper completion of the work, and also including all type of taxes but excluding cess as per Drawing and Technical Specification. (12.11D (i)) | 16.63 | cum | 10,500 | ₹1,74,615 |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.43 MB
SBD.pdf
Tender Documents • 1.10 MB
BIDDOCUMENT.pdf
Tender Documents • 1.26 MB
BOQ_2021385.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .