| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹13.6 LAdmitted-Finance | ₹13.6 L | L1 | Admitted-Finance |
| 2 | L2₹13.9 L+₹22,308.40 (1.63%)Admitted-Finance | ₹13.9 L+₹22,308.40 (1.63%) | L2 | Admitted-Finance |
| Sl No | Description | Qty | Unit | Sri Kailash nath chaturvedi L1 | indrajeet agencies L2 |
|---|---|---|---|---|---|
| 1.00 | Dewatering work by 10 HP Diesel pump set with operator & P.O.L. | 25.04 | Hrs. | 139.5 ₹3,493.08 | 139.3 ₹3,488.07 Lowest |
| 2.01 | (i lift) Earth work excavation in ordinary soil / kanker mixed hard soil I/c Up to 1.50 m. lift and 30 m. lead | 335.13 | cum. | 63.9 ₹21,414.81 | 63.68 ₹21,341.08 Lowest |
| 2.02 | (ii lift) Earth work excavation in ordinary soil kanker mixed hard soil I/c Up to 1.50 m. to 1.80 m lift and 30 m. lead | 60.6 | cum. | 66 ₹3,999.6 | 65.87 ₹3,991.66 Lowest |
| 2.03 | (iii lift) Earth work excavation in ordinary soil kanker mixed hard soil I/c Up to 1.80 m. to 2.10 m lift and 30 m. lead | 64.09 | cum. | 67.9 ₹4,351.71 Lowest | 68.06 ₹4,361.84 |
| 2.04 | (iv lift) Earth work excavation in ordinary soil kanker mixed hard soil I/c Up to 2.10 m. to 2.40 m lift and 30 m. lead | 54.67 | cum. | 70 ₹3,826.9 Lowest | 70.25 ₹3,840.4 |
| 3.00 | Removal of slush from nala bed before excavation s.soil Up to 2.40 m. to 2.70 m lift and 30 m. lead | 17.33 | cum. | 112.5 ₹1,949.63 | 112.44 ₹1,948.5 Lowest |
| 4.01 | (vii lift) Earth work excavation in foundation in mar kabar ordinary & kanker mixed saturated soil crest, wing wall etc. Up to 2.40 m. to 2.70 m lift and 30 m. lead | 49.12 | cum. | 72 ₹3,536.64 Lowest | 72.44 ₹3,558.06 |
| 4.02 | (viii lift) Earth work excavation in foundation in mar kabar ordinary & kanker mixed saturated soil crest, wing wall etc. Up to 2.70 m. to 3.00 m lift and 30 m. lead | 50.32 | cum. | 74 ₹3,723.68 Lowest | 74.63 ₹3,755.13 |
| 4.03 | (ix lift) Earth work excavation in foundation in mar kabar ordinary & kanker mixed saturated soil crest, wing wall etc. Up to 3.00 m. to 3.30 m lift and 30 m. lead | 43.8 | cum. | 76.2 ₹3,337.56 Lowest | 76.81 ₹3,364.45 |
| 4.04 | (x lift) Earth work excavation in foundation in mar kabar ordinary & kanker mixed saturated soil crest, wing wall etc. Up to 3.30 m. to 3.60 m lift and 30 m. lead | 6.39 | cum. | 78.2 ₹499.7 Lowest | 79 ₹504.83 |
Tender Value
Refer Docs
EMD Value
₹1.4 L
Closing Date
4 Mar 2021, 10:00 amClosed
Executive Engineer Minor Irrigation Division Prj
Office of the Executive Engineer Minor Irrigation Division 321/1 shivkuti teliyarganj Prayagraj
Construction of check dam Babhanpur at village Babhanpur, Block-Lalganj, Distt.-Pratapgarh
2021_UPMID_559154_1
1674/M.I./Ac/N.Suchna/20-21 Dt 18.02.21
Open Tender
Civil Works
Item Rate
30 days
Babhanpur, Block-Lalganj, Distt.-Pratapgarh
as per tender notice
2 documents required · 2 mandatory
₹900
Executive Engineer Minor Irrigation Division Prj
₹1.4 L
Yes
5 Mar 2021
27 Feb 2021
4 Mar 2021
27 Feb 2021
4 Mar 2021
27 Feb 2021
27 Feb 2021 - 2 Mar 2021
Amount
Dewatering work by 10 HP Diesel pump set with operator & P.O.L.
(i lift) Earth work excavation in ordinary soil / kanker mixed hard soil I/c Up to 1.50 m. lift and 30 m. lead
(ii lift) Earth work excavation in ordinary soil kanker mixed hard soil I/c Up to 1.50 m. to 1.80 m lift and 30 m. lead
(iii lift) Earth work excavation in ordinary soil kanker mixed hard soil I/c Up to 1.80 m. to 2.10 m lift and 30 m. lead
(iv lift) Earth work excavation in ordinary soil kanker mixed hard soil I/c Up to 2.10 m. to 2.40 m lift and 30 m. lead
Removal of slush from nala bed before excavation s.soil Up to 2.40 m. to 2.70 m lift and 30 m. lead
(vii lift) Earth work excavation in foundation in mar kabar ordinary & kanker mixed saturated soil crest, wing wall etc. Up to 2.40 m. to 2.70 m lift and 30 m. lead
(viii lift) Earth work excavation in foundation in mar kabar ordinary & kanker mixed saturated soil crest, wing wall etc. Up to 2.70 m. to 3.00 m lift and 30 m. lead
(ix lift) Earth work excavation in foundation in mar kabar ordinary & kanker mixed saturated soil crest, wing wall etc. Up to 3.00 m. to 3.30 m lift and 30 m. lead
(x lift) Earth work excavation in foundation in mar kabar ordinary & kanker mixed saturated soil crest, wing wall etc. Up to 3.30 m. to 3.60 m lift and 30 m. lead
(xi lift) Earth work excavation in foundation in mar kabar ordinary & kanker mixed saturated soil crest, wing wall etc. Up to 3.60 m. to 3.90 m lift and 30 m. lead
P.C.C. Work with 1:3:6 (cement,c/sand & 20-40 mm s/ballast i/all cost of material, labour etc. Required for proper completion of work.
R.C.R. Stone masonary work in 1:4 (cement :c/sand) morter i/all the cost of material, labour etc. required for proper complition of the work in foundation.
R.C.R. Stone masonary work in 1:4 (cement :c/sand) morter i/all the cost of material, labour etc. required for proper complition of the work in superstructure.
R.R. Stone masonary work in 1:4 (cement :c/sand) morter i/all the cost of material, labour etc. required for proper complition of the work in superstructure.
P.C.C. Work with 1:2:4 (cement,c/sand & 10-20 mm s/ballast i/all cost of material, labour etc. Required for proper completion of work.
Plaster work 1:3 (cement :c/sand) morter on stone masonary i/all the cost of material, labour etc. required for proper complition of the work.
Raised pointing work 1:2 (cement :c/sand) morter on stone masonary i/all the cost of material, labour etc. required for proper complition of the work.
Laying of C/Sand in inverted filter including cost of material, labour etc.
Laying of Gravel in inverted filter including cost of material, labour etc.
Laying of Stone ballast in inverted filter including cost of material, labour etc.
Laying of dry stone boulder filling in inverted filter including cost of material, labour etc.
indrajeet agencies
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .