Loading…
Loading…
Tender Value
₹2.0 Cr
EMD Value
₹3.9 L
Closing Date
30 Jul 2026, 2:00 pmClosed
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Capital (Works)
Above/Below/Par
OA/4
16 conditions · 4 needing a document upload
Financial Eligibility Criteria: Advance Correction Slip No. 1) Ref: 2022/ce- i/ct/gcc-2022/policy dated- 14.07.2022) A. Para 10.2., Part I of GCC shall be read as under: The tenderer must have minimum average annual contractual turnover of V/N or 'V' whichever is less; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover under: Financial Eligibility Criteria: Advance Correction Slip No. 1) Ref: 2022/ce-i/ct/gcc-2022/policy dated- 14.07.2022) A. Para 10.2., Part I of GCC shall be read as under: The tenderer must have minimum average annual contractual turnover of V/N or 'V' whichever is less; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover under: The tenderers shall submit requisite information as per Annexure-XIV (as per tender document & NIT), along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet.
Similar nature of Work :-"Any civil engineering work involving construction of bridge/culvert/RCC jacketing"
16 conditions · 4 needing a document upload
A . Documents to be uploaded only in the website by the Tenderer Following Annexures duly filled and signed are to be uploaded online only prior to Closing of Tender. Original copy of all the documents to be submitted to office within 7 days whenever demanded by the Railway. Annexures are available at Upload/View Document menu in Home Page of IREPS portal for works tender. 1. The details of the works completed by the tenderer during the last Seven years to be filled in Annexure-I. 2. The details of Plants and Machinery with the tenderer to be filled in Annexure- II. 3. Details of Personnel and Organization of the Tenderer to be filled in Annexure-III. 4. Details of Works presently on hand of the Tenderer to be filled in Annexure- IV. 5. The details regarding Association of Railway Officer s with the tenderer to be filled in Annexure- V. 6. List of the Arbitration cases of the Tenderer during last Five years to be filled in Annexure-VI. 7. List of the Court cases of the Tenderer during last Five years to be filled in Annexure- VII. 8. NEFT MANDATE FORM. All Payments to the agency including the refund of the Earnest Money of the unsuccessful bidder preferably will be remitted through NEFT. The Tenderer is required to submit Bank details and A/C No. etc. in Annexure-VIII. 9.Format for Certificate to be uploaded by Tenderer Along with the tender documents Annexure-IX and IX-A (As per GCC-2022 Annexure-V and V-A). 10. GST COMPLAINT INVOICE Annexure-X 11. LETTER OF CREDIT Annexure-XI, 12. Bid Capacity Declaration Annexure-XII.13. Bid Security declaration Annexure-XIII and 14. Annual Contractual Turnover Data Declaration Annexure-XIV (As per GCC-2022 Annexure-VI-B).
B . T h e tender offer complete in a l l respect and with all documents is t o b e submitted online by e-tendering process through the website www.ireps.gov.in before the closing time/date of this tender as mentioned in the NIT (Notice Inviting Tender). Tenderer can revise the bids any number of times till the closing time/date of the tender. No manual offers shall be accepted.
Demand for the Financial Criteria, Association of Railway Officers, List of Arbitration cases, Court cases and Mandate for NEFT are to be uploaded with a scanned copy duly filled in and signed as per annexure no. IV, V, VI, VII, VIII respectively. These Annexures are available in View Document menu at Home page and is downloadable. The details of the uploaded documents should be produced whenever demanded for verification on written request at any point of time of the tender and contract within 7 days.
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
Replacement of existing steel girder of Br no 62 (3X12.2m, welded plate girder) of up-1/HBC & DN-1/HBC by PSC Slab in between station MDSE-CDAE in HBC of Howrah Division.
175_2026-27
175_2026-27
Open
Works - General
12 Months
Howrah, West Bengal
₹0
₹3.9 L
30 Jul 2026
9 Jul 2026
16 Jul 2026
84 items across 2 schedules
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| — | — | — | 1,45,85,426.65 | ||
| — | 875.00 | — | — | ||
| Unloading of new girder/released girder/components form Railway BFR/Trailor by manual method by the side of railway on the temporary staging. The rate shall include the cost of making of temporary staging, lowering the girder from the staging, with all tools & plants for unloading the girder on level base. NOTE a) CC Cribs and wooden sleepers as per requirment will be supplied by the Railway free of cost at the Railway store or bridge site where the stock is availableand the agency will be return back the materials to the stock holder after purpose of the work is over. b) The rate will include the cost of transportation of all materials including Railway materials with all leading, loading and unloadiing to complete the work in all respect. | — | — | — | 14,08,426.25 | |
| — | 875.00 | — | — | ||
| loading of newly assambled girder components on Railway BFR/Trailor by manual method as per direction of site in-charge. The rate shall include the cost of making of temporary staging, with tools and plant tackles consumables labours transportation etc with all lead in all respect. Note A) BFR is to be placed at BRI siding by the railway free of cost. B) CC Cribs and wooden sleepers as per requirment will be supplied by the Railway free of cost to agency and the material shall be return back to the stock holder after complition of the work. C) The Rate includes cost of all tools and tackles required for the work. D) The work shall be carried out as per instruction of site in- Charge. | — | — | — | 16,25,111.25 | |
| — | 875.00 | — | — | ||
| Erection and placing of PSC/RCC slab on bridge abutment including dismantling of existing girder with road crane of revolving type of capacity 40 MT Or by manual levelling the bed with supplying and laying of materials like epoxy based materials/M-35 cement concrete with 10 mm down stonechips with suitable admixture for quick setting duly passed by Assistant Engineer. The rate will include the safe stacking of released girders at the nearest LC gate with cost of transportation, lead, lift, etc. The work consist of following operation. (a) Construction of temporary road from existing road to bridge location by cutting of earth heaps, dressing level, compacting, etc for movement of crane to and from works complete in all respect. (b) Cutting holding down bolts by gas cutters for releasing base plates under the girder.(c) Taking out girder by lifting with road crane safely from the bridge and placing the same at suitable location away from bridge as per instruction of site incharge. (d) Lifting the RCC slab from site with road crane manually and placing over bridgesafely with proper alignment ,level, and bearing as per instruction of site engineer.e) Arrangement of lighting with supply of generator set anmd 4nos halogen for provision of sufficient lighting from 20.00 hrs till sun rise(f) slabs will be lying at nearest level crossing ,Cost includes trollying the same with railways dip lorry to site with all arrangement of tools and plants etc .All operation will be done uner traffic and power block at night with sufficient ,man power and machine so that block period is not burst. NoTE:_ All loose fittings are to be stacked at the various stores as directed by the site incharge. | — | — | — | 58,63,287.5 | |
| — | 300.00 | — | — | ||
| Supply of stone ballast 50mm size of approved quality duly stacked as directed and specify by sectionalAEN near the bridge site with all lead, lift, transportation , levelling of ground for stacking as directed by sectional AEN. | — | — | — | 7,17,912 | |
| — | 300.00 | — | — | ||
| Spreading of stone ballast supplied in above item from stack duly passed by sectional AEN with all lead , lift , as per requirement as directed by site in charge by railway | — | — | — | 25,191 | |
| — | 244.00 | — | — | ||
| RCC M35 grade as per Railway approved drawing and specification for construction of Bridge/Sub structure/super structure /RCC jacketing of arch ,pier abutment etc.The Rates includes design of concrete mix manufacture of concrete by batching plant ,cost of form work includws erection and de-shuttering, placement of concrete using concrete pump/placing boom ,comption steel reinforcement cutting , bending and binding of Rein forcement with binding wires and placing in proper position , curing of concrete upto specied period complete in all respect including all lead, lift, crossing road/track etc.The rate also includes cost of all ingredients of RCC in cement ,Sand aggregate admixture,Labour tools and Plants etc.But excluding the cost of reinforcement.The contractor has to construct the approach road to the site at his own cost ,if required, no extra payment will be made for this. "RCC M35 grade as per Railway approved drawing and specification for construction of Bridge/Sub structure/super structure /RCC jacketing of arch ,pier abutment etc.The Rates includes design of concrete mix manufacture of concrete by batching plant ,cost of form work includws erection and de-shuttering, placement of concrete using concrete pump/placing boom ,comption steel reinforcement cutting , bending and binding of Rein forcement with binding wires and placing in proper position , curing of concrete upto specied period complete in all respect including all lead, lift, crossing road/track etc.The rate also includes cost of all ingredients of RCC in cement ,Sand aggregate admixture,Labour tools and Plants etc.But excluding the cost of reinforcement.The contractor has to construct the approach road to the site at his own cost ,if required, no extra payment will be made for this. " | — | — | — | 28,96,084.8 | |
| — | 4.00 | — | — | ||
| "Various testing in connection with concrete slab casting for concrete cube testing for compressive strength [1set denotes 1 sample i.e 3 nos of cubes] " | — | — | — | 3,800.6 | |
| — | 4.00 | — | — | ||
| "Various testing in connection with concrete slab casting for permeability test of concrete. " | — | — | — | 11,687.48 | |
| — | 150.00 | — | — | ||
| Trollying of PSC sleeper with all labours, lead ,lift, tools and plant as directed by site in charge of railway. Only dip lorry will be supplied by the railway on temporary basics .The work will be done strictly under railway representatives supervision (UNIT AGAINST THIS ITEM WILL BE TAKEN IN TO ACCOUNT AS PER BEARING) | — | — | — | 9,679.5 | |
| — | 5.00 | — | — | ||
| Pre-Cast bed block of M-35 grade Concrete as per approved drawing to be casted and placed in position over pier / Abutment in true line and level .The rate includes contractors labour, material, tools & Plants etc & other consumable required to carry out the work in all respect. | — | — | — | 91,950 | |
| — | 25.00 | — | — | ||
| Assistantance to Railway crane working during day/night for removing of existing girder for placement of bridge ,slab,over pier /abutment in traffic block by employing atleast 16 labours for 8hours shift.Labour should be present at the site till completion of the traffic block. | — | — | — | 14,935.25 | |
| — | 10.00 | — | — | ||
| Welding of rail joint in situ on running lines under traffic block in day/night time including supply of required petrol and other consumable labours to make proper alignment of rail and levelling the same for Thermit welding of joints of all rails of any length of any type. PF sleeper and finishing the welded joint on top and gauge face as per instruction laid down in IRPWM and welding manual under direction and with entire specifications of the site In-Charge. | — | — | — | 14,957.7 | |
| — | 8000.00 | — | — | ||
| : Transporting of C.C.Crib/ Slab or any other heavy materials including loading and unloading of the materials with contractor's men, tools and plants etc from SSE/BR/HWH,s store or any other railway workshop to worksite or back. | — | — | — | 4,74,400 | |
| — | 20.00 | — | — | ||
| Assembling/erection/ placing of C.C Cribs staging. (CC. Crib will be supplied by Railway free of Cost at Railway store) | — | — | — | 26,920 | |
| — | 150.00 | — | — | ||
| Trollying rail by rail dolly upto 1 km or part thereof including crossing of lines, platform ,ascend, descend, keeping without infrengement as per instruction of site incharge.(UNIT AGAINST THIS ITEM WILL BE TAKEN IN TO ACCOUNT AS PER BEARING) | — | — | — | 3,276 | |
| — | 150.00 | — | — | ||
| Dismantling of track structure from the old girder, stacking them properly and depositing the same to nearest P.Way store as directed by the site in charge. | — | — | — | 50,737.5 | |
| — | 150.00 | — | — | ||
| Linking of track including Guard rail over new girder as per relevant position in IRPWM. | — | — | — | 50,172 | |
| — | 30.00 | — | — | ||
| Cutting of rails 90R/52Kg/60Kg inside or outside of the track for provision gap in the rail section for erection purpose. The rate shall include all labours, tools & tackles etc required to carry out the work complete in all respect. | — | — | — | 2,234.4 | |
| — | 50.00 | — | — | ||
| Driling holes of rails 90R/52Kg/60Kg inside or outside of the track for provision offish bolt for erection purpose. The rate shall include all labours, tools & tackles etc required to carry out the work complete in all respect. | — | — | — | 3,273 | |
| — | 1500.00 | — | — | ||
| Lifting of Track upto 150mm | — | — | — | 77,115 | |
| — | 5000.00 | — | — | ||
| Three round consolidation packing with cotractors men, tools, plants etc. complete in all respect as per instruction of site incharge. Note- Qty Unit, Per Sleeper means "Per Sleeper Per packing". | — | — | — | 1,02,500 | |
| — | 100.00 | — | — | ||
| Changing rail at 13 m length or less in running track as per direction of site in charge. The payment shall be considerd as one side of track only. | — | — | — | 5,790 | |
| — | 151.00 | — | — | ||
| Hiring charge of 5 KV generator set including fuels, lubricating oils,operation and maintenance with lighting arrangement with 6 nos 500 watt halogen 2 nos point fixing complete in all respect. | — | — | — | 74,581.92 | |
| — | 25000.00 | — | — | ||
| Filling of ballast/sand/stone dust eyc into empty cement bag and placing/spreading the same at any location under the bridge as per instruction of Engineer in charge. | — | — | — | 6,42,500 | |
| — | 15.00 | — | — | ||
| Supplying and application of levelling coarse with epoxy morter of Dr fixit pedigrount EG-3 of M/s Pidilite Industry Ltd/ Sikadur 53 or similar of minimum thinckness 25 mm to provide even bed for fixing bed plate. | — | — | — | 2,92,690.8 | |
| — | 30.00 | — | — | ||
| Cutting and dismantling of first class brick work in the bridge piers abutments and wing wall ,arches ,during preblock and block period . The brick work to be chisled up horizontally or chiselling up from top as ditrected by the railway site incharge. During the cutting of brick work all necessary precaution to be taken for safe running of the railway traffic and maintaining safety of the sound part of the structure .all labours , materials ,tools and plants required for the work to be supplied by the contractor including all lead ,lift and crossing the track . Disposal of the gurbageb at scheduled location etc as directed by the site in charge of the railway. | — | — | — | 96,212.7 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
LetterregardingrecommendedlistofBrands_makeofmaterialsdated03.09.2025.pdf
ATTACHMENT
Updatedtenderdocument_151.pdf
ATTACHMENT
Annexure-XIII_1.pdf
ATTACHMENT
Annexure-IVVVIVIIVIII_2.pdf
ATTACHMENT
ACS11GCCWorks2026.pdf
ATTACHMENT
AnnexureV-GCC1.pdf
ATTACHMENT
GCCACS14.07.2022-compressed.pdf
ATTACHMENT
CheckList_3.pdf
ATTACHMENT
JPOSTCables_1.pdf
ATTACHMENT
Annexure-X2.pdf
ATTACHMENT
NewAnnexure-IX-merged.pdf
ATTACHMENT
Annexure-XII_.pdf
ATTACHMENT
ColouredFinal_GCC_April-22_pdf_27.04.22_1.pdf
ATTACHMENT
Annexure-XI_11_2.pdf
ATTACHMENT
Annexure-XIV_1.pdf
ATTACHMENT
Annexure-IIIIII_3.pdf
ATTACHMENT
2ndcorrectionslip.pdf
ATTACHMENT
specialconditionbr-25-26.pdf
ATTACHMENT
Modified-GCC2026March_compressed1.pdf
ATTACHMENT
AnnexureV-GCC1.pdf
CORRIGENDUM
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .