| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.6 LAccepted-AOC | ₹1.6 L | L1 | Accepted-AOC L1 |
| 2 | L2₹1.6 LRejected-Finance | ₹1.6 L | L2 | Rejected-Finance L2 |
| Sl No | Description | Qty | Unit | HAJA MOHIDEEN L2 | PALANI R L1 |
|---|---|---|---|---|---|
| 1.00 | Earth work excavation in hard stiff clay soil with initial lead and lift as per SS 20B for corewall etc., complete. | 2.07 | Cum | 198 ₹409.86 | 197 ₹407.79 |
| 2.00 | Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum. | 9.52 | Cum | 5,416 ₹51,560.32 | 5,414 ₹51,541.28 |
| 3.00 | Collection and supply of Red gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for filling etc.complete, | 12.21 | Cum | 429 ₹5,238.09 | 428 ₹5,225.88 |
| 4.00 | Brickwork in cement mortar 1:5 mix using country bricks 8 3/4"x4 1/4"x2 3/4" and conveyance of all materials to site and all labour charges etc..Complete for 10 Cum | 3.17 | Cum | 6,144 ₹19,476.48 | 6,143 ₹19,473.31 |
| 5.00 | Cement concrete 1:2:4 mix using 20mm ISS metal including top Finish using Trowel Machine with necessary Genset Arrangements including all cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum. | 6.9 | Cum | 7,425 ₹51,232.50 | 7,423 ₹51,218.70 |
| 6.00 | Plastering with cement mortar 1:5 mix to 12mm thick including cost and conveyance of all materials to site and all labour charges etc complete for 10 Sqm. | 11.5 | sqm | 286 ₹3,289 | 285 ₹3,277.50 |
| 7.00 | Supplying and fixing Bitumenpad 12mm thick for expansion joints at every 4.50m intervals inculding cost of material conveyance to site,cutting finishing etc., complete. | 1.5 | sqm | 510 ₹765 | 509 ₹763.50 |
| 8.00 | GST Amount for providing Service to Government Contract Works for the above RENEWAL Works. { GST Amount is the Total GST Amount for overall quoted amount above this row in column "BB" for all works in this package}
(Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD) | 1 | GST Amount | 23,755 ₹23,755 | 23,743 ₹23,743 |
Tender Value
₹1.6 L
EMD Value
₹1,600
Closing Date
27 Feb 2026, 3:00 pmClosed
Block Development officer
Block Development officeR Tenkasi
Providing CC Pavement at Nadu street at Thiruchitrambalam village and Panchayat in Tenkasi Panchayat union in Tenkasi District under Union General fund 2025-26
2026_RDTN_662861_10
BDOBLK/307/2025-A2 DT 18.02.2026
Open Tender
Civil Works
TENKASI
REFER TENDER NOTICE
3 documents required · 3 mandatory
₹0
₹1,600
13 May 2026
20 Feb 2026
27 Feb 2026
20 Feb 2026
27 Feb 2026
20 Feb 2026
Earth work excavation in hard stiff clay soil with initial lead and lift as per SS 20B for corewall etc., complete.
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Collection and supply of Red gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for filling etc.complete,
Brickwork in cement mortar 1:5 mix using country bricks 8 3/4"x4 1/4"x2 3/4" and conveyance of all materials to site and all labour charges etc..Complete for 10 Cum
Cement concrete 1:2:4 mix using 20mm ISS metal including top Finish using Trowel Machine with necessary Genset Arrangements including all cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Plastering with cement mortar 1:5 mix to 12mm thick including cost and conveyance of all materials to site and all labour charges etc complete for 10 Sqm.
Supplying and fixing Bitumenpad 12mm thick for expansion joints at every 4.50m intervals inculding cost of material conveyance to site,cutting finishing etc., complete.
GST Amount for providing Service to Government Contract Works for the above RENEWAL Works. { GST Amount is the Total GST Amount for overall quoted amount above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.17 MB
Tendernotice_2.pdf
PDF • 0.89 MB
BOQ_795945.xls
BOQ • 0.34 MB
Download all tender documents and submit your bid