| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹6.7 CrAccepted-AOC 102 IST FLOOR DEVIKA CHAMBER RDC RAJ NAGAR GHAZIABAD U P | GHAZIABAD | UTTAR PRADESH | 201001 | ₹6.7 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹7.9 Cr+₹1.3 Cr (19.2%)Rejected-Finance | ₹7.9 Cr+₹1.3 Cr (19.2%) | L2 | Rejected-Finance L2 |
| 3 | L3₹8.0 Cr+₹1.3 Cr (19.8%)Rejected-Finance | ₹8.0 Cr+₹1.3 Cr (19.8%) | L3 | Rejected-Finance L3 |
| 4 | L4₹8.0 Cr+₹1.3 Cr (19.9%)Rejected-Finance SC 326 SHASTRI NAGAR GHAZIABAD | GHAZIABAD | UTTAR PRADESH | 201001 | ₹8.0 Cr+₹1.3 Cr (19.9%) | L4 | Rejected-Finance L4 |
| 5 | L5₹8.5 Cr+₹1.8 Cr (27.0%)Rejected-Finance | ₹8.5 Cr+₹1.8 Cr (27.0%) | L5 | Rejected-Finance L5 |
Tender Value
₹8 Cr
EMD Value
₹16 L
Closing Date
16 Mar 2023, 3:00 pmClosed
superintending engineer
saharanpur circle pwd saharanpur
Work of widening and strengthening of the road from Daulatpur-Nanauta-Mangalore (State Road No.-167) via Dugchada, Jatola Damodarpur, Chaundahedi to the border of Uttarakhand (ODR)(Chainage 0.000 to 7.700 (Length 7.700 KM.) in Distt. Saharanpur
2023_CEMRT_780359_1
1399/96 MS/2022 Date 22-02-223
Open Tender
Civil Works
Fixed-rate
365 days
SAHARANPUR
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,714
₹16 L
4 Jul 2023
2 Mar 2023
16 Mar 2023
2 Mar 2023
16 Mar 2023
2 Mar 2023
Amount
Excavation in foundation in ordinary soil (Loam, clay or sand) including lift upto 1.50 M and lead upto 30 M and including filling watering and ramming of excavated earth into the trenches and removal and disposal of surplus earth as directed by the Engineer-in-charge upto a distance of 30 M from the foundation trenches. complete in all respects but excluding GST. (SI No. 251 (a)
Dimantling brick work or stone work in lime or cement mortar and including stacking of materials as directed be the Engineer-in-charge within a distance of 60 meter (200 feet). complete in all respects but excluding GST. SI. No. 692
Construction of Embankmaent with approved material deposited at site form Roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of Table 300-2. complete in all respects but excluding GST.
Mechanically compected to achieve 95% proctors density including arrangement of water, settlement and all T&P including roller and its fuel etccomplete in all respects but excluding GST.(SI No 260)
Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401. complete in all respects but excluding GST.
Providing laying spereading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mix plant carriage of mixed material by tipper to site, laying in uniform layers with paver in uniform layers with paver in subbase/base course on well prepared surface and compacting with vibratory roller to achieve the desired density.For Widening ((Two Layers) thickenss 150+150 mm).complete in all respects but excluding GST.
Providing & applying Primer coat with bitumen emulsion (S/S Type) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.60kg/Sqm. Using mecha- nical means.complete in all respects but excluding GST.
Providing and applying tack coat with bitumen VG-10 using pressure distributor at the rate of 0.25 kg per sqm on the prepared bituminous/granular surface cleaned with mechanical broom. complete in all respects but excluding GST
Providing and laying Dense Graded Bituminous Mecadam with 100-120 TPH hot mix plant producing an avearge output of 75 tonne per hour using crushed aggregates of specified grading premixed with bitminous binder @ 4.5% by waight of total mix and filler, transported to site, laying with hydrostatic paver finisher with sensor control to the required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem rollers to achive the desired compaction as as per MORTH &H specifications clauses 507 complete in all respects but excluding GST
Providing and applying tack coat with bitumen VG-10 using pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous/granular surface cleaned with mechanical broom. complete in all respects but excluding GST
Providing and laying bituminous cocnrete with 100-120 TPH batch type HMP producing and average output of 75 Tonne per hour using crushed aggregates of specified grading premixed with bituminous binder @ 5.40 percent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver fixisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specificiation clause No. 509 complete in all respects but excluding GST
Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement concrete pavement, thickness as per disign, over a prepared sub base with 43 grade cement or any other type as per Clause 1501.2.2 (1:1½:3) coarse and fine aggregates confirming to IS 383 maximum size of coarse aggregate not exceeding 25 mm, mixed in a concrete mixer of not less then 0.2 cum capacity and appropriate weight batcher using approved mix design, laid in approved fixed side form work (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with shovels. rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including provision of contraction and expansion, construction joints as per norms, applying debonding strips primer, sealant, dowel bars, near approaches to bridge/ culvert and construction, joints, admixtures as approved, curing of concrete slabs for 14-days, curing compound (Where specified) and water finishing to lines and grade as per drawing and Technical Specification Clause 1501 including Cost of Polythene Sheet and Dowel bar and also including complete shifting of matrials & Concrete etc.(M-20) (Ch.20 New item -9) complete in all respects but excluding GST
Cement Concrete with 4 cm. guage approved stone ballast, coarse sand & cement in the proportion of 6:3:1 including supply of all materials, labour, Tools & plants etc. required for proper completion of the work complete excluding GST. (SI. No. 281)
R.C.C. Work with cement, approved coarse sand & 2 cm gauge approved stone grit in proportions of 1:2;4 in lintels of door & windows excluding supply of reinforcement and its bending, but including its fixing and binding the same with 24 B.W.G.G.I. binding wire and including necessary centering and shuttering etc. and supply of all materials, labour, Tools & plants etc. required for proper completion of the work including cost of binding wire. The rate excludes making of drip course which shall be paid extra complete in all respects but excluding GST (SI. No. 283)
Cement Concrete with 2 cm gauge approved stone grit, coarse sand & cement in the proportion of 4:2:1 including supply of all materials, labour, Tools & plants etc. required for proper completion of the work. complete in all respects but excluding GST (SI. No. 279 a)
R.C.C. Work with cement, approved coarse sand & 2 cm gauge approved stone grit in proportions of 1:1.5:3 in lintels of door & windows excluding supply of reinforcement and its bending, but including its fixing and binding the same with 24 B.W.G.G.I. binding wire and including necessary centering and shuttering etc. and supply of all materials, labour, Tools & plants etc. required for proper completion of the work including cost of binding wire. The rate excludes making of drip course which shall be paid extra complete in all respects but excluding GST. (SI. No. 284 a)
Supplying, Fitting and Placing un-coated HYSD bar Reinforcement in Foundation complete as per Drawing and Technical Specifications. complete in all respects but excluding GST
Providing and laying boulder apron for bed protection with stone boulders of minimum size and weight as per Table 1300.1, no fragment weighing less than 25 kg laid dry complete as per drawing and technical specifications clause 1301. complete in all respects but excluding GST
(a) Sand filling in plinth and under floor including supply of necessary quantity of sand from a distance not exceeding 8 Kms. from the site of work and including watering, dressing etc. labour and T&P etc. required for proper complition of the work. saplings of girth upto 30 cms. measured at a height of 1 M. above ground level and removal of rubbish upto a distance of 50 M. out side the periphery of area cleared. including cost of sand.complete in all respects but excluding GST S.I. No.255
M-150 Brick on edge pavement on parties with bricks, laid dry joints filled with local sand including preparation of base to proper slope, and its ramming, spreading layer of 1 cm. (3/8") depth of local sand over the subgrade and including supply of all materials, labour Tools &plants etc. required for proper completion of the work. complete in all respects but excluding GST S.I. No. 763
Supply & fixing of NP-3 class 350 mm dia RCC hume pipe (ISI mark) of following diameters including carriage, loading, unloading at site also including cost of hume pipes & collars & all taxes including laying in proper position & joint filling including cost of necessary jute & cement for proper completion of the work complete in all respects but excluding GST
Supply & fixing of NP-3 class 450 mm dia RCC hume pipe (ISI mark) of following diameters including carriage, loading, unloading at site also including cost of hume pipes & collars & all taxes including laying in proper position & joint filling including cost of necessary jute & cement for proper completion of the work complete in all respects but excluding GST
Supply & fixing of NP-3 class 600 mm dia RCC hume pipe (ISI mark) of following diameters including carriage, loading, unloading at site also including cost of hume pipes & collars & all taxes including laying in proper position & joint filling including cost of necessary jute & cement for proper completion of the work complete in all respects but excluding GST
Supply & fixing of NP-3 class 900 mm dia RCC hume pipe (ISI mark) of following diameters including carriage, loading, unloading at site also including cost of hume pipes & collars & all taxes including laying in proper position & joint filling including cost of necessary jute & cement for proper completion of the work complete in all respects but excluding GST
Supply & fixing of NP-3 class 1000 mm dia RCC hume pipe (ISI mark) of following diameters including carriage, loading, unloading at site also including cost of hume pipes & collars & all taxes including laying in proper position & joint filling including cost of necessary jute & cement for proper completion of the work complete in all respects but excluding GST
M-150 Brick work in in 1:4(One cement & four fine sand) mortar in foundation and plinth including supply of all materials labour, Tools & plants etc. required for proper completion of the work complete in all respects but excluding GST. (SI. No. 305 (a))
Struck pointing with cement mortar consisting of 1 part cement and 2 parts of fine sand of 1.25 Fineness modulus complete in all respects but excluding GST. (SI. No. 574)
12 mm thick plaster with cement and fine sand of 1.25 fineness modulus in 1:4 over brick work minimum thickness not to be less than 1 cm including supply of all materials, labour, tools & plants etc required for proper completion of the work complete in all respects but excluding GST. (SI. No.584)
2.5 cm thick Damp Proof Course with Cement and approved coarse sand 1:2 with and including water proofing compound (1 Ltr. to 1 bag of cement of 50 Kg.) as ordered by the Engineer incharge in the proportion as specified by the manufacturer including supply of all materials, labour, Tools & plants etc. required for proper completion of the work and including proper curing & shutterings as necessary complete in all respects but excluding GST. (SI No 361)
SHIV SHAKTI INFRABUILDWELL PRIVATE LIMITED
SINEWY CONSTRUCTIONS PVT. LTD.
SHARMA CONSTRUCTION PROJECT PVT LTD
M/S CHAUDHARY ASSOCIATES
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .