Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹34.5 L
EMD Value
₹68,900
Closing Date
23 Oct 2026, 4:00 pm
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Executive Engineer RnB Division Kulgam
Executive Engineer RnB Division Kulgam
Development of on Street Parking at MC Kulgam
2026_PWDJK_327943_3
82/2026-27/RnB/Kul/7703-13 Dtd 12-10-2026
Open Tender
Civil Works
Percentage
60 days
Kulgam
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,100
Account No. 0470010200000099
₹68,900
13 Oct 2026
13 Oct 2026
24 Oct 2026
13 Oct 2026
23 Oct 2026
13 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1.1 | Earth work in bulk excavation by mechanical means (hydraulic excavator) over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 m2 on plan) including disposal of excavated earth lead upto 50 meters and lift upto 1.5 m, as directed by Engineer-in-Charge. All kinds of soil . | 67.97 | Cum | 164.2 | ₹11,160.67 |
| 1.2 | Demolishing RCC work/tiles etc by mechanical means & stockpiling at designated locations & disposal of dismantled materials upto a lead of 1 kilometer, stacking serviceable & unserviceable material separately including cutting reinforcement bars | 17 | Cum | 1,796.61 | ₹30,542.37 |
| 1.3 | P/L of dry stone soling duly hand packed including carriage by MT 05 Kms | 57.77 | Cum | 805.08 | ₹46,509.47 |
| 1.4 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size) | 33.98 | Cum | 4,562.25 | ₹1,55,025.25 |
| 1.5 | Providing and laying in position specified grade of reinforced cement concrete including curing but excluding the cost of centering, shuttering, finishing and reinforcement. All works upto plinth level 5.1.2 1:1½:3 (1 cement : 1½ coarse sand : 3 graded stone aggregate 20 mm nominal size) | 60.72 | Cum | 6,828.04 | ₹4,14,598.59 |
| 1.6 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with:1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) | 13.59 | Cum | 5,778.08 | ₹78,524.11 |
| 1.7 | Centering and shuttering including strutting, propping etc. and removal of form for: Foundations, footings, bases of columns etc. for mass concrete. | 173.98 | SQM | 251.03 | ₹43,674.2 |
| 1.8 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level 5.22.1 Mild steel and medium tensile steel bars | 7,286.32 | KGS | 108.02 | ₹7,87,068.29 |
| 1.9 | Chequerred precast cement concrete tiles 22mm thick in footpath and courtyard, jointed with neat cement slurry mixed with pigment to match the shade of the tiles, including rubbing, cleaning and curing complete, on 20 mm thick bed of cement mortar 1:4 ( 1 cement : 4 coarse sand) . 11.29.3 Dark shade using ordinary cement and fixing the edges with 4 inch concrete for will be provided separately. | 446.1 | Sqm | 791.53 | ₹3,53,101.53 |
| 2 | Providing and laying at or near ground level factory made kerb stone of M-25 grade cement in position to the required line, level and curvature jointed with cement mortar 1:3 (1 cement: 3 coarse sand) including making joints with or without grooves (thickness of the joints except at sharp curve shall not to be more than 5mm) including making drainage opening wherever required complete etc. as per direction of Engineer-incharge (length of finished kerb edging shall be measured for payment). (Precast C.C. kerb stone shall be approved by Engineer-in-charge) | 11.33 | CUM | 7,507.14 | ₹85,055.9 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.11 MB
BOQ_1109931.xls
BOQ • 0.27 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .