Tender Value
₹15 L
EMD Value
₹15,000
Closing Date
15 Feb 2024, 3:00 pmClosed
Excecutive Officer Ponmanai Town Panchayat Office
Ponmanai Town Panchayat Office Vendelicode
Widening of existing damaged BT road at Eenchacode Sahaya Matha Church to Rajeev Gandhi statue in Ponmanai Town Panchayat
2024_DTP_416326_1
123/2023/A1
Open Tender
Civil Works
Lump-sum
50 days
Ponmanai Town Panchayat
III Class
2 documents required · 2 mandatory
₹0
₹15,000
Yes
Ponmanai Town Panchayat Office Vendelicode
26 Feb 2024
1 Feb 2024
15 Feb 2024
1 Feb 2024
15 Feb 2024
1 Feb 2024
1 Feb 2024 - 15 Feb 2024
7 Feb 2024
Amount
Earth work excavation for foundation and depositing on bank with in the initial lead of 10m and a lift of 2m in hard stiff clay, stiff block cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders etc complete complying with SS20B. TNDSS No:23&24
Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401.
Providing and laying, spreading and compacting graded stone aggregates to Wet Mix Macadam of required thick specification including premixing the materials with water at OMC in mechanical mix plant carriage of mixed material by tipper to site laying in uniform layers with pavers in Sub Base / Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause. 406 of MORTH Rev-5.
Providing and laying Prime Coat over WBM / WMM surface using 7 Kgs of Emulsion Bitumen (SS1) per 10 m² for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 502 of MORTH Rev-5.
Providing and laying Tack Coat over WBM / WMM surface (treated with primer) using 2.50 kg of Bitumen Emulsion (RS-1) per 10 m² for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc complete as per clause 503 of MORTH Rev-5.
Providing and laying 50 mm consolidated thick Dense Bituminous Macadam using 0.24 m³ of 26.50-13.20 mm, 0..25 m³ of 13.20-2.36 mm and 0.23 m³ of 2.36 mm & below and with 53.20 Kgs of VG30 / VG40 bitumen for premixing per 10 m² including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to work site, spreading the mix to uniform thickness of 50mm with paver to the specified grades and cross sections and compacted by Vibratory / Pneumatic Roller to the required density etc., including labour for attending to paver at site etc, including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher / 9 m paver finisher, Vibratory / Pneumatic rollers and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 505 MORTH Rev-5.
Providing and laying Bituminous Concrete to 30 mm thick using 0.13 m³ of 19.00-9.50 mm, 0.17 m³ of 9.50-2.36 mm and 0.26 m³ of 2.36 and below with 50.30 Kgs of VG30 / VG40 bitumen for premixing per 10 m² including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40 mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory / Pneumatic Roller to the required density etc, including labour for attending to paver to site etc, including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher / 9 m paver finisher, Vibratory / Pneumatic roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5.
T. GEORGE STEPHEN
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .