| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹471.3 CrAccepted-AOC C 4 DISTRICT CENTRE SAKET NEW DELHI 110017 | SOUTH | DELHI | 110017 | ₹471.3 Cr Quoted ₹497.5 Cr | L1 | Accepted-AOC ACCEPTED BIDDER |
| 2 | L2₹649.0 CrRejected-Finance CRYSTAL TOWER 4TH FLOOR TELIBANDHA RAIPUR | RAIPUR | RAIPUR | CHHATTISGARH | ₹649.0 Cr | L2 | Rejected-Finance NOT ELIGIBLE |
| 3 | L3₹699.0 CrRejected-Finance | ₹699.0 Cr | L3 | Rejected-Finance NOT ELIGIBLE |
| 4 | L4₹765 CrRejected-Finance | ₹765 Cr | L4 | Rejected-Finance NOT ELIGIBLE |
| Sl No | Description | Qty | Unit | M/s. Ashoka Buildcon Ltd | Rail Vikas Nigam Limited | Larsen & Toubro Limited | Ircon International Limited |
|---|---|---|---|---|---|---|---|
| 1.00“DESIGN, MANUFACTURE, SUPPLY, INSTALLATION, INTEGRATION, TESTING AND COMMISSIONING OF 220 kV RECEIVING SUBSTATION INCLUDING 220 kV, 33kV & 25kV CABLING WORK, COMPLETE 25kV OVERHEAD CATENARY SYSTEM ALONGWITH SWITCHING STATION, 33kV AUXILIARY POWER DISTRIBUTION SYSTEM INCLUDING 33/0.415 kV AUXILIARY SUB-STATION (ASS) AND COMPLETE SCADA SYSTEM, ELECTRICAL AND MECHANICAL WORKS, LIFT & ESCALATOR WORKS FOR PART OF MAIN LINE, STATIONS & KASHELI DEPOT OF MUMBAI METRO RAIL LINE 5 PROJECT OF MMRDA INCLUDING 15 YEARS OF COMPREHENSIVE MAINTENANCE AFTER 2 YEARS OF DEFECT LIABILITY AND MAINTENANCE PERIOD”. | |||||||
| 1.01 | WLC NPV COST | 1 | LS | 6,98,97,99,908 ₹699.0 Cr | 7,65,00,00,000 ₹765 Cr | 6,49,00,00,000 ₹649 Cr | 4,97,45,76,803.52 ₹497.5 Cr |
| 1.02 | Combined Transformer Losses ( Iron loss plus Copper Loss) for One 40/50 MVA Traction Transformer 220/27.5kV and One 15/20 MVA Auxiliary Transformer 220/33kV in RSS | 1 | KW | 2,79,656 ₹2.8 L | - | 210 ₹210 | 2,46,119.79 ₹2.5 L |
Tender Value
₹543 Cr
EMD Value
₹10 L
Closing Date
5 Nov 2024, 3:00 pmClosed
DIRECTOR SYSTEM
1ST FLOOR, A WING, OLD ADMINISTRATIVE BLD, MMRDA BKC, BANDRA E MUMBAI
DESIGN MANUFACTURE SUPPLY INSTALLATION INTEGRATION TESTING AND COMMISSIONING OF POWER SUPPLY AND TRACTION E AND M LIFT AND ESCALATORS INCLUDING 15 YEARS OF COMPREHENSIVE MAINTENANCE AFTER 2 YEARS OF DLMP FOR PART OF METRO LINE 5 OF MMRDA
2024_MMRDA_1018857_1
CA 239
Open Tender
Electrical Works
MUMBAI
Please refer Tender documents.
8 documents required · 8 mandatory
₹11,800
₹10 L
MMRDA BKC
14 Oct 2025
28 Feb 2024
6 Nov 2024
28 Feb 2024
5 Nov 2024
28 Feb 2024
28 Feb 2024 - 15 Apr 2024
28 Mar 2024
“DESIGN, MANUFACTURE, SUPPLY, INSTALLATION, INTEGRATION, TESTING AND COMMISSIONING OF 220 kV RECEIVING SUBSTATION INCLUDING 220 kV, 33kV & 25kV CABLING WORK, COMPLETE 25kV OVERHEAD CATENARY SYSTEM ALONGWITH SWITCHING STATION, 33kV AUXILIARY POWER DISTRIBUTION SYSTEM INCLUDING 33/0.415 kV AUXILIARY SUB-STATION (ASS) AND COMPLETE SCADA SYSTEM, ELECTRICAL AND MECHANICAL WORKS, LIFT & ESCALATOR WORKS FOR PART OF MAIN LINE, STATIONS & KASHELI DEPOT OF MUMBAI METRO RAIL LINE 5 PROJECT OF MMRDA INCLUDING 15 YEARS OF COMPREHENSIVE MAINTENANCE AFTER 2 YEARS OF DEFECT LIABILITY AND MAINTENANCE PERIOD”.
WLC NPV COST
Combined Transformer Losses ( Iron loss plus Copper Loss) for One 40/50 MVA Traction Transformer 220/27.5kV and One 15/20 MVA Auxiliary Transformer 220/33kV in RSS
stage.html
html • 0.05 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.07 MB
Download all tender documents and submit your bid