Loading…
Loading…
| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹2.1 LAdmitted-Finance | +0.00% | ₹2.1 L | L1 | Admitted-Finance |
| 2 | L2₹2.1 LAdmitted-Finance 1 3 GROUND FLOOR SITARAM GHOSH STREET SITARAM GHOSH STREET SITARAM GHOSH STREET KOLKATA WEST BENGAL 700009 UDYAM WB 10 0105152 | KOLKATA | WEST BENGAL | 700009 | +1.58% | ₹2.1 L | L2 | Admitted-Finance |
| 3 | L3₹2.2 LAdmitted-Finance 87 31 BOSE PUKUR ROAD KOLKATA 700042 | KOLKATA | WEST BENGAL | 700042 | +5.10% | ₹2.2 L | L3 | Admitted-Finance |
Tender Value
₹6 L
EMD Value
₹12,000
Closing Date
28 Feb 2026, 1:00 pmClosed
OFFICE OF EE(CIVIL)
THE KOLKATA MUNICIPAL CORPORATION 97 AND 98 GARFA MAIN ROAD
MAINTENANCE OF DRAINAGE SYSTEM BY REMOVAL OF CHOCKAGES AND RELATED WORKS ETC. AT DIFFERENT PLACES ETC. IN WARD NO -105.
2026_KMC_1012626_1
KMC/DG(C)/BR-XII/25-26
Open Tender
CIVIL WORKS
180 days
BOROUGH XII
Please refer Tender documents.
5 documents required · 5 mandatory
₹0
₹12,000
19 May 2026
21 Feb 2026
2 Mar 2026
21 Feb 2026
28 Feb 2026
21 Feb 2026
SECTION(B) - SANITARY AND DRAINAGE WORKS.(B)-(II) SOIL PIPE AND FITTINGS.(a) Original Works.(16.)Supplying, fitting and fixing with cement jointing (3:1) salt glazed stoneware pipe including excavation of earth upto 1.50 metre depth in all sorts of soil both mixed or unmixed and refilling (but excluding concreting at bottom and sides).(iii) 150 mm
SECTION(B) - SANITARY AND DRAINAGE WORKS.(B)-(II) SOIL PIPE AND FITTINGS.(a) Original Works.(16.)Supplying, fitting and fixing with cement jointing (3:1) salt glazed stoneware pipe including excavation of earth upto 1.50 metre depth in all sorts of soil both mixed or unmixed and refilling (but excluding concreting at bottom and sides).(ii) 225 mm
SINGLE BRICK FLAT SOLING OF PICKED JHAMA BRICKS INCLUDING RAMMING AND DRESSING BED TO PROPER LEVEL AND FILLING JOINTS WITH LOCAL SAND. ( REF :PWD (BLDG.)-2017, IT. NO. 1, PAGE NO.14 & 3RD CORRIGENDA ADDENDA DTD-04.06.18,P-1)
Mending potholes and depressions by stitching picked jhama bricks with one brick-on-edge laid in herring bone pattern and including necessary cushion of sand below the soling (and in between layers) including cutting the pothole area to rectangular shape with vertical edges, removing all loose materials , finishing the surface to match with adjacent areas complete as per direction. (b) One brick-on-edge laid in herring bond pattern (thickness 125mm) (Ref: PWD(Rds & brdgs)2018, It. no. 10.09(b), P-280)
CEMENT CONCRETE WITH GRADED JHAMA KHOA (30 MM SIZE) EXCLUDING SHUTTERING IN GROUND FLOOR AND FOUNDATION. (B) 1:4:8 PROPORTION ( REF :PWD (BLDG.)-2017, IT. NO. 1, PAGE NO.23 & 3RD CORRIGENDA ADDENDA DTD-04.06.18, P-9 & 10)
BUILDING WORKS (A) EARTH WORK,ANTITERMITE TREATMENT 2. Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches levelling, dressing and ramming the bottom, bailing outwater as required complete. (a) Depth of excavation not exceeding 1,500 mm.
BUILDING WORKS ( C ) Brickworks,Concrete Works etc A. BRICK WORKS 7. Brick work with 1st class bricks in cement mortar (1:4) (a) In foundation and plinth
PLASTER (TO WALL, FLOOR, CEILING ETC.) WITH SAND AND CEMENT MORTAR INCLUDING ROUNDING OFF OR CHAMFERING CORNERS AS DIRECTED AND RAKING OUT JOINTS INCLUDING THROATING, NOSING AND DRIP COURSE, SCAFFOLDING/STAGING WHERE NECESSARY (GROUND FLOOR).[EXCLUDING COST OF CHIPPING OVER CONCRETE SURFACE] (II) WITH 1:4 CEMENT MORTAR (A) 20 MM THICK PLASTER ( REF :PWD (BLDG.)-2017, IT. NO. 1, PAGE NO. 189 & 3RD CORRIGENDA ADDENDA DTD-04.06.18, P-49 & 50)
SECTION 1. ------------BUILDING WORKS (I) PLASTERING, POINTING ETC. A. ORIGINAL WORKS 1.5mm thick in wall, dado, window sill, floor etc. NOTE: Cement 0.152 cu.m per 100 sq.m
BUILDING WORKS ( C ) Brickworks,Concrete Works etc?36...Hire and labour charges for shuttering with centering and necessary staging upto 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns, lintels curved or straight including fitting, fixing and striking out after completion of works (upto roof of ground floor).(When the height of a particular floor is more than 4 m the equivalent floor height shall be taken as 4 m and extra for works beyond the initial 4 m ht. shall be allowed under 12 (e) for every 4 m or part thereof).(a) 25 mm to 30 mm thick shuttering without staging in foundation... as per decision & direction of Engineer-In-Charge.Notes:- For shuttering in shell roof, grid roof with vertical faces folded plate, arched roof the rate in 36 (a), 36 (b) & 37 (c ) of subhead B above to be increased by 100 % . For grid roof with splayed faces, rate is to be increased by 150%.
BUILDING WORKS ( C )Brickworks,Concrete Works etc.40..Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups,binders etc initial straightening and removal of loose rust (if necessary),cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction.(a) For works in foundation and upto roof of ground floor/upto 4 m.(i) Tor steel/Mild Steel.II. Other than SAIL/ TATA/RINL
ORDINARY CEMENT CONCRETE (MIX 1:1.5:3) WITH GRADED STONE CHIPS (20 MM NOMINAL SIZE) EXCLUDING SHUTTERING AND REINFORCEMENT IF ANY, IN GROUND FLOOR AS PER RELEVANT IS CODES. (I) PAKUR VARIETY ( REF :PWD (BLDG.)-2017, PAGE-26 (ITEM -10(I), CONSUMPTION CHART PG-B-60, SL-3 AND ANNEXTURE-II , FORMAT-A, 3RD CORRIGENDA & ADDENDA P-13 DTD-04.06.2018, PWD(R&B) 2018, CHAPTER-1, PG-227 I-1.03, PG-230,TABLE-I , TABLE III-2 PG-226, )
Supplying & Laying Double wall carrugated (with external annular corrugation and smooth internal wall) high density polythelene pipes conforming to IS 16098 (Part-ii):2013 having stiffness class of SN 8 with Ring stiffness not less than 8.00 KN/Sqm and impact Resistance TIR value not more than10% including necessary jointing materials for non-pressure underground drainage,sewerage & cross drainage application 150mm dia
(C) III: LABOUR RATE FOR SANITARY AND PLUMBING 4.METHOR MAZDOOR NOTE:THE ABOVE RATES ARE EXCLUSIVE OF 10 % PROFIT AND 1% LABOUR WELFARE CESS, WHICH WOULD BE ADMISSIBLE TO THE CONTRACTOR, BUT CONTRACTUAL PERCENTAGE WILL NOT BE APPLICABLE ON THE ABOVE RATES.PAGE 113 OF 124
23.Construction of Catch pit 600mmX525mm. (inside measurement) and depth of invert 1000mm. below G.L. with 250mm. thick cement brick work (1:4) over 100mm. thick jhama cement concrete (1:4:8) bed over a layer of brick flat soling including providing 100mm. thick R.C.C. slab with ordinary cement concrete (mix 1:1.5:3) with reinforcement as per standard drawing, brickon- edge flooring with 20 mm. thick cement plaster (1:4) finished fine with 1.5 mm. thick neat cement in the inside walls and invert including supplying and fixing R.C.P.C. gully grid (5 M.T.load bearing capacity) and 150 mm. dia. C.I. Syphone including cutting hard crust, excavation, dewatering, back filling and removal of spoils as per standard drawing
CONSTRUCTION OF MANHOLE WITH CHAMBER OF SIZE AS GIVEN BELOW AS PER REQUIREMENT WITHOUT SHAFT WITH CEMENT BRICK WORK (1:4) OVER 150MM. THICK JHAMA CEMENT CONC. (1:4:8) BED OVER A LAYER OF BRICK FLAT SOLING INCLUDING PROVIDING 150MM. THICK R.C.C. SLAB WITH ORDINARY CEMENT CONCRETE (MIX 1:1.5:3) WITH REINFORCEMENT AS PER STANDARD DRAWING OVER THE CHAMBER CHAMBER, BRICK ON EDGE FLOORING WITH ORDINARY CEMENT CONCRETE (MIX 1:2:4) IN THE INVERT WITH 20MM. THICK CEMENT PLASTERING (1:4) FINISHED FINE WITH NEAT CEMENT 1.50 MM. THICK IN THE INSIDE WALLS AND INVERT, INCLUDING SUPPLYING, FITTING AND FIXING R.C.P.C. MANHOLE COVER & FRAME (35 M.T. LOAD BEARING CAPACITY) WITH ORDINARY CEMENT CONCRETE (MIX 1:2:4) & C.I. STEPS (4KG. EACH) INCLUDING CUTTING HARD CRUST, EXCAVATION, DEWATERING, BACK FILLING AND REMOVAL OF SPOILS BUT EXCLUDING SHORING COMPLETE AS PER STANDARD DRAWING . (DEPTH OF INVERT SHALL BE BETWEEN 1.25 M. AND 1.80 M. BELOW G.L.) I) AVERAGE DEPTH OF INVERT 1.25 M. BELOW G.L WITH 250 MM. THICK BRICK WORK A) 150 MM TO 400 MM DIA HAVING INTERNAL SIZE (1500MMX750MM)
Construction of special inspection chamber pit of size 900mm. X 600mm. (inside measurement) without shaft with 250mm. thick cement brick work (1:4) over150mm. thick jhama cement conc. (1:4:8) bed over a layer of brick flat soling including providing 150mm. thick R.C.C. slab with ordinary cement concrete (mix 1:1.5:3) with reinforcement as per standard drawing over the chamber, brick on edge flooring with ordinary cement concrete (mix 1:2:4) in the invert with 20mm. thick cement plaster (1:4) finished fine with 1.5 mm. thick neat cement in the inside walls and invert including supplying, fitting and fixing 450mm. dia. (15 M.T.) heavy duty R.C.P.C. cover and frame (15 M.T. load-bearing capacity) with ordinary cement concrete (mix 1:2:4) and C.I. steps (4 kg. each) including cutting hard crust, excavation, dewatering, back filling and removal of spoils but excluding shoring as per standard drawing .(depth of invert between 1.15m. to 1.80m. below G.L.) i) Average depth of invert 1.15 m. below G.L.
Sub Total
Please Enable Macros to View BoQ information
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.44 MB
BOQ_2486997.xls
BOQ • 0.29 MB
FORM-105_66.pdf
Tender Documents • 0.58 MB
PREQUE.pdf
Additional Documents • 0.17 MB
Download all tender documents and submit your bid