Loading…
Loading…
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹2.9 Cr
EMD Value
₹5.8 L
Closing Date
21 Oct 2026, 6:00 pm2d left
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
ER Iqbal Ganie
Executive Engineer PWD RnB Division Banihal
Refer to BOQ
2026_PWDJK_326495_1
NIT 51 of 2026-27 Dated 29-09-2026
Open Tender
Civil Works
Percentage
540 days
Executive Engineer PWD RnB Division Banihal
Refer to SBD
2 documents required · 2 mandatory
₹6,000
Superintending Engineer PWD RnB Circle Udhampur
₹5.8 L
Superintending Engineer PWD RnB Circle Udhampur
29 Sept 2026
29 Sept 2026
22 Oct 2026
29 Sept 2026
21 Oct 2026
29 Sept 2026
12 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in bulk excavation by manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 m2 on plan) including disposal of excavated earth lead upto 50 meters and lift upto 1.5 m, as directed by Engineer-in-Charge. Ordinary Rock | 1,442.4 | cum | 940.3 | ₹13,56,288.72 |
| 2 | Earth work in excavation by manual means in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed All kind of Soil | 64.13 | cum | 479.3 | ₹30,737.51 |
| 3 | Providing and Laying of boulder filling / broken stone layer under foundation concrete | 297.78 | cum | 937.9 | ₹2,79,287.86 |
| 4 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size) | 14.25 | cum | 5,202.9 | ₹74,141.33 |
| 5 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with 1:3:6 with 30% boulder(1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) | 157.04 | cum | 4,294.89 | ₹6,74,469.53 |
| 6 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) | 30.09 | cum | 5,733.6 | ₹1,72,524.02 |
| 7 | Providing and laying in position machine batched and machine mixed design mix M-30 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer-incharge All work upto plinth level. | 292 | cum | 8,119.9 | ₹23,71,010.8 |
| 8 | Dry random rubble masonry with hard stone in foundation and plinth: Without bond stone | 203.37 | cum | 2,793.8 | ₹5,68,175.11 |
| 9 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead upto 50 m and lift upto 1.5 m. | 102.6 | cum | 218.4 | ₹22,407.84 |
| 10 | Providing and laying in position machine batched and machine mixed design mix M-30 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer-incharge All work above plinth level upto floor V level | 63.14 | cum | 9,510.85 | ₹6,00,515.07 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.14 MB
BOQ_1104416.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .