| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹5.4 CrAccepted-AOC | ₹5.4 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹6.0 Cr+₹63.7 L (11.8%)Rejected-Finance GRAM NANEHA ASHA TEHSIL DEVBAND DISTRICT SAHARANPUR MOBILE 9927733433 | ₹6.0 Cr+₹63.7 L (11.8%) | L2 | Rejected-Finance L2 |
| 3 | L3₹6.1 Cr+₹68.7 L (12.8%)Rejected-Finance SHASTRI NAGAR SAHARANPUR | SAHARANPUR | UTTAR PRADESH | 247001 | ₹6.1 Cr+₹68.7 L (12.8%) | L3 | Rejected-Finance L3 |
| 4 | L4₹6.1 Cr+₹76.9 L (14.3%)Rejected-Finance | ₹6.1 Cr+₹76.9 L (14.3%) | L4 | Rejected-Finance L4 |
| 5 | L5₹6.6 Cr+₹1.2 Cr (23.2%)Rejected-Finance | ₹6.6 Cr+₹1.2 Cr (23.2%) | L5 | Rejected-Finance L5 |
Tender Value
₹7.4 Cr
EMD Value
₹14.8 L
Closing Date
18 Oct 2023, 4:00 pmClosed
SE PWD SAHARANPUR
SE PWD SAHARANPUR
Construction work of four-lane road from two-lane road from highway bypass to Civil Enclave Terminal (O.D.R.) in Saharanpur district.
2023_CEMRT_849335_1
6176/104M-S/2023 Date 11-09-2023
Open Tender
Civil Works
Item Rate
180 days
saharanpur
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,714
₹14.8 L
Yes
se office pwd saharanpur
17 Nov 2023
11 Oct 2023
18 Oct 2023
11 Oct 2023
18 Oct 2023
11 Oct 2023
13 Oct 2023
Amount
Excavation for road way in soil by mechanical means including cutting and pushing the earth to site of embankment upto a distance of 100 metres (average lead50 metres), including trimming bottom and side slopes in accordance with requirements of lines, grades and cross sections. as per Morth Specification No. 301, Sr.No.-3.3 (In widening )
Construction of embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2. (E/W Carted For 2Km. lead)
Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401 (In widening )Two Coat)
Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. As per MORTH Specification clause-406 (Two Coat)
Providing and applying primer coat with bitumen emulsion (SS) on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means.
Providing and applying Tack coat with bitumen VG-10 on prepared primed surface including cleaning of road surface and spraying Tack Coat at the rate of 0.25kg/ sqm. using mechanical means. as per MORTH Specification clause-503
Providing and laying dense graded bituminous macadam with 100TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder V.G.-30 @ 4.50 per cent by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 507 complete in all respects.
Providing and laying bituminous concrete with 100-120 TPH batch type hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 to 5.6 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 509 complete in all respects
Cement Concrete with 4 cm gauge approved stone ballast, coarse sand & cement in proportion of 8:4:1 Including cost of all material, labour, T&P, labour cess, royality and all taxes. required for proper completion of the work. As per S.I. No. 281
Cement Concrete with 2 cm gauge approved stone ballast, coarse sand & cement in proportion of 4:2:1 Including cost of all material, labour, T&P, labour cess, royality and all taxes. required for proper completion of the work. As per S.I. No. 279(a)
M - 150 Brick work in 1:3 (one cement & three coarse sand) mortar in foundation & plinth Including cost of all material, labour, T&P, labour cess, royality and all taxes complete. required for propor complition of the work S.I. No. 307
Supply and fixing of 1000 mm dia NP3 type Hume Pipe S&S in position including labour and T&P etc. required for proper completion of work.
Sturck pointing with cement mortar consisting of 1 part cement & 2 part of fine sand of 1.25 fineness modulus S.I.No. 574 Including cost of all material, labour, T&P, labour cess, royality and all taxes complete. S.I. 574
12 cm thick plaster with cement & approved coarse sand in 1:4 over brick work minimum thickness not be less than 1 cm Including cost of all material, labour, T&P, labour cess, royality and all taxes complete. required for propor complition of the work S.I. No. 584a
Supply & Fixing of 350 mm. Dia NP-3 Hume pipe
R.C.C. Work with cement approved coarse sand & 2 cm gauge approved stone grit in proportions of 1:1.5:3 in lintels of door & windows excluding supply of reinforcement and its bending, but including its fixing and binding the same with 24 B.W. G.G.I., binding wire and including necessary centering and shuttering etc. and supply of all materials labour, Tools & plants etc. required for proper completion of the work, including cost of binding wire. The rate excludes making of drip course which shall be paid extra. SI No. 284(a)
M.S. (tor steel or plain) in Plain work such as R.C.C. or R.B. work including bending for proper shape and including supply of steel & its wastage, bend hooks, and authorized overlapping shall be measured and including cost of binding wire. SI.No. 504
Construction of cement concrete kerb with top and bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade on M-15 grade foundation 150 mm thick, foundation having 50 mm projection beyond kerb stone, kerb stone laid with kerb laying machine, foundation concrete laid manually, all complete as per clause 409
amit kumar contractor
SHREE TIRUPATI CONSTRUCTION
SINEWY CONSTRUCTIONS PVT. LTD.
RCC Developers ltd.
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .