Tender Value
Refer Docs
EMD Value
₹5,000
Closing Date
22 Sept 2020, 5:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
SE ETC MEERUT
130 D PAARESHAN BHAWAN VICTORIA PARK MEERUT
WORK TENDER
2020_UPTCL_510507_1
T-85/20-21/ETC/MT SHORT TERM
Open Tender
Electrical Works
Item Rate
45 days
BARAUT
Please refer Tender documents.
2 documents required · 2 mandatory
₹590
SE ETC MEERUT
₹5,000
23 Sept 2020
11 Sept 2020
23 Sept 2020
11 Sept 2020
22 Sept 2020
11 Sept 2020
90 days
Amount
Partly drain out the transformer oil from tank, opening of electrical connection earthing, jumpering etc.
Opening of jumpers of 40 MVA transformer, Cutting of earthing strip and opening of electrical connection.
Complete, dismantling of 40 MVA T/F by opening of radiator, conservator tank, bushing, marshaling box, cooling fans, etc at 132 KV S/S Chhaprauli.
Shifting/ Dragging of 40 MVA T/F from plinth to near open space. Distance about 20 Mtr. Including turning of main tank of required at 132KV Sub-Station Chhaprauli.
Removing of HV side LAs and its structure at 132 KV S/S Chhaprauli and erection of these LAs with structure after installation of 63 MVA T/F including earthing etc.
(a) Additional shifting 1 Job for every 5 Mtr.
Packing of bushing of transformer in 40 MVA T/F Caret.
Dragging of 63 MVA T/F Main tank from unloading site to T/F Plinth at 132 KV S/S Chhaprauli -Approx distance -20 Mtr.
(a) Additional shifting 1 Job for every 5 Mtr.
Complete, erection of 63 MVA T/F by erection of radiator, conservator tank, bushing with its turrets (if available) connecting of all oil pipe line, erection of cooling fans, making control cables connection, bucholz relay etc. for completing the work, topping of T/F oil and final oil filling in tank, radiator, conservator tank and all other associates work for completion of work.
Earthing of main tank of 63 MVA T/F by using M.S. flat 50X6 / 75X10 mm size, its jointing with already laid earth mat for its earthing work.
Placement of new RTCC panel of this new 63 MVA T/F in control room at 132 KV S/S Chhaprauli including its Termination & fitting and laying of control cable if required as per site requirement and its connections.
Carriage of 20/25 KL empty T/F oil tank for the centrifuging of T/F oil where it is available with in distance of 50 Km approx.
Centrifuging of complete T/F oil in T/F by connecting centrifuging pipes circulating the T/F oil through PVT. centrifuging machine and taking the BDV value of the oil periodically till the required value is achieved.( approx. 25 KL)
Jumpering of T/F from HV with single Moose/Zebra/ Panther and LV side with double zebra/Moose/Panther complete up to 33 KV main bus.
SUN ENGINEERING WORKS
Gupta Elect and Engg Works
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart shows the information on this page on a best-effort basis and does not guarantee that it is accurate, complete or current. Check it against the buyer's official notice and documents before you act on it; the official record prevails. TenderKart is not liable for any loss or claim arising from the use of this information. If you notice any error or omission, please let us know at .