| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹13.4 LAccepted-Finance | L1 | Accepted-Finance L1 | |
| 2 | L2₹14.5 L+₹1.0 L (7.78%)Accepted-Finance 52 A CUDDALORE ROAD VRIDDHACHALAM 606 001 CUDDALORE DIST | VRIDDHACHALAM | CUDDALORE | TAMIL NADU | 606001 | L2 | Accepted-Finance L2 |
Tender Value
Refer Docs
EMD Value
₹14,900
Closing Date
24 Jun 2021, 3:00 pmClosed
SE Operation Trichy
Superintending Engineer, Operation circle, TANTRANSCO, 110 KV SS Campus, Trichy-01.
AMC for the existing EHT 230KV and 110KV EHT lines in Aduthurai Lines Section of Kumbakonam Operation Division
2021_EB_202497_1
SEOTRY06202122AMC04
Open Tender
Electrical and Maintenance Works
Works
240 days
Kumbakonam
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹14,900
Yes
13 Jul 2021
12 Jun 2021
25 Jun 2021
12 Jun 2021
24 Jun 2021
12 Jun 2021
Amount
Labour Charges for
Conducting periodical line patrol & checking tower members, insulators, jumpers, hardware fittings & all other accessires, and identifying the weak spots to carry out the rectification works periodically by Ground line patrol when the line is in energised condition including all labour, lead, lift, etc., complete, as per the instructions of the Engineer in charge of the line.
Conducting special line patrol for tripping & checking insulators, jumpers, hardware fittings & all other accessires & identifying the weak spots to carry out the rectification works by availing Line Clear including all labour lead,lift,etc., complete, as per the instructions of the Engineer in charge of the line.
Conducting special line patrol for breakdown & checking insulators, jumpers, hardware fittings & all other accessires by climbing the towers & identifying the weak spots to carry out the rectification works by availing Line Clear including all labour, lead, lift, etc., complete, as per the instructions of the Engineer in charge of the line.
Conducting Pre monsoon checking of tower members, insulators, jumpers, hardware fittings & all other accessires by climbing the towers & identifying the weak spots to carry out the rectification works periodically by availing Line Clear including all labour, lead, lift, transport etc., complete, as per the instructions of the Engineer in charge of the line.
Clearing Heavy jungle .
Clearing light jungle .
Clearing Scrub jungle .
Uprooting and Removing large palamyarh/cocunut stumps.
Uprooting and Removing small palamyarh/cocunut stumps.
Clearing of Jouliflora without uprooting.
Tree cutting with cost of all labour,lead,lift for all kind of trees etc.,complete.
PCC (1:2:4) using 40mm HBG stone for Muffing & Coping with form work including cost of all materials,curing, lead,lift,etc., complete
Plastering with CM 1:3, 12mm thick for coping portion of tower leg including cost of all materials, labour, lead, lift, curing etc. complete
Replacment of 14 units of tension insulators with fittings, including cost of all , labour, lead,lift,etc., complete as per standard specification.
Replacment of 13 units of tension insulators with fittings, including cost of all , labour, lead,lift,etc., complete as per standard specification.
Replacment of 8 units of tension insulators with fittings, including cost of all , labour, lead,lift,etc., complete as per standard specification.
Replacment of 7 units of tension insulators with fittings, including cost of all , labour, lead,lift,etc., complete as per standard specification.
Providing mid span joints for Zebra conductor by availing LC including charges for lowering the conductor, providing jointing & re-stringing with all labour, lead, lift etc., complete as directed by the Engineer at site.
Providing mid span joints for Panther conductor by availing LC including charges for lowering the conductor, providing jointing & re-stringing with all labour, lead, lift etc., complete as directed by the Engineer at site.
Rectifying/Replacing the defective 230 kV jumpers which have been identified by the patrolling gang & providing new jumpers including charges for providing temporary earthing at works spot making arrangements at towers for rectification/ replacement of defective jumpers with new jumbers, removing temporary earthing from works spot after completion of works with all labour, lead. lift,etc., complete, as per the instructions of the Engineer in charge of the line.
Rectifying/Replacing the defective 110 kV jumpers which have been identified by the patrolling gang & providing new jumpers including charges for providing temporary earthing at works spot making arrangements at towers for rectification/ replacement of defective jumpers with new jumbers, removing temporary earthing from works spot after completion of works with all labour, lead. lift,etc., complete, as per the instructions of the Engineer in charge of the line.
Providing 230 kV Repair sleeve for conductor by availing LC including charges for lowering the conductor, providing jointing & re-stringing complete, as per the instructions of the Engineer in charge of the line.
Providing 110 kV Repair sleeve for conductor by availing LC including charges for lowering the conductor, providing jointing & re-stringing complete, as per the instructions of the Engineer in charge of the line.
ZIYAVUDEEN
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .