| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹18.5 CrAccepted-AOC | ₹18.5 Cr Quoted ₹20.9 Cr | L1 | Accepted-AOC Accepted |
| 2 | L2₹21.0 CrRejected-Finance 1ST 2ND FLOOR PLOT NO 13 C 13 3 RAMA ROAD SIDE INDUSTRIAL AREA NAJAFGARH ROAD DELHI 110015 INDIA | WEST | DELHI | 110015 | ₹21.0 Cr | L2 | Rejected-Finance L2 Bidder |
Tender Value
₹26.6 Cr
EMD Value
₹44.8 L
Closing Date
27 Nov 2023, 6:00 pmClosed
Sr. Manager (EE)
O/o ED Engg., ER and NER, Old RD Building, Safdarjung Airport, New Delhi-110003
SITC of Smart Visual Docking Guidance System (SVDGS) at Various Airports
2023_AAI_170631_1
AAI/CHQ/ENGG.E/ER/SVDGS/2023
Open Tender
Electrical Works
180 days
Various Airports as per Tender document
As per Tender Document
39 documents required · 39 mandatory
₹5,900
₹44.8 L
Yes
20 Feb 2024
13 Oct 2023
4 Dec 2023
14 Oct 2023
27 Nov 2023
3 Nov 2023
14 Oct 2023 - 25 Oct 2023
Amount
Design, Manufacture and Supply of Smart Visual Docking Guidance System (SVDGS) for azimuth Aircraft for precision parking complying to latest ICAO requirement complete including Manual Switching Board, the system shall have ability to identify the incoming aircraft, complete in all respect as required and as per technical specifications. (Refer SCC, Appendix - A).
Installation, Testing & Commissioning of Smart Visual Docking Guidance System (SVDGS) as mentioned in Item No. 1 complete as required. Job also includes Supply & Laying of Powder coated MS pole suitable for mounting SVDGS and other accessories including mounting of operator panel (manual switching board) in IP65 enclosure, Pole foundation with RCC 1:2:4 concrete with suitable steel foundation bolts along with nuts, washers, anchor plate etc. complete, supply & laying of CAT 6 cable from switch to each SVDGS, Operator panel & other locations as required, including, connection, etc. to make the system fully functional & complying to latest ICAO Guidelines. (Refer SCC, Appendix - A)
Design, Manufacture and Supply of Gate Operating System (GOS) along with networking infrastructure like server, switches, router with application software , to give BLOCK ON / BLOCK OFF or CHOCK ON / CHOCK OFF times for SVDGS and complete Departure/ Arrival information Time Status of SVDGS in real time Status of aircraft docking in real time Docking event log including error codes Stand Number Aircraft type in IATA code GOS Functionality as specified, including supply of Industrial type Workstation for Gate Operating System 01 no. main & 01 no. redundant system with server including connection to SVDGS consisting of Ethernet switch, Ethernet Router, industrial ethernet switch, software, printer and suitable size UPS etc. complete as required and as per technical specifications. (Refer SCC, Appendix - A)
Installation, Testing & Commissioning of Gate Operating System (GOS) along with networking infrastructure like server, switches, router with application software i/c all the necessary connections inter connections (as mentioned in item no. 3), providing necessary booster as per site requirement for successfull commissioning of SVDGS & GOS, installation of Industrial type Workstation for Gate Operating System 01 no. main & 01 no. redundant system with server including connection to SVDGS consisting of monitor Ethernet switch, Ethernet Router, industrial ethernet switch, software, printer and suitable size UPS etc. complete as required. (Refer SCC, Appendix - A)
SITC of LED Sign Board for stand number visible from required directions and co ordinates of stand visible from front as per ICAO Annex.14 (legends as approved by Engineer-in-Charge) made out of anodized 2mm thick Aluminium frame with suitable angle support with 1.5MM thick Al. backcover, 4 MM thick polycarbonate sheet with glare free face, the letter & symbol should be screen printed on inside of sign face made of self adhesive film of 3M applied on the inside face with required colouring, suitable arrangement shall be made for water tightness & locking arrangement including installation on the existing SVDGS pole. Signboard shall be uniformly internally illuminated with LED lights to achieve illumination level to be fed power supply from nearby SVDGS pole including necessary wiring etc. complete as required and as per specifications.
SITC of 1 KVA online UPS with 30 minute backup i/c interlinks, SMF battery & rack suitable for single phase input supply, online double conversion type, LCD Display and capable for producing 230V, 50Hz, single phase AC output supply complete as required and as per specifications (to be installed in enclosure mentioned above)
Annual Comprehensive Maintenance Contract for Smart Visual Docking Guidance Systems (SVDGS) and all associated equipments for satisfactory maintenance of the system by providing required spares and accessories, tools etc. and attending to complaints/ faults/ breakdowns and taking rectification action, ensuring serviceability / satisfactory working condition of the system, maintenance of records / documentation including providing 04 nos. trained skilled persons (1 nos. for each Airport as specified in SCC, Appendix-A) in general shift for daily preventive maintenance and to receive complaints etc. as per the detailed specifications, terms and conditions complete as required.
1st Year (After Defect Liability Period of 02 Years).
2nd Year @ 1.76% escalation on 1st year (After Defect Liability Period of 02 Years).
3rd Year @ 3.96% escalation on 1st year (After Defect Liability Period of 02 Years).
4th Year@ 6.17% escalation on 1st year (After Defect Liability Period of 02 Years).
5th Year @ 8.37% escalation on 1st year (After Defect Liability Period of 02 Years).
Annual Comprehensive Maintenance Contract for Smart Visual Docking Guidance Systems (SVDGS) and all associated equipments for satisfactory maintenance of the system by providing required spares and accessories, tools etc. and attending to complaints/ faults/ breakdowns and taking rectification action, ensuring serviceability / satisfactory working condition of the system as per the detailed specifications, terms and conditions complete as required.
1st Year (After Defect Liability Period of 02 Years).
2nd Year @ 1.76% escalation on 1st year (After Defect Liability Period of 02 Years).
3rd Year @ 3.96% escalation on 1st year (After Defect Liability Period of 02 Years).
4th Year@ 6.17% escalation on 1st year (After Defect Liability Period of 02 Years).
5th Year @ 8.37% escalation on 1st year (After Defect Liability Period of 02 Years).
Annual Comprehensive Maintenance Contract for Gate Operating System (GOS) along with networking infrastructure like server, switches, router with application software and all associated equipments for satisfactory maintenance of the system by providing required spares and accessories, tools etc. and attending to complaints / faults / breakdowns and taking rectification action, ensuring serviceability / satisfactory working condition of the system, maintenance of records / documentation including providing 08 no. trained skilled person (01 no. for each Airport as specified in SCC, Appendix-A ) in general shift for daily preventive maintenance and to receive complaints etc. as per the detailed specifications, terms and conditions complete as required.
1st Year (After Defect Liability Period of 02 Years).
2nd Year @ 1.76% escalation on 1st year (After Defect Liability Period of 02 Years).
3rd Year @ 3.96% escalation on 1st year (After Defect Liability Period of 02 Years).
4th Year@ 6.17% escalation on 1st year (After Defect Liability Period of 02 Years).
5th Year @ 8.37% escalation on 1st year (After Defect Liability Period of 02 Years).
Note 1: Rate quoted shall be inclusive of any taxes, duties, cess, fee, royalty charges etc. levied under any statute but exclusive of GST. Goods & Services Tax (GST) shall be paid to the contractor for any taxable supply / services / works against a valid tax invoice as per terms and conditions of the contract. 2. For further detail of BOQ please refer tender document.
Bidder Name
Amount in Words
Inxee Systems Private Limited
Vardhman Airport Solutions Pvt Ltd
Vardhman Airport Solutions Pvt Ltd
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid