Tender Value
₹30.9 Cr
EMD Value
₹30.9 L
Closing Date
29 Sept 2026, 5:00 pmDue tomorrow
Chief Engineer, Bridges-I, Odisha
Nirman Soudha, O/o EIC (Civil), Odisha, Bhubaneswar
Improvement such as widening and strengthening of Balimi Badandha Odapada road from Ch.0/000km to 18/923km in the District of Dhenkanal for the year 2026-27
2026_EICCL_139949_1
CE-BRIDGES-11/ 2026-27
Open Tender
Civil Works - Roads
Percentage
485 days
in the District of Dhenkanal
Please refer Tender documents.
4 documents required · 4 mandatory
₹10,000
₹30.9 L
Yes
12 Sept 2026
12 Sept 2026
30 Sept 2026
12 Sept 2026
29 Sept 2026
12 Sept 2026
12 Sept 2026 - 25 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness. as per approved Drawing & Technical Specifications and as per Clause-201 of MoRT&H Specifications for Road & Bridge works (5th Revision). | 1,07,730 | Sqm | 8.63 | ₹9,29,709.9 |
| 2 | Excavation for road work in soil with hydraulic excavator of 0.9cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes in accordance with requirements of lines, grades and cross sections and transporting to the embankment locations with all lifts & leads up to 1000m.as per approved Drawing & Technical Specifications and as per Clause - 301 of MoRT&H Specifications for Road & Bridge works (5th Revision). | 4,589.69 | Cum | 93.01 | ₹4,26,887.07 |
| 3 | Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment locations with all lifts & leads up to 1000m.as per approved Drawing & Technical Specifications and as per Clause - 301 of MoRT&H Specifications for Road & Bridge works (5th Revision). | 17,703.92 | cum | 74.85 | ₹13,25,138.41 |
| 4 | Scarifying and removing the existing bituminous road surface to the required depth as per approved drawing and technical specifications and disposal of scarified materials within all lifts and lead upto 1000mtr. complete in all respect as per Section 900, Clause 305.4.3, 305.8, 305.9.5, 501.8.3.2, 501.8.7.2 and 501.8.8.1 of MoRT&H Specifications for Road & Bridge works (5th Revision) & including cost of all labour, T&P, royalty etc complete and as per direction of Engineer-in-Charge. | 33,676.5 | Sqm | 6.06 | ₹2,04,079.59 |
| 5 | Reworking and compacting the scarified surface with Stone screened Dust passing through 2.36 mm sieve and retained on 0.075 mm sieve to line and level as per Clause 501.8.3.2 of MoRT&H Specifications for Road & Bridge works (4th Revision) including cost, conveyance, taxes, cess,royalties of all materials, cost of all labour, T&P required for the work etc. complete as per specification & direction of Engineer-in-charge | 33,676.5 | Sqm | 14.78 | ₹4,97,738.67 |
| 6 | Loosening, leveling and Compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150mm, mixed with water at OMC and then compacted by rolling so as to achieve minimum dry density as given in Table 300-2 for embankment construction as per Technical Specifications and as per Clause - 305.3.4 of MoRT&H Specifications for Road & Bridge works (5th Revision). | 5,754.29 | Cum | 36.08 | ₹2,07,614.78 |
| 7 | Construction of embankment with approved materials deposited at site from roadway cutting and excavation from foundation of CD & structures graded and compacted to meet requirement of table 300-2 as per approved Drawing & Technical Specifications and as per Clause -305 of MoRT&H Specifications for Road & Bridge works (5th Revision). | 17,371.89 | cum | 35.86 | ₹6,22,955.98 |
| 8 | Construction of embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2 as per approved Drawing & Technical Specifications and as per Clause -305 of MoRT&H Specifications for Road & Bridge works (5th Revision). | 66,482.38 | Cum | 203.91 | ₹1,35,56,422.11 |
| 9 | Providing compacted granular materials in shoulder by using moorum having required P.I. value spreading in uniform layers not exceeding 100mm in depth and compacting with smoth wheeled roller to achieve the desired density, as per approved Drawing & Technical Specifications and as per Clause - 407 of MoRT&H Specifications for Road & Bridge works (5th Revision) including cost, conveyance, royality & other taxes of materials, cost of labour, machinery, T&P etc complete.. | 4,560.42 | Cum | 827.2 | ₹37,72,379.42 |
| 10 | Turfing the slopes of embankment with compact turf grass as per approved Drawing & Technical Specifications and as per Clause - 307 of MoRT&H Specifications for Road & Bridge works (5th Revision) including cost, conveyance, royality & other taxes of materials, cost of labour, T&P etc complete. | 68,088 | Sqm | 29.16 | ₹19,85,446.08 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 3.59 MB
DTCN_BALIMI.pdf
Tender Documents • 1.16 MB
BOQ_609769.xls
BOQ • 0.74 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .