| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹3.1 CrAdmitted-Finance | L1 | Admitted-Finance | ||
| 2 | L2₹3.1 Cr+₹18,547.26 (0.06%)Admitted-Finance MOH 263 CIVIL LINES PS KOTWALI NAGAR GONDA | GONDA | UTTAR PRADESH | 271001 | L2 | Admitted-Finance |
Tender Value
₹3.1 Cr
EMD Value
₹17.5 L
Closing Date
22 Sept 2026, 12:00 pmClosed
SE GONDA CIRCLE PWD GONDA
SE GONDA CIRCLE PWD GONDA
Construction work of Kithura to Gulriha Link Road
2026_CEDPW_1183835_1
4017/2Com(B)/Gonda Circle/26-27 Dt. 25.08.26
Open Tender
Civil Works
Percentage
180 days
Balrampur
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,600
Yes
₹17.5 L
Yes
Gonda
13 Oct 2026
10 Sept 2026
22 Sept 2026
10 Sept 2026
22 Sept 2026
10 Sept 2026
10 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Construction of Embankment with approved material obtained from borrow pits with all lifts upto 1.50 m tramsporting to site, spreading, grading to required stope and compacted to meet requirement of Table 300.1 and 300.2b with lead upto 1000bm as per Technical Specification Clause 301.50 ( Excluding Royaltiy) | 9,000 | CUM | 86 | ₹7,74,000 |
| 2 | Providing, laying and sperading Material on a prepared sub grade, adding cement @2% by weight to the spread Material manually, mixing in place with rotavator and compacting with the road roller at OMC to achieve the desired unconfined compressive strength and to form a layer of sub-base | 1,027.7 | CUM | 4,800 | ₹49,32,960 |
| 3 | Providing, laying, spreading on a prepared sub base, cement@4% by weight to the spread material manully mixing in place with rotavator and compacting with the road roller at OMC to achieve the desired unconfined compressive strength and to form a layer of base. | 975 | CUM | 5,900 | ₹57,52,500 |
| 4 | Providing and applying tack coat with Bitumen (VG-10) using bitumen distributor at the rate of 0.35 kg per SQM on the surface treated with primer cleaned with Hydraulic broom as per Technical Specification Clause 503.
(Including cost of Bitumen VG-10) | 9,750 | SQM | 28 | ₹2,73,000 |
| 5 | Providing, laying and rolling of open-graded premix carpet of 20 mm average thickness composed of 13.2 mm to 5.6 mm aggregates VG 10 to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 80-100 KN static roller capacity, finished to required level and grades to be followed by seal coat of either Type C as per Technical Specification Clause 508. (Including cost of Bitumen VG-10) | 9,750 | SQM | 258 | ₹25,15,500 |
| 6 | Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type C, as per Technical Specification Clause 510.
(Including cost of Bitumen VG-10) | 9,750 | SQM | 91 | ₹8,87,250 |
| 7 | Construction of Shoulder with approved material obtained from borrow pits with all lifts upto 1.50 m tramsporting to site, spreading, grading to required stope and compacted to meet requirement of Table 300.1 and 300.2b with lead upto 1000 m as per Technical Specification Clause 301.50 ( Excluding Royaltiy) | 2,158 | CUM | 85 | ₹1,83,430 |
| 8 | Constuction of Culvert :Excavation in foundations in ordinary soil (Loam clay or sand) including lift upto 1.5m. (5fts.) and lead upto 30m. (100fts.) & including filling, watering and ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer-incharges upto a distance of 30m. (100 fts.) from the foundation trenches. As per SI No. 251 | 55.49 | CUM | 125 | ₹6,936.25 |
| 9 | Providing and laying Cement concrete 1:4:8 (1 cement : 4 fine sand : 8 graded brick aggregate 40 mm. nominal size) including supply of all materials, labour and T & P etc. required for proper completion of the work and curing complete, also including cost of formwork in foundation and floors. as per SI No. 281 | 5.76 | CUM | 4,300 | ₹24,768 |
| 10 | Providing and laying dry brick ballast (O.B.B.) under and half round of the pipe including cost of all materials T&P etc complete. | 7.96 | CUM | 1,370 | ₹10,905.2 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.71 MB
BOQ_2227692.xls
BOQ • 0.34 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .