| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.8 LAccepted-Finance 14 1 1 HRIDAY KRISHNA BANERJEE 1ST BY LANE KADAMTALA HOWRAH W B | HOWRAH | WEST BENGAL | 711101 | L1 | Accepted-Finance L1 | |
| 2 | L2₹2.9 L+₹9,032 (3.22%)Rejected-Finance | L2 | Rejected-Finance L2 | |
| 3 | L3₹2.9 L+₹9,537 (3.40%)Rejected-Finance | L3 | Rejected-Finance L3 |
Tender Value
₹2.8 L
EMD Value
₹5,700
Closing Date
29 Jan 2026, 12:00 pmClosed
EXECUTIVE ENGINEER CIVIL BR III KMC
109 M A K A SARANI KOLKATA 700054
IMPROVEMENT OF UTTARAN PASSAGE AT 16/5/D, 16/5/H/4, B.B. GHOSH SARANI AND ITS SURROUNDING AREAS IN WARD NO-14 EXCAVATED BY LAYING OF SEWER
2026_KMC_988367_1
KMC/EE-III/014/B15/25-26
Open Tender
CIVIL WORKS
Percentage
40 days
EXECUTIVE ENGINEER CIVIL BR III KMC
Please refer Tender documents.
6 documents required · 6 mandatory
₹0
₹5,700
23 Feb 2026
16 Jan 2026
31 Jan 2026
16 Jan 2026
29 Jan 2026
16 Jan 2026
Earthwork in cutting to form road section in correct profile including removal of spoil not exceeding initial lead of 50m and initial lift of 1.5m (Mode of measurement: pre works and post work
ORDINARY CEMENT CONCRETE ( MIX 1:2:4 ) WITH GRADED STONE CHIPS ( 20 MM NOMINAL SIZE) EXCLUDING SHUTTERING AND REINFORCEMENT, IF ANY, IN GROUND FLOOR AS PER RELEVANT IS CODES
Supplying, spreading and compacting Sand to required thickness, in layers not exceeding 150 mm to proper gradient and camber, inundating each layer by water and packing and ramming layer by layer to achieve desired compaction, including lighting, guarding, barricading and making adequate earthen bundh where necessary, curing with water as per direction, mending cracks and depressions by ramming wherever necessary. Note:- Add cost at site of the materials to arrive at the complete rate. The compaction factor for dry, clean sand may be taken as 0.835. (The payment is to be made on the basis of finished compacted volume). d) For Coarse Sand
BUILDING WORKS (D) Flooring A. ORIGINAL WORKS 48. Supplying & laying as per IRC-SP:063-2004 paver unit of any shade of approved quality as per relevant IS code, laid in pattern as directed in pavement, footpath, driveway (paver block only), etc including necessary underlay complete in all respect with all labour and material. [Border concrete if necessary to be paid separately]. Note: Sub-grade CBR should not be less than 5. (b) 50 mm thick interlocking designer concrete paver block M- 30 grade for non-traffic zone,buiding premises,garden,parks,domestic drive as per IS: 15658- 2006(over 20-30 mm medium sand bed on 200mm thk bound gnaular /granular base course including cost of sand for sand bed but excluding cost of base course & subgrade preparation.) (ii) Coloured Decorative
Laying of interlocking Paver Blocks as per approved design over 20-30mm th medium yellow sand bed with true to line,lavelling,proper compaction with vibrator etc. with jointing with kerb/edge should be made with Cement Concrete (1:2:4)etc. as per the direction of the Engineer-in-charge and including cost of materials,labour etc. complete
BUILDING WORKS (B) DISMANTLING, CUTTING CHASE, HOLES ETC 6. Dismantling artificial stone flooring upto 50 mm. thick by carefully chiselling without damaging the base and removing rubbish as directed within a lead of 75 m. a) In ground floor including roof.
Labour for taking out old soling edging including removing debris. (a) Single flat soling ( Ref :PWD (Bldg.)-2017, It. No. 15, Page No. 230)
Labour for laying single brick flat soling including ramming and dressing bed to proper level and filling joints with powdered earth. ( Ref :PWD (Bldg.)-2017, It. No. 2, Page No. 14)
Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand. ( Ref :PWD (Bldg.)-2017, It. No. 1, Page No.14 & 3rd Corrigenda Addenda dtd-04.06.18,P-1)
35mm thick Cement Concrete Pavement (1:2:4) in floor/footpath etc. with graded stone chips 11.2mm down,properly leveled with 3mm thick screen on top by cement slurry [email protected] cement per Sqm. Rounding off corners, chequering as required including taking necessary protective measure complete in Gr.floor/footpath.
Estimated amount
Add: 9%SGST
Add: 9%CGST
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 4.90 MB
Tendernotice_2.pdf
PDF • 5.35 MB
Tendernotice_3.pdf
PDF • 0.81 MB
Tendernotice_4.pdf
PDF • 0.70 MB
BOQ_2414488.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .