Tender Value
₹3.8 Cr
EMD Value
₹7.6 L
Closing Date
10 Nov 2022, 3:00 pmClosed
Additional collector (Development)
2nd Floor, DRDA Building, Nagapattinam
PMGSY III 2021-22 Batch I Nagapattinam district, Upgradation of road at Kilvelur block Package No TN-09-402
2022_RDTN_121583_1
TN9402
Open Tender
Civil Works - Roads
Piece-work
180 days
Nagapattinam
As seen in the tender notice
10 documents required · 10 mandatory
₹0
₹7.6 L
Yes
2nd Floor, DRDA Building, Nagapattinam
15 Dec 2022
26 Oct 2022
10 Nov 2022
26 Oct 2022
10 Nov 2022
26 Oct 2022
26 Oct 2022 - 31 Oct 2022
1 Nov 2022
Amount
01.Upgrading the road from Keralanthan Mudithalam sigar Nagalur Melpathi Hc Road Road km 0/0 - 3/176 and 5/176-5/976 in Kilvelurl Block
Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per Technical Specification Clause 201. ' in Km. 0/000 - 3/176 - 5/176 - 5/976
Scarifying the existing bituminous road surface to a depth of 150 mm and disposal of scarified material with a lift upto 3 m and lead upto 1000 m as per Technical Specification Clause 301.4. ' in Km. 0/000 - 3/176 - 5/176 - 5/976
Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross-sections, and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m as per Technical Specification Clause 302.3 ' in Km. 0/000 - 3/176 - 5/176 - 5/976
Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause 301.5 (Filling with Cut Earth) ' in Km. 0/000 - 3/176 - 5/176 - 5/976
Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1.( Carted Earth) ' in Km. 0/000 - 3/176 - 5/176 - 5/976
Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause 301.5 (Gravel shoulder)
Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with three wheel 80-100 kN static roller capacity to achieve the desired density, complete as per Technical Specification Clause 402 Grading III
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 2 as per Technical Specification Clause 405. (Grading II)
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 2 as per Technical Specification Clause 405. (Grading II)
Providing, laying and spreading soil on a prepared sub-base, pulverising, adding the designed quantity of cement to the spread soil, mixing in place with rotavator, grading with the motor grader and compacting with the road roller at OMC to achieve the desired 7 days unconfined compressive strength of 2.76 Mpa and to form a layer of base as per Technical Specification Clause 404. 8 % { C B T }
Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502
Providing and laying surface dressing as wearing course consisting of a layer of bituminous binder laid on the prepared surface, followed by a cover of crushed stone aggregates of specified size and rolling with three wheel 80-100 kN static roller including cleaning the road surface as per Technical Specification Clause 507. {using mechanical means Nominal chipping size 13.2mm}
Providing and laying surface dressing as wearing course consisting of a layer of bituminous binder laid on the prepared surface, followed by a cover of crushed stone aggregates of specified size and rolling with three wheel 80-100 kN static roller including cleaning the road surface as per Technical Specification Clause 507. {using mechanical means Nominal chipping size 9.50mm}
Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign as per IRC:67 made of encapsulated lens type reflective sheeding vide Clause 1701.2.3 fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground levels as per drawings and Technical Specification Clause 801
Logo board
Sign board
Circular Board
Octagonal Board
Citizen board
Name board
Maintanance board
Provision for Kilometre Stones
Provision for Hectametre Stones
Construction of 1.5 m RCC Slab culvert of Keralanthan Mudithalam to Sigar Nagalur Melpathi Hc road @ Ch. 0/020, 0/225, 0/700
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
Cement concrete 1 : 2.5 : 5 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1 : 2 : 4 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. (BELOW SILL)
Cement concrete 1 : 2 : 4 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. (ABOVE SILL)
Cement concrete 1 : 2 : 4 mix using 20mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1:1.5:3 using 20mm ISS HBG metal for all RCC item of works excluding cost of Rein forcement and fabricating charges, centering and shuttering but including curing and shall be finished smooth with cement mortar 1:3, 12mm thick. and with kraft paper without claiming extra as directed by the departmental officers complete complying with standard specifications.
Supplying and Fabricating and placing in position MS steel or Ribbed Tor Steel for all Reinforced Cement Concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.(MS rod or RTS bar will be supplied departmentally at section stores and cost will be recoverd at issue rate). the binding wire shall supplied by the contactor.
Providing and fixing 6mm Bitumen felt for expansion joint Between Dirtwall &Deck slab
Providing and fixing Tar Paper for bearing Between Bed Block & Deck slab
Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 614, 709, 1204.3.7
Gravel filling between body wall including cost and conveyance of gravel, labour for filling, watering and compacting etc complete complying with standard specification and as directed by the departmental officer.
Construction of 1.5 m RCC Slab culvert of Keralanthan Mudithalam to Sigar Nagalur Melpathi Hc road @ Ch. 1/582
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
Cement concrete 1 : 2.5 : 5 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1 : 2 : 4 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. (BELOW SILL)
Cement concrete 1 : 2.: 4 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1 : 2 : 4 mix using 20mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1:1.5:3 using 20mm ISS HBG metal for all RCC item of works excluding cost of Rein forcement and fabricating charges, centering and shuttering but including curing and shall be finished smooth with cement mortar 1:3, 12mm thick. and with kraft paper without claiming extra as directed by the departmental officers complete complying with standard specifications.
Supplying and Fabricating and placing in position MS steel or Ribbed Tor Steel for all Reinforced Cement Concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.(MS rod or RTS bar will be supplied departmentally at section stores and cost will be recoverd at issue rate). the binding wire shall supplied by the contactor.
Providing and fixing 6mm Bitumen felt for expansion joint Between Dirtwall &Deck slab
Providing and fixing Tar Paper for bearing Between Bed Block & Deck slab
Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 614, 709, 1204.3.7
Gravel filling between body wall including cost and conveyance of gravel, labour for filling, watering and compacting etc complete complying with standard specification and as directed by the departmental officer.
Construction of 1.5 m RCC Slab culvert of Keralanthan Mudithalam to Sigar Nagalur Melpathi Hc road @ Ch. 2/110, 2/188,2/477, 2/715, 2/810
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
Cement concrete 1 : 2.5 : 5 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1 : 2 : 4 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. (BELOW SILL)
Cement concrete 1 : 2.: 4 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1 : 2 : 4 mix using 20mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1:1.5:3 using 20mm ISS HBG metal for all RCC item of works excluding cost of Rein forcement and fabricating charges, centering and shuttering but including curing and shall be finished smooth with cement mortar 1:3, 12mm thick. and with kraft paper without claiming extra as directed by the departmental officers complete complying with standard specifications.
Supplying and Fabricating and placing in position MS steel or Ribbed Tor Steel for all Reinforced Cement Concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.(MS rod or RTS bar will be supplied departmentally at section stores and cost will be recoverd at issue rate). the binding wire shall supplied by the contactor.
Providing and fixing 6mm Bitumen felt for expansion joint Between Dirtwall &Deck slab
Providing and fixing Tar Paper for bearing Between Bed Block & Deck slab
Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 614, 709, 1204.3.7
Gravel filling between body wall including cost and conveyance of gravel, labour for filling, watering and compacting etc complete complying with standard specification and as directed by the departmental officer.
Construction of 1.5 m RCC Slab culvert of Keralanthan Mudithalam to Sigar Nagalur Melpathi Hc road @ Ch. 5/181,5/453,5/500, 5/562, 5/668, 5/867
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
Cement concrete 1 : 2.5 : 5 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1 : 2 : 4 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. (BELOW SILL)
Cement concrete 1 : 2.: 4 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1 : 2 : 4 mix using 20mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1:1.5:3 using 20mm ISS HBG metal for all RCC item of works excluding cost of Rein forcement and fabricating charges, centering and shuttering but including curing and shall be finished smooth with cement mortar 1:3, 12mm thick. and with kraft paper without claiming extra as directed by the departmental officers complete complying with standard specifications.
Supplying and Fabricating and placing in position MS steel or Ribbed Tor Steel for all Reinforced Cement Concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.(MS rod or RTS bar will be supplied departmentally at section stores and cost will be recoverd at issue rate). the binding wire shall supplied by the contactor.
Providing and fixing 6mm Bitumen felt for expansion joint Between Dirtwall &Deck slab
Providing and fixing Tar Paper for bearing Between Bed Block & Deck slab
Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 614, 709, 1204.3.7
Gravel filling between body wall including cost and conveyance of gravel, labour for filling, watering and compacting etc complete complying with standard specification and as directed by the departmental officer.
Construction of 3.0 m RCC Slab culvert @ 0/930of Keralanthan Mudithalam to Sigar Nagalur Melpathi Hc road @ 0/930
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
Cement concrete 1 : 2.5 : 5 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1 : 2 : 4 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. (BELOW SILL)
Cement concrete 1 : 2 : 4 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. (ABOVE SILL)
Cement concrete 1 : 2 : 4 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Reinforce 1:1.5:3 using 20mm ISS HBG metal for all RCC item of works excluding cost of Rein forcement and fabricating charges, centering and shuttering but including curing and shall be finished smooth with cement mortar 1:3, 12mm thick. and with kraft paper without claiming extra as directed by the departmental officers complete complying with standard specifications.
Supplying and Fabricating and placing in position MS steel or Ribbed Tor Steel for all Reinforced Cement Concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.(MS rod or RTS bar will be supplied departmentally at section stores and cost will be recoverd at issue rate). the binding wire shall supplied by the contactor.
Providing and fixing 6mm Bitumen felt for expansion joint Between Dirtwall &Deck slab
Providing and fixing Tar Paper for bearing Between Bed Block & Deck slab
Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 614, 709, 1204.3.7
Gravel filling between body wall including cost and conveyance of gravel, labour for filling, watering and compacting etc complete complying with standard specification and as directed by the departmental officer.
Construction of Protective work @ Km. 0/005 - 0/077,0/153 - 0/206,0/282 - 0/376,0/398 - 0/437,0/745 - 0/811,2/053 - 2/080,5/185 - 5/272,5/415 - 5/453,5/507 - 5/655, of Keralanthan Kudithalam to Sigar Nagalur Melpathi Hc road
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
REACH :- Km 0/000 - 1/000
REACH :- Km 5/000 - 6/000
Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
REACH :- Km 0/000 - 1/000
REACH :- Km 5/000 - 6/000
Cement concrete 1 : 2.5 : 5 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
REACH :- Km 0/000 - 1/000
REACH :- Km 5/000 - 6/000
Cement concrete 1 : 2: 4 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.BELOW SILL
REACH :- Km 0/000 - 1/000
REACH :- Km 5/000 - 6/000
Cement concrete 1 : 2: 4 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.ABOVE SILL
REACH :- Km 0/000 - 1/000
REACH :- Km 5/000 - 6/000
Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 614, 709, 1204.3.7
REACH :- Km 0/000 - 1/000
REACH :- Km 5/000 - 6/000
Providing and fixing 20 mm thick compressible fibre board in expansion joint complete as per drawing and technical specifications
REACH :- Km 0/000 - 1/000
Dismantling Existing CD works @ Km. 3235 , 2175 , 1230, , 4302, 4542, 4751, 4901, 4974, 5124, of Karuppur kayathur Enankudy Vawaladi to Kattalaipuliyakudi road
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202.
Dismantling of existing structures like culverts, bridges, retaining walls and other structures comprising of brick masonry, including disposal of unserviceable material and stacking the serviceable material with all lift and lead of 1000 m as per Technical Specification Clause 202.
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202., Reinforced Cement Concrete
Five Year Maintanance
For the First Year from the date of completion of work
For the Second Year from the date of cpmpletion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
GST Amount for providing Service to Government Contract Works for the above RENEWAL & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount above this row in column "BB" for all works in this package}(Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
S.KARTHIKEYAN
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .