Loading…
Tenderkart now works inside Claude and ChatGPT: search and analyse tenders right from your chat
Loading…
Tender ID
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹20 L
EMD Value
₹40,000
Closing Date
30 Nov 2026, 6:00 pm
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
GE (AF) SIRSA
OFFICE OF GARRISON ENGINEER AF SIRSA HARYANA-125055
REPAIR MAINT OF STEEL GATES AND MISC BR WORKS FOR BPs HANGER IN TECH AREA AT AF STN SIRSA
2026_MES_798902_1
GE/SRA/T-58/2026-27
Open Tender
Miscellaneous Works
Item Rate
210 days
GE (AF) SIRSA
PLEASE REFER TENDER DOCUMENTS
9 documents required · 9 mandatory
₹500
GE (AF) SIRSA
₹40,000
Yes
16 Nov 2026
16 Nov 2026
1 Dec 2026
16 Nov 2026
30 Nov 2026
25 Nov 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1REPAIRS TO HANGAR DOORS | |||||
| 1.01 | M&L for making operational non-running existing sliding Hangar door shutter, each leaf of size exceeding 2.50 m but not exceeding 7.50 m in clear width and 7.50 m to 12.00 m in clear height, including straightening/realignment of worn-out or misaligned top and bottom rails, removal, overhauling and refixing of unserviceable/defective rollers, tightening/replacement of loose nuts and bolts, necessary welding and drilling, rectification of defective/broken locking arrangements, oiling, greasing and adjustment of rollers, wheel shafts and other moving parts, and resetting of derailed steel gate leaf on the existing rails, as required, to ensure smooth and proper functioning of the hangar door shutter, complete all as specified and directed by the Engineer-in-Charge.
NOTES:
(a) The work shall be carried out with the shutter leaf remaining in its existing opening. Taking down, dismantling or removal of the complete shutter leaf shall not form part of this item.
(b) Replacement of broken, worn-out or unserviceable parts such as nuts, bolts, rods, flat iron, angle iron, channels, rollers, wheel shafts, guide rails, ball bearings and other major components shall be measured and paid for separately under the appropriate items.
(c) All tools, plants, machinery, scaffolding, ladders, lifting/support arrangements, welding equipment and labour required for carrying out the above repairs & adjustments shall be deemed included in the quoted rate. | 34 | EACH LEAF | - | - |
| 1.02 | M&L for cleaning, greasing, oiling and adjustment of existing top hangar door rail track, measured in running metre, complete all as specified and directed, including removal of dirt/rust deposits, checking and minor adjustment of guides, brackets and pulleys, tightening of fasteners, minor welding if required, and ensuring proper alignment and smooth movement of shutters complete all as specified and directed.
NOTES:
(1) Measurement shall be in running metre of top rail track actually attended. Each individual track shall be measured separately.
(2) Item includes cleaning, greasing, oiling, minor adjustments and minor welding necessary for smooth operation.
(3) Major replacements such as rollers, ball bearings, shafts, rails or structural members shall be measured and paid separately.
(4) Rate shall be deemed to include all labour, tools, plants, scaffolding and incidental works | 150 | RM | - | - |
| 1.03 | M&L for cleaning, greasing, oiling and adjustment of existing bottom hangar door rail track, measured in running metre, complete all as specified and directed, including removal of dirt/rust deposits, checking and minor adjustment of guides and rollers, tightening of fasteners, minor welding if required, and ensuring proper alignment and smooth movement of shutters complete all as specified and directed.
NOTES:
(1) Measurement shall be in running metre of bottom rail track actually attended. Each individual track shall be measured separately.
(2) Item includes cleaning, greasing, oiling, minor adjustments and minor welding necessary for smooth operation.
(3) Major replacements such as rollers, ball bearings, shafts, rails or structural members shall be measured and paid separately.
(4) Rate shall be deemed to include all labour, tools, plants, scaffolding and incidental works. | 400 | RM | - | - |
| 1.04 | M&L for oiling, greasing, and cleaning of pulleys for each steel sliding hangar door, including:
(i) Cleaning using approved industrial cleaning agents/thinner, if required
(ii) Oiling and greasing to reduce friction
(iii) Adjustment for smooth functioning of door
NOTES:
(1) Minor consumables and routine adjustments included.
(2) T&P, scaffolding, ladders, and labour included. | 20 | EACH JOB | - | - |
| 1.05 | S&F in repairs hangar door wheel made of mild steel (IS 2062 Fe-410) of diameter not exceeding 350 mm and thickness not more than 100 mm complete all as specified and directed including:
(i) Cutting/machining of grooves for bearing and circlip
(ii) Providing and fitting high-precision wheel with locking pin
(iii) Removal of existing unserviceable wheel and fixing of new wheel complete with shaft/axle for bottom support
(iv) Greasing, minor welding and adjustment work as required
NOTES:
(1) Wheel must match or exceed the specification of the original wheel (diameter, load capacity and shaft diameter same or higher).
(2) Rate includes supply of wheel and shaft/axle, tools & plants, scaffolding and labour.
(3) Ball bearings shall be measured and paid separately. | 15 | EACH WHEEL | - | - |
| 1.06 | M&L for easing, adjusting, greasing and alignment of existing hangar door base rollers, top guide rollers and wheel shafts, carried out in situ, without taking down and refixing of the shutter/leaf complete all as specified and directed including:
(i) Opening up, dismantling and refixing of fasteners, clamps, brackets and covers, and localized gas cutting if required, for access to rollers or shafts
(ii) Providing temporary supports, jacks or props for controlled unloading of rollers for easing and adjustment
(iii) Removal, cleaning, overhauling, greasing and refixing of rollers and wheel shafts
(iv) Tightening of loose nuts, bolts and screws connected with the roller assemblies
(v) Minor welding associated with roller brackets or mountings, if required
(vi) Final alignment and ensuring smooth movement of the door on its tracks
NOTES:
(1) Minor consumables such as grease, oil, electrodes, bolts & cleaning materials are included in quoted rate.
(2) Replacement of major components such as rollers, wheel shafts, brackets or bearings shall be measured and paid separately.
(3) All tools and plants, jacks, lifting devices, scaffolding, ladders, gas cutting equipment and labour required shall be deemed included in the quoted rate.
(4) This item shall be applicable only where easing/adjustment is carried out in situ, without taking down and refixing of the shutter/leaf. The same shutter/leaf shall not be measured simultaneously under this item and under Item-01. | 25 | EACH JOB | - | - |
| 1.07 | S&F in replacement of stainless steel ball bearing of any diameter for hangar door rollers, as per existing design/specification.
NOTES: Specifications must match or exceed original. (2) T&P, scaffolding, ladders, and labour included. | 35 | EACH | - | - |
| 1.08 | S&F in repair top guide roller assembly (MS) with diameter not exceeding 300 mm and thickness 30–100 mm, including:
(i) Fixing of ball bearing and central pin
(ii) Lifting existing door for installation
(iii) Welding, greasing, and alignment of top guide for smooth shutter movement
NOTES:
(1) Roller must match or exceed specification of original.
(2) Rate includes T&P, scaffolding, labour; shaft/axle included.
(3) Ball bearings measured separately. | 12 | EACH ROLLER | - | - |
| 1.09 | GENERAL NOTES COMMONLY APPLICABLE TO ITEM NO 1.01 TO 1.08
(1) Scope Limitation :
These items cover mechanical repair, overhauling, replacement, alignment, and refixing of sliding hangar door shutters and associated mechanical components only. Electrical/motorized systems, if any, are excluded.
(2) Experienced Manpower
All works shall be executed only through skilled and experienced workmen having proven experience in handling and repairing large sliding steel hangar doors or similar heavy industrial doors.
(3) Careful Execution & Protection
All dismantling, handling, repair, welding, alignment, and re-erection works shall be carried out carefully and systematically so as not to cause any damage to existing doors, rails, structures, finishes, or embedded parts.
(4) Safety Requirements
The contractor shall strictly follow all safety precautions, including use of PPE, proper scaffolding, barricading, warning signage, and safe lifting/jacking arrangements.
(5) Tools, Plants & Machinery
All T&P, scaffolding, lifting arrangements, jacks, welding equipment, and machinery required shall be arranged by the contractor and deemed to be included in the quoted rates.
(6) Rectification of Damage
Any damage caused to hangar doors, rails, structures, or surrounding installations due to the contractor’s operations shall be made good or replaced at the contractor’s own cost.
(7) Inspection, Trial & Acceptance
After completion of repair of each door, the same shall be cleaned, lubricated, adjusted, and operated repeatedly to demonstrate smooth and safe functioning before acceptance.
(8) Quality & Workmanship Responsibility
The contractor shall remain fully responsible for the quality of workmanship and proper functioning of doors repaired under Items 1–8 during the execution period. | - | - | - | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.70 MB
BOQ_896267.xls
BOQ • 0.60 MB
GENINSTRCTIONT.pdf
Tender Documents • 1.79 MB
Tender.pdf
Tender Documents • 3.11 MB
CREDIT.pdf
Additional Documents • 0.07 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .