| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.6 LAccepted-AOC STATION ROAD P O UKHRA DIST BURDWAN PIN 713363 W B | UKHRA | BURDWAN | WEST BENGAL | 713363 | L1 | Accepted-AOC TC Recommendation | |
| 2 | L2₹1.7 L+₹6,730.72 (4.22%)Rejected-Finance PANDADESWAR BARDHAMAN 713346 WEST BENGAL INDIA | PANDAVESWAR | BARDHAMAN | WEST BENGAL | 713346 | L2 | Rejected-Finance TC Recommendation | |
| 3 | L3₹1.7 L+₹10,962.20 (6.87%)Rejected-Finance | L3 | Rejected-Finance TC Recommendation |
Tender Value
₹1.6 L
EMD Value
₹2,000
Closing Date
25 Mar 2024, 3:00 pmClosed
General Manager
Office of The General Manager Bankola Area, PIN-713363
Repairing ad maintenance of power transformers (A) 3.15 MVA 11KV 3.3KV of ESP unit (B) 2MVA 11KV 3.3KV of ESP unit 1MVA 11KV 3.3KV at sorpi unit (D) 3.15MVA 11KV 3.3KV at sorpi unit E 1MVA 11KV 550 volt at sorpi project
2024_ECL_305020_1
ECL/GM/BA/E TENDER/23-24/EnM/425 Dt. 14.03.2024
Open Tender
Electrical and Maintenance Works
Item Rate
15 days
shyamsundarpur colliery
Please refer to NIT document
5 documents required · 5 mandatory
₹2,000
8 May 2024
14 Mar 2024
26 Mar 2024
14 Mar 2024
25 Mar 2024
14 Mar 2024
14 Mar 2024 - 18 Mar 2024
Amount
Item Description/ Heading
Drain out and top up of transformer oil after overhauling
supply of dog brand gasket
Disconnection of connection lids and makng reconnection providing proper insulation
labour chargesfor removng and fitting of top cover testing commissioning etc
Dehydration and filteration of transformer
Transporting loading and unloading of filter machine tools and tackles etc to and fro
Dehydration and filteration of transformer oil of M and B make 2MVA 11KV/3.3KV transformer at ESP unit
Supplyand fitting of breather complete with silica gel connecting lever etc
Drain out and top up of transformer oil after overhauling
supply of dog brand gasket
Disconnection of connection lids and makng reconnection providing proper insulation
labour chargesfor removng and fitting of top cover testing commissioning etc
Dehydration and filteration of transformer
Dehydration filteration and topping up transformer oil of 3.15MVA 11KV/3.3KV powar transformer installed at 11KV sorpi sub station
Dehydration and filteration of transformer oil of 1MVA B make 2MVA 11KV/550 Volt transformer installed at sorpi project
Total impact of GST for the purpose of CTC
BENGAL ELECTRICAL ENTERPRISE
DUTTA ELECTRIC
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .