Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.3 LAccepted-Finance | L1 | Accepted-Finance OK | |
| 2 | L2₹2.0 L+₹69,020 (52.8%)Accepted-Finance | L2 | Accepted-Finance OK | |
| 3 | L3₹2.0 L+₹71,350 (54.6%)Accepted-Finance | L3 | Accepted-Finance OK |
Tender Value
Refer Docs
EMD Value
₹2,000
Closing Date
22 Feb 2024, 12:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
SE EDC BIJNOR
Avas Vikas Colony, Bijnor
various work on 33/11 KV S/S Under EDD-Ist, Chandpur in Anurakshan Month February, 2024
2024_PVVNL_898428_1
65/2023-24/EDC BIJNOR
Open Tender
Electrical Works
Item Rate
30 days
SE EDC BIJNOR
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,180
SE EDC BIJNOR
₹2,000
Yes
28 Feb 2024
16 Feb 2024
22 Feb 2024
16 Feb 2024
22 Feb 2024
16 Feb 2024
Amount
Removal of ACSR Dog Conductor from both side spans of damaged pole and removal of HT/LT line accessories from damaged pole
Digging of pit of damaged pole in pakka road( Hard soll) with the help of road cutter/ digging mahina Tractor etc for dismantling the pole
Digging of pit of damaged pole in kachha road (soft soll) for dismantling the damaged pole
Dismantling of damage single support pcc pole/ST pole from pit and ST pole Carringe from work site to JE Store and damaged pcc pole will be carrige from work siie to dumplng yard inccluding loading and unloading at both end
Carriage of new 8.5 mtr long pcc pole 11mtr pole from cetal store Bijnor /JE store to work site including and unloading at both end
Erection & fabrication of following support inccluding fitting of all reqiired accessories of HT/LT line as per RESPO schedulee
Single supports on pcc pole of8.5mtr long
Grouting concreting and plinth of singlee support on ST pole of 11 mtr long with cament stone ballast & coarse sand in ration of 1:3:6 complete in all respet
Layying Straighting sagging & binding of ACSR Dog conductor in both side spans of new erected pole in HT/LT line
For attending 33 kv /11kv Break down providing & replacement of damaged disc insulator and jointig of conductor and replacement of jumpers
Fixing of Disc insulator as per site requirement
Fixing of Pin insulator as per site requirement
Cutting /choping tree branches in the way of 33 kv /11 kv HT line
The following material is required to suppiied by the contractor and fixing of its materials on pole as required
Stay clamp
Stay insulator
F- Brackets
X-Arm Holding clamps
F- Clamps
Earth Clamp
Bolt and Nuts off size
Layying Straighting sagging & binding of ACSR Weasel /Rabbit /Dog conductor of Ht/LT line in different sectors & cartage of materials from JE store of PVVNL Discom with loading & unloading at both end
HT line
LT line
Re- Laying lifting stringing & proper sagging of new conductor in replace of old damage removed conductor on HT/LT line with binding jumpering etc including cartage loading &unloading from central store bijnor /JE store to site of work
ACSR Weasel Conductor HT line
ACSR Weasel Conductor L T line
Re-sagging of conductor of loose HT/LT line which includines opening of jumpers binding & re jumpereing etc complete in all respect
11 kv ( 3 wire ) line at variou place
LT line ( 3/5 wire ) at various place
Providing and fixing of bamboo phanti with the binding wire in LT line at different place
Carriage of scrap matrial from JE store to cental bijnor including safe loading and unloading at both ends
Carriage of AB cable 95/120 Sq mm from store center bijnor to work site loading and unloading at both end
Laying lifting & stringing of AB cable size 95/120 sq mm in place of dismantling damage AB and fixing of all type clamp & connecting complete in all respect
Carriage of distribution box (single phase /Three phase ) from store center bijnor to work site including safe loading and unloading at both ends
Installation of single /Three phase disttribution box on pole with providing sutibal Lt clamp and making LT lead connection complete in all respect
Bhagwat singh contractor and supplier
ANSHIKA ENTERPRISES
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .