| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹5.5 LAccepted-AOC | L1 | Accepted-AOC L1 |
Tender Value
Refer Docs
EMD Value
₹5,700
Closing Date
3 Jul 2025, 2:00 pmClosed
SE/CEDC/Metro/CBE
The Superintending Engineer/CEDC/Metro/CBE
Construction of new Compound wall at North side of the Central Stores/ Metro in Coimbatore SS premises at Tatabad, Coimbatore.
2025_EB_570681_1
Spec.No.05/2025-2026, Dt.16.06.2025
Open Tender
Civil Works
Works
60 days
SE/CEDC/Metro/CBE
Refer tender documets
2 documents required · 2 mandatory
₹0
₹5,700
22 Jul 2025
18 Jun 2025
4 Jul 2025
18 Jun 2025
3 Jul 2025
18 Jun 2025
18 Jun 2025 - 3 Jul 2025
Amount
Dismantling, Clearing away and stacking the materials for reuse of brick, Block wall including labour, lead, lift, etc., complete
Earth work excavation and depositing on bank with initial lead of 10m and initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders including labour, lead, lift, etc., complete as per standard specification
Supplying and filling with M. sand for foundation including cost of all materials, well consolidation, labour, lead,lift, etc. complete
PCC 1:3:6, using 20mm HBG metal for foundation including cost of cement, all materials, labour, curing, lead, lift, etc. complete
RCC 1:1.5:3 using 12-20mm hard machine broken granite stone for raft foundation including cost of all materials, centering, curing, labour, lead, lift, etc. complete. but excluding cost of steel reinforcement
RCC 1:1.5:3 using 12-20mm hard machine broken granite stone for columns including cost of all materials, form work, centering, curing, labour, lead, lift, etc. complete. But excluding cost of steel reinforcement. (Upto Ground Level)
RCC 1:1.5:3 using 12-20mm hard machine broken granite stone for Plinth beam for compound wall including cost of all materials, form work, centering, curing, labour, lead, lift, etc. complete. But excluding cost of steel reinforcement.
Refilling with excavated soil other than sand in foundation consolidation as per std. specn. with watering including all labour, lead, lifts.etc, complete.
Flyash Brick 230 x 110 x 75mm work in CM 1:5 for walls including cost of all materials, curing,labour, lead, lift, etc. complete.
Providing steel reinforcement with MS/RTS rods of reputed approved make for reinforced concrete works, including cost of steel MS/RTS rods, binding wire, Minor T & Ps labour charges for cutting, straightening bending as per type design drawing, placing aligning, and tying properly with all leads and lift etc., complete as per Standard Specification
Plastering with CM 1:5, 12mm thick including cost of all materials, labour, curing, lead, lift, etc. complete.
Painting the exterior walls with two coats of Distember of first class quality and of approved colour over a primer coat including cost of all materials, labour, scrapping the walls with sand paper, scaffolding, etc.,
RCC 1:2:4 using 12-20mm hard machine broken granite stone for coping, including cost of all materials, form work, centering, curing, labour, lead, lift, etc. complete. But excluding cost of steel reinforcement.
SGST to be quoted in Percentage (value alone)Ex. 9%, it should be entered as 9 only
CGST to be quoted in Percentage (value alone)Ex. 9%, it should be entered as 9 only
Inter-state GST @18% for other than Tamil Nadu supplier. If the contractor is within Tamil Nadu may be quoted as "0" only
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .