Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.1 CrAccepted-AOC | ₹2.1 Cr | L1 | Accepted-AOC Lowest Amount |
| 2 | Not Admitted-Finance | - | - | Not Admitted-Finance Not qualified for AOC |
| 3 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
| 4 | Not Admitted-Fee/PreQual/Technical 71C5A 10A PARK ROAD KEELARAMANPUTHOOR NAGERCOIL 629004 | KANNIYAKUMARI | TAMIL NADU | 629004 | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
| 5 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹2.5 Cr
EMD Value
₹2.5 L
Closing Date
27 Dec 2023, 3:00 pmClosed
Executive Officer
Verkilambi Town Panchayat
Strengthening of BT Road from Malavilai to Ottalivilai Road (Malavilai to Oorani , Kandavilagam to Ottalivilai road) in Verkilambi Town Panchayat
2023_DTP_395143_1
422/2023/A1
Open Tender
Civil Works - Roads
Works
180 days
Verkilambi Town Panchayat
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹2.5 L
15 Feb 2024
1 Dec 2023
27 Dec 2023
1 Dec 2023
27 Dec 2023
1 Dec 2023
Amount
Picking the existing BT surface to 50 mm, deep and replacing the metal fit for reuse, to bring the existing surface to camber including leveling and sectioning as directed by the Departmental officers including labour and hire charges for tools and plants and all other incidental charges etc complete as per standard specifications. as per clause 702 of MORTH Rev-5.
Providing, laying, spreading and compacting graded stone aggregates to Wet Mix Macadam for required thick specification including premixing the materials with water at OMC in mechanical mix plant carriage of mixed material by tipper to site laying in uniform layers with pavers in Sub Base / Base course on well prepared surface and compacting with vibratory roller to achieve the desired density, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc complete. as per Clause 406 of MORTH Rev-5.
Providing and laying Priming coat 7Kg / 10 m² over WMM surface using of SSI Emulsion Bitumen for 10 m² and cost Emulsion Bitumen which will be supplied and procured by the contractor himself at his own cast as per special condition appended including labour charges for preparing the surface for laying the tack coat and for applying the required quantity of bituminous by mechanical sprayer including hire and fuel for all tools and plants employed etc complete. MORTH Specifications 111,112,501,503 & 900.
Providing and laying Tack coat 2.50 Kg / 10 m² over Wet Mix Macadam surface using of RS1 Emulsion Bitumen for 10 m² and cost of Emulsion Bitumen which will be supplied and procured by the contractor himself at his own cost as per special condition appended including labour charges for preparing the surface for laying the tack coat and for applying the required quantity of bituminous by mechanical sprayer including hire and fuel for all tools and plants employed etc complete. MORTH Specifications 111,112,501,503 & 900.
Providing and laying 50 mm consolidated thick Dense Bituminous Macadam using 0.24 m³ of 26.50-13.20 mm, 0..25 m³ of 13.20-2.36 mm and 0.23 m³ of 2.36 mm & below and with 53.20 Kgs of VG30 / VG40 bitumen for premixing per 10 m² including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to work site, spreading the mix to uniform thickness of 50mm with paver to the specified grades and cross sections and compacted by Vibratory / Pneumatic Roller to the required density etc, including labour for attending to paver at site etc, including hire charges and fuel charges for 20-30 ton CMP with bitumen boiler, tipper trucks, Paver Finisher / 9 m paver finisher, Vibratory / Pneumatic rollers and all other tools and plant required, including fuel and all other incidental charges etc complete. using CMP Clause 505 MORTH Rev-5.
Providing and laying Bituminous Concrete 30 - 40 mm thick using 0.13 m³ of 19.00-9.50 mm, 0.17 m³ of 9.50-2.36 mm and 0.26 m³ of 2.36 and below with 50.30 Kgs of VG 30 / VG 40 bitumen for premixing per 10 m² including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40 mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory / Pneumatic Roller to the required density etc, including labour for attending to paver to site etc, including hire charges and fuel charges for 20-30 ton CMP with bitumen boiler, tipper trucks, Paver Finisher / 6 m paver finisher, Vibratory / Pneumatic roller and all other tools and plant required, including fuel and all other incidental charges etc complete. using CMP Clause 507 of MORTH Rev-5.
Road marking with hot applied thermoplastic compound with reflectorising glass beads on bituminous surface proving and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 Gms / m² area thickness of 2.5 mm exclusive of surface applied glass beads as per IRC: 35. The finished surface to be level uniform and free from streaks and holes. as per MORT&H specification No.803.
Earth work excavation for foundation and depositing on bank with in the initial lead of 10m and a lift of 2m in hard stiff clay, stiff block cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders etc complete complying with SS20B. TNDSS No:23&24
Cement concrete of mix 1:4:8 (one part of cement four part of sand and eight part of aggregates) using 40 mm gauge machine broken granite stone jelly for foundation including de watering if found necessary and laid in layers of not more than 15 cm thick well rammed and consolidated etc complying with standard specification. TNDSS No:28
Supplying and erecting centering to sides and soffits including supports and strutting with necessary centering for soffits upto 3 meter height using mild steel sheet of size 90 cm x 60 cm x 10 mm gauge with MS angles of size 25mm x 25mm x 3mm laid over silver oak (CW) joists of size 10cm x 6cm spaced upto 90cm c/c and casurina props or 10 cm to 13 cm dia spaced at 0.750 cm c/c complying with standard specifications. TNDSS No:30&86
Cement concrete of mix 1:3:6 (one part of cement three part of sand and six part of aggregates) using 40 mm gauge machine broken granite stone jelly for foundation including de watering if found necessary and laid in layers of not more than 15 cm thick well rammed and consolidated etc complying with standard specification. TNDSS No:24
M A I N T E N A N C E : Towards the charges for routine maintenance of the road work executed under NABARD SCHEME including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc with the periodicity for the above activities as prescribed in IRC-SP-20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost.
Clearing and Grubbing by Light Jungle removing and disposing of all materials such as bushes, shrubs, stumps, roots, grass, weeds, top organic soil not exceeding 150 mm in thickness as rubbish including all other incidental charges etc complete as per MORTH Specification 111, 112, 201.
Upkeeping 1st year (50%)
Upkeeping 2nd year (60%)
Upkeeping 3rd year (60%)
Upkeeping 4th year (60%)
Upkeeping 5th year (60%)
Earth work excavating and deposting on bank with initial lead of 10 m & initial lift of 2 m in Hard stiff clay, Stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders SS 20B for making up the berms as per clause 111, 112, 201, 202, 301 to 305 & 900 of MORTH Vth Revision (Twice in a Year)
Upkeeping 1st year (40%)
Upkeeping 2nd year (40%)
Upkeeping 3rd year (40%)
Upkeeping 4th year (40%)
Upkeeping 5th year (40%)
Tack coat - Providing and applying tack coat with Bitumen Emulsion (RS-I Type) using emulsion pressure distributor at the rate of 2Kg/m² on the prepared Bituminous / Granular surface cleaned with mechanical broom as per clause 503.
Upkeeping 4th year (3%)
Upkeeping 5th year (5%)
Bituminous Concrete - Providing and laying Bituminous Concrete 30 mm consolidated thick using 0.13 m³ of 19.00 - 9.50 mm, 0.17 m³ of 9.50 - 2.36 mm and 0.26 m³ of 2.36 mm & below with 50.30 Kgs of 60 / 70 Grade Bulk Bitumen cost and conveyance of all materials to CMP site, heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20 - 30 ton capacity, Conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40 mm with mechanical pavers to the specified grades and cross sections and compaction by Vibratory / Pneumatic rollers to the required density etc including labour for loading bitumen into bitumen tank and Metal to feeder unit, labour for attending to paver site etc including hire charges and fuel charges for 20-30 ton CMP with bitumen boiler tipper, trucks, paver Finisher / 9M, Vibrator rollers and all other tools and plants required, including all other incidental charges etc as per standard specification using CMP Clause 507 of MORTH Rev-5
Upkeeping 4th year (3%)
Upkeeping 5th year (5%)
stage.html
html • 0.05 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].