Tender Value
₹31.4 L
EMD Value
₹62,900
Closing Date
25 May 2026, 6:00 pmClosed
XEN RMC Dn.-II CAD ANTA
XEN RMC Dn.-II CAD ANTA
Excavation / Desilting, Construction of VRB/ Pipe Culvert and Gravel Roads in Drainage system in Laxmipura Distributary Section under Sub Division CAD Mangrol. (Laxmipura Section 01)
2026_CADKO_557837_1
nit 2 of 2026-27
Open Tender
Civil Works - Canal
Percentage
365 days
Mangrol
Excavation / Desilting, Construction of VRB/ Pipe Culvert and Gravel Roads in Drainage system in Laxmipura Distributary Section under Sub Division CAD Mangrol. (Laxmipura Section 01)
2 documents required · 2 mandatory
₹1,000
XEN RMC Dn.-II CAD ANTA
₹62,900
Yes
13 May 2026
10 May 2026
26 May 2026
10 May 2026
25 May 2026
10 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Cutting & clearance of jungle, bushes, shrubs Ankra/Ipomoea, Juliflora typna etc. on canal and bunds in dry/moist/slushy conditions including disposal as per instructions of the Engineer-in-charge. Cost of wood has been deducted from rates and thus will be property of contractor after cutting. (b)Thick | 2,505 | Sqm | 2.5 | ₹6,262.5 |
| 2 | Excavation including loading, unloading, disposal and dressing of excavated earth within initial lead of 50m and lift up to 1.5m including dressing of excavated area and dewatering wherever required complete in all respect in. (b) Hard/dense soil. | 8,313.2 | Cum | 79 | ₹6,56,742.8 |
| 3 | Compaction of earth or highly weathered strata (b) By mechanical equipment such as sheep foot roller/ pneumatic tyred roller/vibro compactor / vibro sheep foot compactor required as per site condition to obtain dry density of. (i) at least 95% of Standard Proctor's density | 8,243.35 | Cum | 33 | ₹2,72,030.55 |
| 4 | Centring and shuttering for slabs, beams,lintels,columns,trough with or without caps and base including proping and remove. | 28.62 | sqm | 225 | ₹6,439.5 |
| 5 | Side shuttering including propping etc. complete (to achieve finish F 2 for :(c)Retaining wall, counterfort, abutment, wing walls up stream or down- stream slope facings of dams and open faces of construction joints etc. | 193.64 | sqm | 220 | ₹42,600.8 |
| 6 | Supplying of MS reinforcement including labour charges for bending, binding and placing in position all reinforcement as per drawing including cost of binding wire and all leads and lifts using. Tor or ribbed bars(IS :1786-1985) | 1,714.16 | kg | 78 | ₹1,33,704.48 |
| 7 | Providing and Laying in position of Cement concrete Nominal mix (1:3:6) including leads of all construction materials, curing, compaction and finishing with rendering in cement sand mortar 1:3 (1 cement : 3 coarse sand) and making good the joints excluding the cost of centering, shuttering and reinforcement. Well graded crusher broken stone aggregate of maximum size upto 20 mm | 24.78 | Cum | 4,654 | ₹1,15,326.12 |
| 8 | Providing and Laying in position of Cement concrete Nominal mix (1:2:4) including leads of all construction materials, curing, compaction and finishing with rendering in cement sand mortar 1:3 (1 cement : 3 coarse sand) and making good the joints excluding the cost of centering, shuttering and reinforcement. Well graded crusher broken stone aggregate of maximum size upto 20 mm | 83.31 | Cum | 5,161 | ₹4,29,962.91 |
| 9 | Providing and Laying in position of Cement concrete Design mix M-25 including leads of all construction materials, plasticizers (if required), curing, compaction and finishing with rendering in cement sand mortar 1:3 ( 1 cement : 3 coarse sand) and making good the joints excluding the cost of centering, shuttering and reinforcement. Well graded crusher broken stone aggregate of maximum size upto(For mix design Cement content considered 420 kg/ cum of concrete) 20 mm | 22.88 | Cum | 5,975 | ₹1,36,708 |
| 10 | Extra labour charges for obstruction in laying & placing the reinforced cement concrete due to reinforcement in Columns, slabs, cantilevers projections staircases, lintels, beams, chajjas,
Retaining walls, piers, abutments, galleries, arch covers, bed plates, sluice capstan bases etc | 22.88 | Cum | 200 | ₹4,576 |
stage.html
html • 0.02 MB
cancelled_1.pdf
pdf • 0.33 MB
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.72 MB
Tendernotice_2.pdf
PDF • 0.57 MB
BOQ_993118.xls
BOQ • 0.27 MB
BOQitem1.rar
PDF • 0.39 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .