| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.9 LAccepted-AOC GALI NO 24 SURYAN NAGAR HISAR HARYANA 125005 | HISAR | HISAR | HARYANA | 125005 | ₹1.9 L | L1 | Accepted-AOC ok |
| 2 | L2₹2.0 L+₹5,936.91 (3.08%)Rejected-Finance GALI NO 5 SUNAROWALI VINOD NAGAR MILL GATE HISAR | ₹2.0 L+₹5,936.91 (3.08%) | L2 | Rejected-Finance ok |
| 3 | Rejected-Technical | - | - | Rejected-Technical Not fulfill the condition |
Tender Value
₹2.0 L
EMD Value
₹4,000
Closing Date
20 Jun 2026, 6:00 pmClosed
BHUPENDER SINGH
DIV 1 Hissar
A/mtc estimate of sewerage scheme in sector-15A, Hisar for the year 2025-2026.
2026_HBC_529403_1
20262422FB53 8B86 466D 83F5 B755BC48E4BB259HSV
Open Tender
Civil Works
Works
60 days
Hisar
Replacing and construction of RCC Slab on Sewerage Manhole at various locations in Sector 15A Hisar and all other works contingent thereto
2 documents required · 2 mandatory
₹250
Yes
₹4,000
Yes
10 Aug 2026
15 Jun 2026
22 Jun 2026
15 Jun 2026
20 Jun 2026
15 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | [6.25.1]Providing and laying in position machine batched and machine mixed design mix M-25 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer-in-charge. 1. All works up to plinth level | 18.07 | cum | 4,464 | ₹80,664.48 |
| 2 | [6.30.3]Centering and shuttering including strutting, propping etc. and removal of form for 3. Suspended floors, roofs, landings, balconies and access platform | 51.18 | Sqm | 208 | ₹10,645.44 |
| 3 | [6.33.6]Steel reinforcement for R.C.C. work, where not included in the complete rate of RCC, including straightening, cutting, bending, placing in position, binding, wastage, overlaps, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire etc. complete in all respect below plinth level Note: Reinforcement shall be measured in length including hooks, if any, separately for different diameters as actually used in work , excluding overlaps. Wastage, overlaps, couplings, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire or other methods of binding & placing shall not be measured and cost of these items shall be deemed to be included in the rates for reinforcement. 6. Thermo-Mechanically Treated bars of grade Fe-500D or more | 1,625 | Kg. | 66 | ₹1,07,250 |
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.96 MB
BOQ_608434.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .