| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹41.0 LAccepted-AOC 17 1 SANKAR COLONY PALAYAMKOTTAI TIRUNELVELI | TIRUNELVELI | TIRUNELVELI | TAMIL NADU | ₹41.0 L | L1 | Accepted-AOC L1 |
| 2 | L2₹41.7 LRejected-Finance 6 2 SIVAN NORTH CAR STREET PALAYAMKOTTAI TIRUNELVELI 2 | ₹41.7 L | L2 | Rejected-Finance L2 |
| Sl No | Description | Qty | Unit | M/S VIJAY INFRATECH L2 | MARSHAL VIGNESH & CO L1 |
|---|---|---|---|---|---|
| 1.001) Improvements of Melapillayarkulam Agragaram to B.G road Km 0/0-1/100 in Manur Block in Tirunelveli District | |||||
| 2.00 | Clearing Scrub Jungle without alignment for the widening of the formation of the road cutting of trace up to 30mm girth products the cleaning are to be stocked in such a place as ordered by the departmental officer and the ground shall be left in a perfectly clean condition. All holes of hollows whether original, existing (or) produced by digging of roots shall than be carefully filled up the earth well rammed and leveled of and the entire work completed in all respect. | 1,579.82 | sqm | 6.43 ₹10,158.24 | 6 ₹9,478.92 |
| 3.00 | Picking the existing surface to 50mm to 100mm thick including labour and hire charges for picking tools and plants and all other incidental charges etc complete as per stadard specification | 1,381.79 | sqm | 23.77 ₹32,845.15 | 23 ₹31,781.17 |
| 4.00 | Earth work excavation and depositing on bank with an intial of 10m and lift 2m in hard stiff clay, stiff black cotton, hard red earth and earth mixed with small size boulders, hard gravelly soil etc., as per SS 20A including laying and spreading in layer etc.complete. | 394.96 | cum | 142.8 ₹56,400.29 | 140 ₹55,294.40 |
| 5.00 | Collection and supply of gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS Km 0/0-1/0 | 336.52 | cum | 346.8 ₹1.2 L | 340 ₹1.1 L |
| 6.00 | Collection and supply of gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS Km 1/0 - 1/100 | 33.75 | cum | 346.8 ₹11,704.50 | 340 ₹11,475 |
| 7.00 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 125mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. | 518.18 | cum | 2,442.9 ₹12.7 L | 2,395 ₹12.4 L |
| 8.00 | Applying PRIMECOAT over WMM surface at 7.00Kg of SS-1 Bitumen Emulsion ncluding cost of bituminous emulsion which will be supplied by the department at section stores and its cost will be recovered as per special condition appended including labour charges for preparing the surface for laying tack coat and for applying required quantity of bituminous emulsion by mechanical sprayer including hire and fuel charges for all tools and plants employed etc., complete as per clause 503 of MOST specification. | 4,145.37 | sqm | 88.74 ₹3.7 L | 87 ₹3.6 L |
| 9.00 | Providing and laying Tack coat over WMM surface (Treated with Primer)using 2.50 Kg of bitumen emulsion RS-1 for 10sqm area including cost and conveyance of bituminous binder including labour charges for preparing the surface and applying the required quantity of bitumen as tack coat by bitumen sprayer | 4,156.25 | sqm | 20.81 ₹86,491.56 | 20.4 ₹84,787.50 |
| 10.00 | BITUMINOUS CONCRETE 25MM THICK USING cmp (Grade-II) Providing and laying Bituminous Concrete to 25/30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5 | 103.91 | cum | 11,666.86 ₹12.1 L | 11,438 ₹11.9 L |
Tender Value
₹49.4 L
EMD Value
₹50,000
Closing Date
19 Feb 2026, 3:00 pmClosed
Project Director
DRDA, Tirunelveli
Improvements of one road in Manur Block
2026_RDTN_651745_9
A4/4221855/2025
Open Tender
Civil Works
180 days
Tirunelveli District
As per Pre Qualification Details
5 documents required · 5 mandatory
₹0
₹50,000
22 May 2026
13 Feb 2026
19 Feb 2026
13 Feb 2026
19 Feb 2026
13 Feb 2026
1) Improvements of Melapillayarkulam Agragaram to B.G road Km 0/0-1/100 in Manur Block in Tirunelveli District
Clearing Scrub Jungle without alignment for the widening of the formation of the road cutting of trace up to 30mm girth products the cleaning are to be stocked in such a place as ordered by the departmental officer and the ground shall be left in a perfectly clean condition. All holes of hollows whether original, existing (or) produced by digging of roots shall than be carefully filled up the earth well rammed and leveled of and the entire work completed in all respect.
Picking the existing surface to 50mm to 100mm thick including labour and hire charges for picking tools and plants and all other incidental charges etc complete as per stadard specification
Earth work excavation and depositing on bank with an intial of 10m and lift 2m in hard stiff clay, stiff black cotton, hard red earth and earth mixed with small size boulders, hard gravelly soil etc., as per SS 20A including laying and spreading in layer etc.complete.
Collection and supply of gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS Km 0/0-1/0
Collection and supply of gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS Km 1/0 - 1/100
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 125mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Applying PRIMECOAT over WMM surface at 7.00Kg of SS-1 Bitumen Emulsion ncluding cost of bituminous emulsion which will be supplied by the department at section stores and its cost will be recovered as per special condition appended including labour charges for preparing the surface for laying tack coat and for applying required quantity of bituminous emulsion by mechanical sprayer including hire and fuel charges for all tools and plants employed etc., complete as per clause 503 of MOST specification.
Providing and laying Tack coat over WMM surface (Treated with Primer)using 2.50 Kg of bitumen emulsion RS-1 for 10sqm area including cost and conveyance of bituminous binder including labour charges for preparing the surface and applying the required quantity of bitumen as tack coat by bitumen sprayer
BITUMINOUS CONCRETE 25MM THICK USING cmp (Grade-II) Providing and laying Bituminous Concrete to 25/30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5
Providing Rumble Strips covered with Bituminous Concrete Bituminous 20mm high at center,250mm vide placed at 1m center to center at approved locatioons to control speed marked with white strips of road marking paint.
Provision for HM stones
Provision for KM stones
Maintenance Towards the charges for routline maintenance of the road work executed under Nabard including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRC-SP-20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost
For the First Year from the date of completion of work
For the Second Year from the date of cpmpletion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.23 MB
BOQ_788133.xls
BOQ • 0.29 MB
Technicalbid09.pdf
Tender Documents • 0.41 MB
Pricebid09.pdf
Additional Documents • 0.29 MB
Download all tender documents and submit your bid