| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹36.5 LAccepted-AOC | L1 | Accepted-AOC KL1 Bidder | |
| 2 | L2₹36.9 L+₹40,000 (1.10%)Rejected-AOC | L2 | Rejected-AOC L2 bidder | |
| 3 | Rejected-Technical | - | Rejected-Technical Irregular |
Tender Value
Refer Docs
EMD Value
₹78,450
Closing Date
17 Oct 2023, 11:00 amClosed
CGM HnC APGCL
3rd Floor Bijulee Bhawan Paltan Bazar Guwahati 781001
EPC for Grouting in Inspection Gallery Clearing of debris from sump pit El 271.25 m to Adit 2 El. 310.25 m at dam gallery and Laying of new pipeline for dewatering repairing refitting and painting of old dewatering pipeline at KLHEP
2023_APGCL_32727_1
CGM HC 2023-24 KLHEP Grouting 20 44
Open Tender
Civil Works
Tender cum Auction
60 days
Hatidubi Dam West Karbi Anglong
Please refer Tender documents.
3 documents required · 3 mandatory
₹2,000
Yes
₹78,450
Yes
6 Mar 2024
2 Oct 2023
17 Oct 2023
2 Oct 2023
17 Oct 2023
2 Oct 2023
Amount
Grouting in Inspection Gallery and other seepage affected areas of KLHEP Dam (Surface area 1116.12 sqm) Grouting will include: a) Cleaning of exposed concrete surface of sticking material including loose and foreign material by cleaning with oil free air blast as per direction of Engineer in charge. b) Chipping of unsound/ weak concrete material from concrete surface of dam with manual chisel and/ or by standard power driven percussion type or of approved make including tapering of all edges, making square shoulders of cavities including cleaning the exposed concrete surface and reinforcement with wire brushes etc. and disposal of debris for all lead and lifts all complete as per direction of Engineer-In-Charge. (75 mm avg. thickness) c) Providing, mixing and applying SBR polymer (of approved make) modified Cement mortar in proportion of 1:4 (1 cement: 4 graded coarse sand with polymer minimum 2% by wt. of cement used) as per specifications and directions of Engineer-in-charge. d) Providing, mixing and applying SBR polymer (of approved make) modified Cement mortar in proportion of 1:4 (1 cement: 4 graded coarse sand with polymer minimum 2% by wt. of cement used) as per specifications and directions of Engineer-in-charge. 25 mm average thickness in 2 layers. e) Providing, mixing and applying SBR polymer (of approved make) modified Cement mortar in proportion of 1:4 (1 cement: 4 graded coarse sand with polymer minimum 2% by wt. of cement used) as per specifications and directions of Engineer-in-charge. 50 mm average thickness in 3 layers. f) Providing and inserting 12mm dia galvanised steel injection nipple in honey comb area and along crack line including drilling of holes of required diameter (20mm to 30mm) up to depth from 30mm to 80mm at required spacing and making the hole & crack dust free by blowing compressed air, sealing the distance between injection nipple with adhesive chemical of approved make and allow it to cure complete as per direction of Engineer-In-Charge. Dam gallery (at 1.00m c/c x 6 rows) Dam d/s face Pier, btn 1st stg. & 2nd stg. Concrete g) Providing and injecting approved grout in proportion recommended by the manufacturer into cracks/ honey-comb area with seepage water of concrete by suitable gun/ pump at required pressure including cutting of nipples after curing etc. complete as per directions of Engineer-in-Charge. Polyurethane injection grout in concrete/ RCC work of approved make. At gallery, at d/s face and At piers, gate groves h) Providing and applying integral crystalline slurry of hydrophilic in nature for waterproofing treatment to the RCC structures, prepared by mixing in the ratio of 5:2 (5 parts integral crystalline slurry : 2 parts water) for vertical surfaces and 3:1 (3 parts integral crystalline slurry : 1 part water) for horizontal surfaces and applying the same from negative (internal) side with the help of synthetic fiber brush. For vertical and overhead surface two coats @ 0.70kg per sqm. For sealing cracks and faulty construction joints, routed out/making U-shape groove size 25x25mm and then primed the area with integral crystalline slurry @0.05kg/running metre and while the surface is tacky filled the groove upto surface with crystalline mortar @1.50kg/running metre. Once crystalline mortar is touch dry then finally applied two coats of integral crystalline slurry @0.05kg/running metre per coat.
Clearing of debris from sump pit (EL. 217.25m) to ADIT-2 (EL. 310.25m) at dam gallery, KLHEP Clearing of debris, muds and silts from dam gallery from sump pit level (EL. 217.25m) to ADIT-2 (EL. 310.25m), carrying and taking out of same and disposing outside including necessary labour, tools and equipment for all the works complete as directed by Department.
Laying of new pipeline for dewatering; repairing, re-fitting and painting of old dewatering pipeline at dam gallery of KLHEP Providing and laying double flanged C.I./ D.I. pipes including testing of joints Laying and fixing in position of existing C.I. pipes and finishing with 2 coats of epoxy paint.
Bidder Name
Amount in Words
Dynasoure Concrete Treatment Pvt Ltd
New Horizon Enterprise
Dynasoure Concrete Treatment Pvt Ltd
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .