| 1 | L1₹30.6 LAdmitted-Finance | L1 | Admitted-Finance | |
| 2 | L2₹34.5 L+₹3.9 L (12.8%)Admitted-Finance | L2 | Admitted-Finance | |
| 3 | L3₹34.9 L+₹4.3 L (14.2%)Admitted-Finance | L3 | Admitted-Finance | |
| 4 | L4₹39.5 L+₹8.9 L (29.3%)Admitted-Finance | L4 | Admitted-Finance |
| Sl No | Description | Qty | Unit | M/S R R ELECTRICAL SERVICES L2 | M/S INTERNATIONAL STORES L3 | Powermech Engineering Services L4 | M/S SOFI SONS L1 |
|---|---|---|---|---|---|---|---|
| 1.01 | Supply and Fixing of G.I. Foundation Bolts (J Type) M24x750 mm long (Set of 4 No.’s per pole i:e 1 job = 4 Nos of GI Foundation Bolts per pole) along with GI Nuts | 46 | Job | 2,000 ₹92,000 | 2,100 ₹96,600 | 1,100 ₹50,600 Lowest | 2,800 ₹1,28,800 |
| 1.02 | Providing and Laying of RCC Foundation for 9.0 mtr. Long Octagonal poles including proper curing. 0.5m x 0.5 m x 1.8 m (RCC with concrete ratio M20 1:1.5:3) with minimum 8 Nos. of 12 mm dia longitudinal MS reinforcement rods with 10 rings of 8 mm diafor fixing the pole complete job (cost of HDPE corrugated Pipe for Cable entry included). 300 mm above ground and rest below ground (May vary as per central verge condition)
Debris of excavated material to be dispoed off immediately in view of sensitive / VVIP movemets | 46 | Job | 4,000 ₹1,84,000 Lowest | 4,500 ₹2,07,000 | 6,200 ₹2,85,200 | 5,000 ₹2,30,000 |
| 1.03 | Transportation of Octagonal Poles 9 mtr long from Bemina Stores to working site at Rajbagh including loading and unloading | 46 | No. | 500 ₹23,000 | 400 ₹18,400 | 100 ₹4,600 Lowest | 500 ₹23,000 |
| 1.04 | Erection of 9 mtr Octogonal Poles on RCC Foundations | 46 | No. | 2,000 ₹92,000 | 1,000 ₹46,000 Lowest | 2,100 ₹96,600 | 4,000 ₹1,84,000 |
| 1.05 | Providing and Earthings for Octagonal poles using GI Rod / Spike ( 3 feet) and 8 swg GI Wire | 46 | No. | 1,000 ₹46,000 | 700 ₹32,200 | 420 ₹19,320 Lowest | 420 ₹19,320 Lowest |
| 1.06 | Supply of Pre fabricated galvanized Iron (65 microns) double arm bracket (Dimensions as per drawing attached) | 41 | No. | 2,200 ₹90,200 | 2,400 ₹98,400 | 1,500 ₹61,500 Lowest | 1,500 ₹61,500 Lowest |
| 1.07 | Supply of Pre fabricate galvanized Iron (65 microns) Triple arm bracket (Dimensions as per drawing attached) | 4 | No. | 2,500 ₹10,000 | 2,800 ₹11,200 | 3,220 ₹12,880 | 1,860 ₹7,440 Lowest |
| 1.08 | Supply of Pre fabricate galvanized Iron (65 microns) Single arm bracket (Dimensions as per drawing attached) | 1 | No. | 1,200 ₹1,200 | 1,700 ₹1,700 | 1,100 ₹1,100 Lowest | 1,100 ₹1,100 Lowest |
| 1.09 | Fixing of Pre fabricated galvanized Iron Single / double / triple arm bracket on top of 9 mtr Octogonal pole (with top dia 70 mm) for holding LED lighting Luminaries | 46 | No. | 100 ₹4,600 Lowest | 200 ₹9,200 | 250 ₹11,500 | 250 ₹11,500 |
| 1.10 | Supply and Fixing of DK thermoplastic cable Junction/ Termination T boxes 8"x10"of class IP55/IP65 fitted with two 6-10 Amp MCB strip,4-way terminal block / connectors Including. , Clamps ,nut & bolts washers and copper lugs/thimbles for 1.5 sqmm Copper wire connections to be fitted properly inside the door opened gear box provided on the bottom side of the pole | 46 | No. | 100 ₹4,600 | 2,000 ₹92,000 | 10 ₹460 Lowest | 600 ₹27,600 |
Tender Value
₹43.9 L
EMD Value
₹87,800
Closing Date
11 Aug 2025, 2:30 pmClosed
Executive Engineer, ED-II, Rajbagh,Srinagar
Executive Engineer, ED-II, Rajbagh,Srinagar
Street light Illumination of Bakshi Stadium-LD Hospital-Lal Mandi Road stretch from Naaz/Gonikhan crossing and Bakshi stadium crossing using 9mtr Octagonal poles on central parapet/central verge under Capex Budget 2025-26
2025_PDD_281359_1
e-NIT No ED-II 08 of 2025-26 dt 15-07-2025
Open Tender
Electrical Works
Turn-key
120 days
Srinagar
Please refer Tender documents.
5 documents required · 5 mandatory
₹1,000
Executive Engineer, ED-II, Rajbagh,Srinagar
₹87,800
25 Aug 2025
16 Jul 2025
12 Aug 2025
19 Jul 2025
11 Aug 2025
26 Jul 2025
19 Jul 2025 - 25 Jul 2025
Amount
Supply and Fixing of G.I. Foundation Bolts (J Type) M24x750 mm long (Set of 4 No.’s per pole i:e 1 job = 4 Nos of GI Foundation Bolts per pole) along with GI Nuts
Providing and Laying of RCC Foundation for 9.0 mtr. Long Octagonal poles including proper curing. 0.5m x 0.5 m x 1.8 m (RCC with concrete ratio M20 1:1.5:3) with minimum 8 Nos. of 12 mm dia longitudinal MS reinforcement rods with 10 rings of 8 mm diafor fixing the pole complete job (cost of HDPE corrugated Pipe for Cable entry included). 300 mm above ground and rest below ground (May vary as per central verge condition) Debris of excavated material to be dispoed off immediately in view of sensitive / VVIP movemets
Transportation of Octagonal Poles 9 mtr long from Bemina Stores to working site at Rajbagh including loading and unloading
Erection of 9 mtr Octogonal Poles on RCC Foundations
Providing and Earthings for Octagonal poles using GI Rod / Spike ( 3 feet) and 8 swg GI Wire
Supply of Pre fabricated galvanized Iron (65 microns) double arm bracket (Dimensions as per drawing attached)
Supply of Pre fabricate galvanized Iron (65 microns) Triple arm bracket (Dimensions as per drawing attached)
Supply of Pre fabricate galvanized Iron (65 microns) Single arm bracket (Dimensions as per drawing attached)
Fixing of Pre fabricated galvanized Iron Single / double / triple arm bracket on top of 9 mtr Octogonal pole (with top dia 70 mm) for holding LED lighting Luminaries
Supply and Fixing of DK thermoplastic cable Junction/ Termination T boxes 8"x10"of class IP55/IP65 fitted with two 6-10 Amp MCB strip,4-way terminal block / connectors Including. , Clamps ,nut & bolts washers and copper lugs/thimbles for 1.5 sqmm Copper wire connections to be fitted properly inside the door opened gear box provided on the bottom side of the pole
Supply and Fixing of 6-10 AMP SP MCB C Curve
Supply of 150 watt LED Luminaries (140 Lm/Watt) of IP 66 CT; 5700 K CRI Type70 m of standard make with inbuilt surge protector and IK 10 (Complete Specs attached) The standard Guarantee for complete fitting will be 48 months from the date of commissioning. Supplier shall confirm Four years free maintenance of LED luminaries including materials and Lumens as per LM70 even at 4th year.FOR FIRST 2 YEARS- DLP OF CONTRACT, IT SHALL BE RESPONSIBILTY OF CONTRACTOR /EXECUTING AGENCY TO REMOVE DEFECTIVE LIGHTS FROM STREET LIGHT POLES AND REPLACE/REPAIR THE SAME FROM THE SERVICE CENTRE. FOR REST OF 2 YEARS, DEFECTIVE LED LUMINAIRE SHALL BE HANDED OVER TO THE AUTHORISED SERVICE CENTRE OF MANUFACTURER FOR ITS REPAIR / REPLACEMENT. (A CERTIFICATE OF COMPLIANCE OF FREE MAINTENANCE FOR 4 YEARS SHALL BE MANDATORY FROM THE SUPPLIER/MANUFACTURER OF LED LUMINAIRE PRE DISPATCH INSTRUCTIONS ). IN CASE OF FAILURE OF MANUFACTURER TO REPLACE THE LEDS, THE DIVISION SHALL RECOMMEND BLACKLISTING/DEBARMENT OF THE MANUFACTURER OF LIGHTS FROM ANY TENDER OF KPDCL.
Installation of 150 watt LED Luminaries (140 Lm/Watt) on Streetlight arm brackets
Supply and laying of 1.5 sq.mm PVC insulated multistrand flexible copper wire for service connections from connection plate (DK thermoplastic cable Junction/ Termination T boxes) to the LED luminary. individual circuit including loop & earthings laid properly .Colour combination must be green (earth),Netural(black),Phase(red).
Supply of 25 mmsq 4 core PVC Aluminium XLPE Armoured flexible cable
Supply of 70 mm sq 3.5-core XLPE armoured power cable (FRLS) of 1.1 KV grade
Underground Laying of LT Cable (4 core 25 sqmm /3.5 core 70 sqmm) through HDD (Horizantel Drilling) in HDPE Pipes beneath central parapeth, road crossings and othe identified locations (This shall Including Cost of HPDE PE-80 and PN-10 or higher Pipe of 63 Outer Diameter)
Normal Laying of LT Cable (4 core 25 sqmm /3.5 core 70 sqmm) - within RCC foundation upto Pole junction box and DT/ AVR cabling
Dismantling of foot path tiles/dever stone/ Central Parapet for Foundation Laying pole erection/& after completion of work its refixing including cost of broken tiles/dever stone & cement mortor or sand so as to bring it in the original shape where ever required
Dismantling of existing Streetlight poles inclind all allied accessoires and transportation to stores
Dismantling of PCC Poles (including their proper dsiposal) alongwith allied Accessories (to be handed over to Sub Division)
Supply,installation,testing and commissioning of 63 kVA ,11/0.433kV, 3-phase Distribution Transformer Energy Level-2 (Pre Ammendement), Aluminium wound , and with LV Cable Box having detachable Aluminium Gland plate (Arcing horns included) with LV Bimetallic terminal connection suitable for vertical take off of cable.
Supply and erection of ST poles 9 mt long (ST410 SP33) with Earthing Channel Piece
Supply and Fixing of GI Channels/Cross arm/GI Angle for SS and V Cross-arm with F Top along with all pole collars
Providing and Earthing of substation and AVR --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239.GI Strip for neutral earthing of size 25 mm x 3 mm for connection of transformer body,G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber made of brick masonary with RCC slab covers. (Neutral earthing to be laid through Conduit)
Supply and Fixing of Galvanized nuts & bolts/washers
Supply and fixing of Self Adhesive Insulation Tape (Steel Grrip/Anchor or equivalent)
Supply and Fixing of 11 kV Gapless Surge Arrestor,9 kV ,10 kA ,LA with polymer housing, Stn. Type
Supply and Fixing of 11kV GO, AB Switch 3-Phase, 3-Pole, 200 Amp, Vertical Type (Complete with Pipe / Handle and its separate earthing using GI Pipe/Strip)
Supply and Fixing of 11 kV Horn Gap Fuse Set 3 Phase 200A
Supply and Fixing of 11kV Polymeric composite Disc Insulator 12kV,min failing load 45kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm with fittin
Supply and Fixing of 11kV Polymeric composite Pin Insulator 12kV, 5kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm
Providing and Fixing of Anti climbing Device using GI Barbed Wire with end clamps with 2 GI Clamps with GI Nuts & Bolts.
Providing and Painting of ST poles 9 mt long with 1 coat of red oxide and 2 coats of Al. paint
Providing and Earthing of 9 meter ST poles Complete by GI Pipe 40 mm 3 mtr long through GI Strip 25x3mm
Providing and Cement Bottoming of 9 meter ST poles in 1:2:4 mix as per R.E.C.standards 0.48 cum/pole
Providing and laying of 0.03 ASCR conductor for DT jampering
Construction of 6 ft length x 4 ft breadth and height upto 6 feet bed by using galvanized channel (100x50x50) 6 mm, pole butts, 4 no. 10 feet long with base plate both sides for installation of stabilizer/AVR including cement concrete under ground of required size suitable for accomodating stabilizer/AVR. The cost shall include Fencing of the Bed (wire mesh welded 1'' square mesh) along with Roofing using Colour Coated GI Roofing Sheet. Gate Arrangement (fitted with Aldrof and lock) to be proided at the front side of the Wire mesh structure) for easy access to the AVR. Entire Wire mesh fencing strucure shal be duly painted with one coat of Red oxide and two coats of Al-Paint . The structure should pe properly earthed using GI strip and GI Pipe/Spike
Shifting of AVR (45 KVA) and LT Panel from Stores Bemina to working Site and their installation on the Bed Structure( including loading and unloading) LT Panel to be earthed on both sides with 8 SWG GI wire and GI Spikes )
Supply and installation of LT Thread through Trivector meter 200 Amp (prodigy meter)
Supply and Fixing of Cable Route Markers
Supply and Fixing of Wedge Connectors / PG Clamps
Supply and Fixing of 11 KV danger plates with clamps
Supply and Fixing of Aluminium Thimbes for 25 sqmm Cable
Supply and Fixing of Aluminium Thimbes for 70 sqmm Cable
Supply and laying of 2 core 16 sqmm LT Cable (un-armoured) to be laid overhead on existing Electric utility / Street light poles This includes reconnecting existing LED Luminaries installed on poles to this newly laid overhead cable )
Supply and fixing of Main Control Box with 2 No. 100 Amps MCCB (one as spare) TPN installed before meter
Supply and fixing of Contactor 160 Amps 4 Pole MCX 32
Supply and fixing of Muki Clamps with Shakle insulators inclusing GI nuts and bolts
Supply and fixing of Control Box with 2 No. 16 Amps 4 pole MCBs along with pole clamps/straps
Fluorescent Sign board of appropriate size (4'x3')showing details of the work like name of the Deptt, work, Head of the account, date of start and date of commissioning any other detail as required, fixed over GI Angle
Providing/Submission of Both Pre and Post Work Execution Geo-Tagged Coloured Photographs of subjected work on A4 sized photopaper (2 pic per page -Pre and Post)
M/S R R ELECTRICAL SERVICES (BID ID -2438038)
M/S INTERNATIONAL STORES (BID ID -2438458)
Powermech Engineering Services (BID ID -2438762)
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .