Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.9 CrAdmitted-Finance BERWAR KISHTWAR | KISHTWAR | JAMMU AND KASHMIR | 182132 | ₹2.9 Cr | L1 | Admitted-Finance |
| 2 | L2₹3.2 Cr+₹37.7 L (13.2%)Admitted-Finance | ₹3.2 Cr+₹37.7 L (13.2%) | L2 | Admitted-Finance |
| 3 | L3₹3.4 Cr+₹59.0 L (20.7%)Admitted-Finance | ₹3.4 Cr+₹59.0 L (20.7%) | L3 | Admitted-Finance |
| 4 | Rejected-Technical | - | - | Rejected-Technical Not Eligible |
| 5 | Rejected-Technical | - | - | Rejected-Technical Not Eligible |
| Sl No | Description | Qty | Unit | Satwant Singh Contractor L3 | M/S HARISH GUPTA L2 | MS Abdul Rashid Bhat and Sons L1 |
|---|---|---|---|---|---|---|
| 1.00SH: 1. Construction of Retaining Walls | ||||||
| 1.10 | Earthwork in excavation by manual means in trenches for foundations of drains, pipes cables etc. over areas not exceeding 1.50 mtr in width & 10 sqm on plan
Soil = 70% (35% Manual means, 35% Mechanical means), OR = 30% | 224.5 | Cum | 180 ₹40,410 | 80 ₹17,960 Lowest | 100 ₹22,450 |
| 1.20 | P/L in positon cement concrete of specified grade 1:3:6 in foundation including cost of formwork using 40mm nominal size | 78.3 | Cum | 3,800 ₹2,97,540 Lowest | 4,800 ₹3,75,840 | 3,800 ₹2,97,540 Lowest |
| 1.30 | P/L in positon cement concrete of specified grade 1:2:4 using 20mm nominal size crushed including cost of formwork | 3.3 | Cum | 5,800 ₹19,140 | 5,200 ₹17,160 | 4,000 ₹13,200 Lowest |
| 1.40 | Random Rubble stone masonry with hard nallah stone in foundations upto plinth with 1:6 cement mortar | 168.24 | Cum | 2,800 ₹4,71,072 | 2,900 ₹4,87,896 | 2,600 ₹4,37,424 Lowest |
| 1.50 | Dry Random Rubble stone masonry using hard nallah stones in Panels of R/Walls. | 188.89 | Cum | 1,800 ₹3,40,002 | 1,800 ₹3,40,002 | 1,300 ₹2,45,557 Lowest |
| 1.60 | Back filling behind R/Walls, wing walls, Return wall etc. | 71.5 | Cum | 650 ₹46,475 | 550 ₹39,325 | 200 ₹14,300 Lowest |
| 2.00SH:2 Construction of B/Wall | ||||||
| 2.10 | Earthwork in excavation by manual means in trenches for foundations of drains, pipes cables etc. over areas not exceeding 1.50 mtr in width & 10 sqm on plan
Soil = 70% (35% Manual means, 35% Mechanical means), OR =30% | 882 | Cum | 180 ₹1,58,760 | 80 ₹70,560 Lowest | 100 ₹88,200 |
| 2.20 | P/L in positon cement concrete of specified grade 1:3:6 in foundation including cost of formwork | 296.52 | Cum | 3,800 ₹11,26,776 Lowest | 4,800 ₹14,23,296 | 3,800 ₹11,26,776 Lowest |
Tender Value
Refer Docs
EMD Value
₹4 L
Closing Date
4 Jul 2022, 12:00 pmClosed
EXECUTIVE DIRECTOR (P)
RO JAMMU, HOUSE NO 261 SECTOR 6 CHANNI HIMMAT JAMMU 180015
Restoration of road by way of clearance of landslides Snow including construction of RWall BWall and laying of WBMIII BM and BC on Chatroo Singpora road From km 0000 to km 19600 in the UT of Jammu and Kashmir for FY 202223
2022_NHIDC_692878_1
NHIDCL/ROJMU /KTWR/Maint/CS/ 0-19.600/165/2021-22
Open Tender
Civil Works - Roads
Item Rate
150 days
CHATROO
Please refer Tender documents.
5 documents required · 5 mandatory
₹11,800
NHIDCL
₹4 L
RO JAMMU
29 Jul 2022
3 Jun 2022
5 Jul 2022
3 Jun 2022
4 Jul 2022
27 Jun 2022
3 Jun 2022 - 15 Jun 2022
15 Jun 2022
Amount
SH: 1. Construction of Retaining Walls
Earthwork in excavation by manual means in trenches for foundations of drains, pipes cables etc. over areas not exceeding 1.50 mtr in width & 10 sqm on plan Soil = 70% (35% Manual means, 35% Mechanical means), OR = 30%
P/L in positon cement concrete of specified grade 1:3:6 in foundation including cost of formwork using 40mm nominal size
P/L in positon cement concrete of specified grade 1:2:4 using 20mm nominal size crushed including cost of formwork
Random Rubble stone masonry with hard nallah stone in foundations upto plinth with 1:6 cement mortar
Dry Random Rubble stone masonry using hard nallah stones in Panels of R/Walls.
Back filling behind R/Walls, wing walls, Return wall etc.
SH:2 Construction of B/Wall
Earthwork in excavation by manual means in trenches for foundations of drains, pipes cables etc. over areas not exceeding 1.50 mtr in width & 10 sqm on plan Soil = 70% (35% Manual means, 35% Mechanical means), OR =30%
P/L in positon cement concrete of specified grade 1:3:6 in foundation including cost of formwork
P/L in positon cement concrete of specified grade 1:2:4 using 20mm nominal size crushed including cost of formwork
Random Rubble stone manually with hard nallah stone in foundations upto plinth with 1:6 cement mortar
Back filling behind R/Walls, wing walls, Return wall etc.
SH:3 Clearance of Land Slide
Clearance of land slides/boulders in soil,ordinary rock nd hard rock including loading & unloading of extra carriage and haulage of materials by tipper for all leads and lifts.
SH 4: Clearance of Snow
Clearance of snow from Km 0.00 TO 19.600 KM
SH: 5. WBM- III & Bituminious Macadam & Bituminous Concrete.
Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with 3 wheeled steel/ vibratory roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density.(Thickness=75mm)
Providing and applying primer coat with bitumen emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.60 kg/sqm using mechanical means.
Providing and laying bituminous macadam with 100-120 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading premixed with bituminous binder, transported to site, laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled as per clauses 501.6 and 501.7 to achieve the desired compaction(Thickness=50mm)
Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous/granular surface cleaned with mechanical broom.
Providing and laying bituminous concrete with 100-120 TPH batch type hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 to 5.6 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 509 complete in all respects(Thickness=30mm)
SH: 6. Filling Pot-holes and Patch Repairs with Bituminous concrete
Filling Pot-holes and Patch Repairs with Bituminous concrete, 30mm. Removal of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 504, compacting, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2
M/S HARISH GUPTA
Satwant Singh Contractor
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .