Loading…
Loading…
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹2.8 Cr
EMD Value
₹5.6 L
Closing Date
22 Oct 2026, 3:00 pm
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Executive Engineer, BUILDING DIVISION PURNEA
EE
EE, BUILDING DIVISION PURNEA, BCD, PURNEA, BIHAR
Superintending Engineer, Purnea Circle
SE
Rais Raise of Perimeter Wall at Central Jail, Purnea for the year 2026-27 (Re-Tender)
140536
28/SBD/BCD/PURNEA/2026-27
Open Tender
CIVIL
Purnia
• Unconditional bank guarantee from any scheduled Indian bank issued within the state in the format given. Total Bid Security Amount in Rupees 556520.00
• (i) Legal Status of Bidder 4.3(a) (ii) Place of Registration. (iii) write Principal place of Business (iv) Power of attorney of signatory Bid 4.2(iv)
• Total value of civil engineering construction work, in Rupees, Performed in last five years. Minimum annual financial turnover (in all classes of civil engineering construction works only) amount of construction work of at least the equal to the 50 % of estimated cost of works for which bid has been invited. The turn over will be indexed at the rate of 8% for a year 2021-22 2022-23 2023-24 2024-25 2025-26
• Amount in Rupees related to Work Experience of Similar nature Satisfactory completed at least one similar work of value not less than 50% of estimated Cost .
• Minimum Quantities of work done as prime contractor in any one year during last five years, units shall be same as in Requirement column Items Qty Unit Brick Work 302 Cum PCC / RCC 215 Cum Plaster Work 12260 Sqm Concertina Coil 1100 Meter
• Electrical License The contractor or his identified sub-contractor should possess required valid electrical license for executing the building electrification works and should have executed similar electrical works for a minimum amount as indicated in Appendix in any one year
• (a) Amount of Existing commitments and ongoing works in Rupees Sec 2-1.4(A)
• (b) Amount of Work for which Bid already submitted, in Rupees Sec 2-1.4(B)
• Evidence of accesses to Financial Resources in Rupees Evidence of access to or availability of credit facilities (10% of estimated cost), certified by bankers (for work under this bid). 4.2(i)
• Proposed methodology and programme of construction Select from drop down list the proposed methodology and programme of construction, backed with equipment planning and deployment 4.3(l)
• Litigation History. Select from drop down list. Information regarding any litigation, current or during the last five years, in which the Bidder is involved, the parties concerned, and disputed amount. (Attached or not) 4.3(j)
• Affidavit Select from drop down list. Regarding statements made in the required attachments are true and correct. Sec-2, Affidavit
• Undertaking Select from drop down list. Able to invest a minimum of cost up to 25% of contract value of work. During implementation of contract. Sec-2, Undertaking
• Registration No. IT.& ST Registration & clearance Certificate Labour License Character Certificate NOC for Debar (If required)
• Numbers and Maximum age of Equipments with bidder Type of Equipment Nos. Maxm. Age Concrete Mixer with Integral weigh Batching facility 2 5 Water Tanker 1 5 Steel shuttering 3000 sft 5 Vibrator (Plate & Niddle) 4 5
• Name of the Personnel and Experince in years and Select from drop down list Personnel / Qualification Site Engineer / B.E. (Civil) + 03 Years Exp. (3 years in Building Construction) or Diploma in Civil + 7 year Exp. In Building construction or retired A.E. 1 No. Site Supervisor /Fresh Graduate in Civil or Diploma Civil + 02 Years Exp. or retired I.T.I Holder. 2 Nos.
CIVIL
PERCENTAGE
L1
1
21 documents required · 21 mandatory
₹10,000
Processing Fee: 5900
₹5.6 L
at office of EE BCD PURNEA on 06-10-2026 03:00 pm, office of SE BCD PURNEA on 07-10-2026 03:00 pm
24 Sept 2026
24 Sept 2026
23 Oct 2026
24 Sept 2026
22 Oct 2026
24 Sept 2026
14 Oct 2026
Bill of Quantity
Raise of Perimeter Wall at Central Jail, Purnea for the Year 2026 - 27 (Re-Tender)
Estimated Cost :- Rs. 27825673.00
Earnest Money:- Rs. 556520.00
Cost of B.O.Q :- Rs. 10000.00
Time of Completion:- 09 Months
Sl. No Particulars Qty Unit Rate Amount
1. 15.7.3 Demolishing brick work including stacking of serviceable material and disposal of unserviceable material within 50 meters lead: In lime mortar 417.481 M² 340.50 142152.00
2. 15.7.4 Demolishing brick work including stacking of serviceable material and disposal of unserviceable material within 50 meters lead: In cement mortar 207.643 M² 823.70 171036.00
3. 5.2.2 Reinforced cement concrete work in wall (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts, etc. upt floor five level excluding cost of centring, shuttering, finishin and reinforcement. 1:1:5:3(1 cement: 1.5 coarse sand:3 graded stone aggregate 20mm nominal size) 409.964 M3 5670.00 2324496.00
4. 6.1.14A+ 6.3C Brick work with bricks of class designation 100A in foundations and plinth in :Cement mortar 1:6 (1 cement: 6 coarse sand )With Extra tor Brick work in superstructure above plinth level upto floor V cum 554.985 M3 5662.10 3142381.00
5. 13.12.2 15 mm cement plaster on rough side of single or half brick wall of mix. 1:4(1 cement: 4 coarse sand ) 24520.460 M² 176.40 4325409.00
6. 13.78.1+ 13.79.1 Finishing walls with water proofing cement paint of approved brand and manufacture and of required shade to give an even shade with Applying one coat of cement primer of approved brand and manufacture on wall surface:Cement primer, 24520.460 M² 119.80 2937551.00
7. 5.22 Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete.
A. 5.22.7A Thermo-Mechanically Treated bars TMTC-500-8mm dia. 12624.18 Kg 94.50 1192985.00
B. 5.227B Thermo-Mechanically Treated bars TMTC-500-10 mm dia 363.09 Kg 92.60 33622.00
C. 5.227C Thermo-Mechanically Treated bars TMTC-500-12mm dia 24570.42 Kg 90.80 2230994.00
8. 5.9 Centring and shuttering including strutting,propping etc. and removal of form for
A. 5.9.1 Foundations, footings, bases of columns etc. for mass concrete. 119.37 M² 211.60 25259.00
B. 5.9.6 Columns,Pillars, Piers, Abutments, Posts and Struts 1566.20 M² 494.40 774329.00
C. 5.9.5 Lintels, beams, plinth bams, griders, bressumers and contilevers. 42.28 M² 404.70 17111.00
D. 5.9.17 Cornices and mouldings 2091.39 M² 625.20 1307537.00
9. 25.2 Providing and fixing double scaffolding system (cup lock type) on the exterior side of building/structure, upto 25 metre height, above ground level, including additional rows of scaffolding in stepped manner as per requirement of site, made with 40mm dia M.S. tube, placed 1.5 metre centre to centre, horizontal & vertical tubes joint with cup & lock system with M.S. Tubes, M.S. tube challis 20582.34 M² 176.20 3626608.00
10. 10.43 Providing and fixing concertina coil fencing with punched tape concertina coil 600 mm dia 10 metre openable length ( total length 90 m), having 50 nos rounds per 6 metre length, upto 3 m height of wall with existing angle iron ‘Y’ shaped placed 2.4 m or 3.00 m apart and with 9 horizontal R.B.T. reinforced barbed wire, 2200.92 M 272.60 599971.00
11. 2.8.1 Earth work in excavation in foundation trenches or drains(not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m . including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All Kinds of soil. 77.021 M3 360.70 27781.00
12. 2.28 Supplying and Filling in plinth with local sand and under floors including, watering, ramming consolidating and dressing complete 10.955 M3 287.30 3147.00
13.. 11.72 Providing designation 100 A one brick flat soling joints filled with local sand including cost of watering, taxes, royalty all complete as per building specification and direction of E/l, 68.28 M² 283.30 19344.00
14. 4.1.2 Providing and laying in position cement concrete of specified grade exluding the cost of centring and shuttering-all work upto plinth level.1:1.5:3(1 Cement :1.5 coarse sand:3 graded stone aggregate 20 mm nominal size) 3.851 M3 4420.80 17025.00
15. 5.1.2 Providing and laying in position specified grade of reinforced cement concrete excluding the cost of centring,shuttering,finishing and reinforcement-All work puto plinth level.1:1:5:3(1 cement: 1.5 coarse sand:3 graded stone aggregate 20 mm nominal size) 15.438 M3 4688.30 72378.00
16. 6.1.14C+ 6.3C Brick work with fly ash bricks as per IS 12894(2002) & IS 3495 in foundations and plinth in :Cement mortar 1:6 (1 cement: 6 coarse sand )Extra tor Brick work in superstructure above plinth level upto floor V 48.60 M3 5765.20 280212.00
17. 1007C Supplying of steel Angle (50x50x6mm) 228.220 Kg 58.90 13442.00
18. 10.33.4 Labour for fitting and fixing barbed wire fencing in six rows horizontal up to a height of 1.85m and two diagonals including fixing of post in cement concrete at 2.5m centres including cost of staples (but excluding the cost of cement concrete, angle, iron post, its cutting and making holes, nuts & bolts) all complete as per building specification and direction of E/l. 90.46 M 74.60 6748.00
19 Carriage cost of Materials
20 Extra cost of Materials
Correction Factor @ 0.982 on Shedule Items = ₹ 26,410,092.00
Add GST 5.36% of Total = ₹ 1,415,581.00
EXECUTIVE ENGINEER
BUILDING DIVISION, PURNEA
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
Re Tender Doc Raise of Perimeter wall in Central Jail Purnea.doc
NIT • 0.66 MB
NIT 28 RE Tender.pdf
NIT • 0.70 MB
BOQ Raise of Perimeter Wall.xlsx
NIT • 0.02 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .