| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹17,654Admitted-Finance | ₹17,654 | L1 | Admitted-Finance |
| 2 | L2₹21,822+₹4,168 (23.6%)Admitted-Finance | ₹21,822+₹4,168 (23.6%) | L2 | Admitted-Finance |
| 3 | L3₹23,101+₹5,447 (30.9%)Admitted-Finance | ₹23,101+₹5,447 (30.9%) | L3 | Admitted-Finance |
| 4 | L4₹28,653.15+₹10,999.15 (62.3%)Admitted-Finance | ₹28,653.15+₹10,999.15 (62.3%) | L4 | Admitted-Finance |
| 5 | L5₹30,990+₹13,336 (75.5%)Admitted-Finance | ₹30,990+₹13,336 (75.5%) | L5 | Admitted-Finance |
| Sl No | Description | Qty | Unit | M/S MAA JAJWALA KRIPA ENTERPRISES L1 | Sagar Construction Comapny L5 | R.R. CONSTRUCTION COMPANY L2 | V VIRAT CONSTRUCTION COMPANY L7 | AARTI ENTERPRISES POKARAN L3 | MAA SANCHIYA ENTERPRISES L4 | MAABHADRIYA RAY CON.COMPAY L6 | MAA BHADARIYA RAY ENTEPRISES L8 |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1.00 | Earth work in excavation for roadway, including trimming bottom and
side slopes in accordance with requirement of line, grades and cross
sections, including disposal of surplus material with all lift and lead
upto 1000 metre as per MoRT&H specification clause 301 | 1 | Cum | 60 ₹60 Lowest | 150 ₹150 | 115 ₹115 | 186.05 ₹186.05 | 125 ₹125 | 154.84 ₹154.84 | 171.5 ₹171.5 | 184 ₹184 |
| 2.00 | Dismantling of existing structures like culverts, bridges, retaining
walls, CC road and other structure comprising of masonry, cement
concrete, wood work, steel work, including T&P and scaffolding
wherever necessary, sorting the dismantled material, disposal of
unserviceable material and stacking the serviceable material with all
lifts and lead of 50 metres as directed by Engineer | 1 | Cum | 30 ₹30 Lowest | 275 ₹275 | 200 ₹200 | 310.87 ₹310.87 | 209 ₹209 | 258.72 ₹258.72 | 290.1 ₹290.1 | 306.54 ₹306.54 |
| 3.00 | Providing and laying in position cement concrete of specified grade
excluding the cost of centring and shuttering - All work upto plinth
level 1:1½:3 (1 Cement : 1½ coarse sand : 3 graded stone aggregate 20
mm nominal size). | 1 | Cum | 3,000 ₹3,000 Lowest | 4,500 ₹4,500 | 3,000 ₹3,000 Lowest | 4,669 ₹4,669 | 3,133 ₹3,133 | 3,885.82 ₹3,885.82 | 4,200.2 ₹4,200.2 | 4,609.8 ₹4,609.8 |
| 4.00 | Providing and laying in position cement concrete of specified grade
excluding the cost of centring and shuttering - All work upto plinth
level 1:3:6 (1 Cement : 3 fine/ coarse sand : 6 graded stone aggregate 40
mm nominal size). | 1 | Sqm | 1,200 ₹1,200 Lowest | 2,900 ₹2,900 | 2,000 ₹2,000 | 3,614.25 ₹3,614.25 | 2,425 ₹2,425 | 3,008.06 ₹3,008.06 | 3,200.5 ₹3,200.5 | 3,568.5 ₹3,568.5 |
| 5.00 | Cement concrete flooring 1:2:4 (1 cement : 2 coarse sand : 4 graded
20mm nominal size stone aggregate) finished with a floating coat of
neat cement including cement slurry, but excluding the cost of
nosing of steps etc. complete. including Providing /mixing of
synthetic fibers compulsorily complying with IS 16481:2022 of 06
mm/12 mm length to be mixed @ 0.25% by weight of Cement i.e.
125 gms per 50 kg Cement up to 900 gms per cum of Concrete/
mortar | 1 | Cum | 50 ₹50 Lowest | 289 ₹289 | 250 ₹250 | 333.78 ₹333.78 | 225 ₹225 | 277.79 ₹277.79 | 310.5 ₹310.5 | 333.38 ₹333.38 |
| 6.00 | Random rubble masonry with hard stone in foundation and plinth
including levelling up with cement concrete 1:6:12 (1 cement : 6
coarse sand : 12 graded stone aggregate 20 mm nominal size) upto
plinth level with Cement Mortar 1:6 ( 1-Cement : 6-Sand). | 1 | Cum | 2,500 ₹2,500 Lowest | 3,766 ₹3,766 | 2,500 ₹2,500 Lowest | 3,839.4 ₹3,839.4 | 2,575 ₹2,575 | 3,195.45 ₹3,195.45 | 3,450.5 ₹3,450.5 | 3,985.2 ₹3,985.2 |
| 7.00 | Brick work with FPS bricks of class designation 75 in foundation
and plinth in: Cement mortar 1:4 (1 cement : 4 coarse sand) | 1 | Cum | 500 ₹500 Lowest | 4,200 ₹4,200 | 2,500 ₹2,500 | 4,427 ₹4,427 | 2,968 ₹2,968 | 3,682 ₹3,682 | 4,100.5 ₹4,100.5 | 4,424 ₹4,424 |
| 8.00 | Cement plastering including T&P, scaffolding, material and complete
labour, including cost of water, curing, racking of joints etc. with 12
mm cement plaster of mix : including Providing /mixing of synthetic
fibers compulsorily complying with IS 16481:2022 of 06 mm/12 mm
length to be mixed @ 0.25% by weight of Cement i.e. 125 gms per
50 kg Cement up to 900 gms per cum of Concrete/ mortar | 1 | Sqm | 50 ₹50 Lowest | 127 ₹127 | 150 ₹150 | 179.33 ₹179.33 | 121 ₹121 | 149.25 ₹149.25 | 170.25 ₹170.25 | 204 ₹204 |
| 9.00 | Earth work for Sewer line and Manhole in excavation in foundation,
trenches manholes, road side chambers etc. including dressing of
sides and ramming of bottoms, including getting out the excavated
material, refilling after laying pipe/ foundation and disposal of surplus
excavated material at a lead upto 50m suitable site as per direction
of Engineer for following depths, below natural ground / Road top
level including allowances for any additional excavation beyond the
drawings (measurement for payment to be as per standard
drawings), re-handling of material/earth to complete the task | 1 | Cum | 110 ₹110 Lowest | 187 ₹187 | 170 ₹170 | 236.21 ₹236.21 | 159 ₹159 | 196.59 ₹196.59 | 224.25 ₹224.25 | 239 ₹239 |
| 10.00 | Structural steel work riveted, bolted or welded in built up sections,
trusses and framed work, including cutting, hoisting, fixing in position
and applying a priming coat of approved steel primer all complete | 1 | kg | 114 ₹114 | 50 ₹50 Lowest | 80 ₹80 | 90.5 ₹90.5 | 61 ₹61 | 75.28 ₹75.28 | 85.5 ₹85.5 | 91.2 ₹91.2 |
Tender Value
₹24 L
EMD Value
₹48,000
Closing Date
14 May 2026, 6:00 pmClosed
EXECUTIVE OFFICER
NAGAR PALIKA POKARAN
REPAIR WORK AT DIFFIERNT PLACE NAGAR PALIKA POKARAN (SEWER, INTERLOCKING ROAD AND OTHER WORK)YEAR 2026-27
2026_DLB_556669_1
RO 77 DATE 04-05-2026 work no 02
Open Tender
Civil Works
Item Rate
365 days
POKARAN
Please refer Tender documents.
2 documents required · 2 mandatory
₹500
E.O NAGAR PALIKA POKARAN
₹48,000
Yes
20 May 2026
7 May 2026
15 May 2026
7 May 2026
14 May 2026
7 May 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation for roadway, including trimming bottom and
side slopes in accordance with requirement of line, grades and cross
sections, including disposal of surplus material with all lift and lead
upto 1000 metre as per MoRT&H specification clause 301 | 1 | Cum | 235.5 | ₹235.5 |
| 2 | Dismantling of existing structures like culverts, bridges, retaining
walls, CC road and other structure comprising of masonry, cement
concrete, wood work, steel work, including T&P and scaffolding
wherever necessary, sorting the dismantled material, disposal of
unserviceable material and stacking the serviceable material with all
lifts and lead of 50 metres as directed by Engineer | 1 | Cum | 393.5 | ₹393.5 |
| 3 | Providing and laying in position cement concrete of specified grade
excluding the cost of centring and shuttering - All work upto plinth
level 1:1½:3 (1 Cement : 1½ coarse sand : 3 graded stone aggregate 20
mm nominal size). | 1 | Cum | 5,910 | ₹5,910 |
| 4 | Providing and laying in position cement concrete of specified grade
excluding the cost of centring and shuttering - All work upto plinth
level 1:3:6 (1 Cement : 3 fine/ coarse sand : 6 graded stone aggregate 40
mm nominal size). | 1 | Sqm | 4,575 | ₹4,575 |
| 5 | Cement concrete flooring 1:2:4 (1 cement : 2 coarse sand : 4 graded
20mm nominal size stone aggregate) finished with a floating coat of
neat cement including cement slurry, but excluding the cost of
nosing of steps etc. complete. including Providing /mixing of
synthetic fibers compulsorily complying with IS 16481:2022 of 06
mm/12 mm length to be mixed @ 0.25% by weight of Cement i.e.
125 gms per 50 kg Cement up to 900 gms per cum of Concrete/
mortar | 1 | Cum | 422.5 | ₹422.5 |
| 6 | Random rubble masonry with hard stone in foundation and plinth
including levelling up with cement concrete 1:6:12 (1 cement : 6
coarse sand : 12 graded stone aggregate 20 mm nominal size) upto
plinth level with Cement Mortar 1:6 ( 1-Cement : 6-Sand). | 1 | Cum | 4,860 | ₹4,860 |
| 7 | Brick work with FPS bricks of class designation 75 in foundation
and plinth in: Cement mortar 1:4 (1 cement : 4 coarse sand) | 1 | Cum | 5,600 | ₹5,600 |
| 8 | Cement plastering including T&P, scaffolding, material and complete
labour, including cost of water, curing, racking of joints etc. with 12
mm cement plaster of mix : including Providing /mixing of synthetic
fibers compulsorily complying with IS 16481:2022 of 06 mm/12 mm
length to be mixed @ 0.25% by weight of Cement i.e. 125 gms per
50 kg Cement up to 900 gms per cum of Concrete/ mortar | 1 | Sqm | 227 | ₹227 |
| 9 | Earth work for Sewer line and Manhole in excavation in foundation,
trenches manholes, road side chambers etc. including dressing of
sides and ramming of bottoms, including getting out the excavated
material, refilling after laying pipe/ foundation and disposal of surplus
excavated material at a lead upto 50m suitable site as per direction
of Engineer for following depths, below natural ground / Road top
level including allowances for any additional excavation beyond the
drawings (measurement for payment to be as per standard
drawings), re-handling of material/earth to complete the task | 1 | Cum | 299 | ₹299 |
| 10 | Structural steel work riveted, bolted or welded in built up sections,
trusses and framed work, including cutting, hoisting, fixing in position
and applying a priming coat of approved steel primer all complete | 1 | kg | 114.5 | ₹114.5 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.90 MB
Provisions.pdf
Tender Documents • 0.27 MB
BOQ_991090.xls
BOQ • 0.35 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .