Tender Value
₹50 L
EMD Value
₹1 L
Closing Date
21 Oct 2026, 5:00 pm
Director Works EO RAJUVAS Bikaner
Director Works EO RAJUVAS Bikaner
Construction of Cattle Shed at LRS Chandan
2026_RAJUV_601570_2
NIT 4 of 2026-27
Open Tender
Civil Works
Percentage
270 days
Chandan
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,000
Director Works EO Account As per NIT
₹1 L
Yes
29 Sept 2026
29 Sept 2026
22 Oct 2026
29 Sept 2026
21 Oct 2026
29 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic Excavator )/ manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sum on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m, including taking out the excavated soil and depositing and refilling of jhiri with watering & ramming and disposal of surplus excavated soil as directed with in a lead of 50 meter. All kinds of soils. | 110.75 | Cum | 178 | ₹19,713.5 |
| 2 | Providing and laying in position cement concrete including curing, compaction etc. complete in specified grade excluding the cost of centering and shuttering - All work up to plinth level. 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size). | 60.11 | Cum | 3,962 | ₹2,38,155.82 |
| 3 | Random Rubble stone masonry for with hard stone in foundation and plinth in Cement Sand mortar above 30 CM thick wall in:Cement Mortar 1:6 ( 1-Cement : 6-Sand). | 29.84 | Cum | 3,406 | ₹1,01,635.04 |
| 4 | Brick masonry with F.P.S. bricks of class designation 100 in foundation and plinth with bricks Cement mortar 1 : 6 (1 cement : 6 coarse sand) | 75.15 | Cum | 5,294 | ₹3,97,844.1 |
| 5 | Centering & shuttering with plywood or steel sheets including strutting, propping bracing both ways with steel props and removal of formwork for upto floor five level for : Suspended floors, roofs, landings, staircases, balconies, girders, cantilevers, b Columns, pillars, posts and struts etc. | 260.64 | Sqm. | 374 | ₹97,479.36 |
| 6 | Providing and laying in position specified grade of cement concrete for all RCC structural elements upto plinth level including curing, compaction, finishing with rendering in cement sand mortar 1:3 (1 cement: 3 coarse sand) and making good the joints and cost of plastizers(if required) excluding the cost of centering, shuttering and reinforcement. M20 grade Nominal Mix / Design Mix | 8.19 | Cum | 5,921 | ₹48,492.99 |
| 7 | Providing and fabricating reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding (including cost of binding wire) all complete up to floor five levelThermo-mechanically Treated bars (Conforming of relevent IS code) | 864 | Kg | 82 | ₹70,848 |
| 8 | Random Rubble stone masonry with hard stone in superstructure above plinth level and upto five level above 30cm. thick walls in :Cement Mortar 1:6 ( 1-Cement : 6-Sand). | 54.6 | Cum | 4,175 | ₹2,27,955 |
| 9 | Pointing on stone masonary in cement mortar 1:3 (1 cement : 3 fine sand): Raised and cut pointing | 163.8 | Sqm. | 256 | ₹41,932.8 |
| 10 | Providing & fixing precast cement concrete coping 1 : 2 : 4 mix 50mm thick complete as per specification : | 27.3 | Sqm. | 440 | ₹12,012 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 4.24 MB
Tendernotice_2.pdf
PDF • 2.85 MB
Tendernotice_3.pdf
PDF • 0.19 MB
TenderDocument2.pdf
Tender Documents • 0.58 MB
BOQ_1066308.xls
BOQ • 0.36 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .