Construction of Concrete Road RMC-25 at Girish Ghosh Road Bye lane near Thakuran Pukur from South East Corner to SouthWest corner of pond in ward no 23 under Bally Municipality. Length276.00 mtr.
2026_MAD_1042499_26
NIT/BM/00066/Eng/EO/2026-27
Open Tender
CIVIL WORKS
Percentage
14 days
Bally Municipality
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹58,708
18 Sept 2026
18 Sept 2026
5 Oct 2026
19 Sept 2026
3 Oct 2026
19 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Construction of Concrete Road (RMC-25) at Girish Ghosh Road Bye lane near Thakuran Pukur from South East Corner to South-West corner of pond in ward no - 23 under Bally Municipality. Length = 276.00 mtr. | |||||
| 1.01 | Picking up and removing old bituminous layer or sand sealing coat from old black topped surface and cleaning the exposed surface by scraping and stacking the material as directed. (a) By manual means : (i) From 25 mm to 50 mm thick. [Ref : P.W.D.(Rds), Page -321, Item-18.02] | 233.85 | M2 | 22.6 | ₹5,285.01 |
| 2 | Brick work with 1st class bricks in cement mortar (1:4) (a) In foundation and plinth [Ref: P.W.D (Bldg) 2017, Page - 15, Item.- 7] | 16 | M3 | 5,560 | ₹88,960 |
| 3 | 125 mm. thick brick work with 1st class bricks in cement mortar (1:4) in ground floor. [Ref : P.W.D (Bldg) 2017. Page- 16, Item- 16] | 14.38 | M2 | 722 | ₹10,382.36 |
| 4 | Wet Mix Macadam Base Course
Providing, laying, spreading and compacting
graded stone aggregate to Wet Mix Macadam
specification including screening of aggregates andgranular materials, premixing the material with waterat OMC in Wet Mix Plant, carriage of mixed materialby tipper to site, laying in uniform layers with Paver inSub- base / Base course on well prepared surfaceand compacting with Vibratory Roller to achieve thedesired density, including supply of all materials, machinery, fuel and lubricants, including incidental costs for lighting, guarding, barricading, making earthen bundh to protect the edges including cost of quality control complete as per Clause 406 of
Specifications for Road & Bridge Works of MoRT&H
(5th Revision). [Ref : P.W.D.(Rds), w.e.f 30.08.18 Page -249, Item-4.12] (Analysis Rate -22) | 180 | M3 | 2,454.1 | ₹4,41,738 |
| 5 | Supplying ready mixed concrete of M 25 Grade with well graded stone chips of 20 mm nominal size containing designed quantity of cement per Cu.m of wet concrete produced in computerised batching plant under controlled condition using approved super plastisizer, designing concrete mix following I.S. 10262 and I.S. 456, transporting the mix with agitation in transit mixer to work site depositing the mix on a platform erected for the purpose at required levels of concreting and then placing the mix in its final location of form work, compacting and curing the same complete as per specification & direction of the Engineer-in-charge including computerised batching plant transit mixer with all accessories vibrators etc. inclusive of all other incidental charges in this connection complete but excluding cost of hire charge of platform and its supporting staging which would be paid through separate item. [cement to be supplied by the Manufacturer/ supplier] In ground floor and foundation. (i) Without approved concrete pump in ground floor. [Ref : P.W.D.(Bldg.), Page-32, Item No. 18(i)] (Analysis rate -25) | 269 | M3 | 7,204.87 | ₹19,38,110.03 |
| 6 | Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if any, in ground floor as per relevant IS codes. (i) Pakur Variety [Ref: P.W.D (Bldg) 2017, Page-26 Item No- 10] Analysis no-23. | 3.5 | M3 | 6,031.38 | ₹21,109.83 |
| 7 | Hire and Labour Charges for shuttering with hard wood for precast R.C. Slab curved, or stright and striking out the same including fitting, fixing the precast slab in position with necessary carriage and haulage, hosting etc, complete in all respect. [Ref: P.W.D (Bldg) 2017, Page-43, Item No- 38] | 20.5 | M2 | 94 | ₹1,927 |
| 8 | Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction. (a) For works in foundation and upto roof of ground floor/upto 4 m (i) Tor steel/Mild Steel II. Other than SAIL/ TATA/RINL [Ref : P.W.D (Bldg) 2017, Page-43, 44 Item No. 40.a.(i).II] | 0.3 | MT | 58,515 | ₹17,554.5 |
| 9 | Filler joint providing & filling Joint sealing compound as per drawing & technical specification with coarse sand and 6% bitumen by weight. [PWD (Rds) Page 314, Item -14.13(iv)](Analysis rate-36) | 881 | MTR | 22.48 | ₹19,804.88 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 9.27 MB
BOQ_2558789.xls
BOQ • 0.31 MB
Cn_1042499_1_30.pdf
PDF • 0.88 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .