| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹21.0 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹22.8 L+₹46,650 (2.09%)Rejected-AOC | L2 | Rejected-AOC L2 | |
| 3 | L3₹36.7 L+₹14.4 L (64.6%)Rejected-AOC | L3 | Rejected-AOC L3 |
Tender Value
₹47 L
EMD Value
₹94,000
Closing Date
12 Oct 2021, 6:00 pmClosed
CWE (AF) Bhisiana
HQ CWE (AF) Bhisiana
REPAIR/ REPLACEMENT/ MAINT OF VCB/ SF6/ SERVO STABILIZER, ISOLATION, DISTRIBUTION, POWER TRANSFORMERS ALONG WITH CONNECTED ITEMS AT AF STATION BHISIANA
2021_MES_474916_1
CWE(BHI)/BHI-33/2021-22
Open Tender
Civil Works
Item Rate
270 days
AF Bhisiana
As Per cover 1
6 documents required · 6 mandatory
₹500
Yes
GE AF Bhisiana
₹94,000
Yes
28 Oct 2021
14 Sept 2021
14 Oct 2021
14 Sept 2021
12 Oct 2021
29 Sept 2021
14 Sept 2021 - 20 Sept 2021
Amount
M & L for online Dehyderation and filtration of transformer oil of servo voltage stabilizer, Isolation transformer, Distribution transformer & Power transformer etc of various capactiy, complete all as specified and as directed. Note: (i) Contractor will provide BDV test of transformer oil before and after filtration including dehyderation. (ii) After dehyderation and filteration BDV of transformer oil should not be less than 50KV at 2.5mm gap for 01 minute.
Supply & pouring of transformer oil with Dielectric strength not less than 60 KV including filling of transformer oil in any type of transformer and voltage stablizer located at workshop or any type of site, complete all as specified and as directed. Note :- Contractor will provide manufacturer test certificate of transformer oil for BDV test.
M&L for replacement of HT porcelain bushings set complete of distribution transformer including metal and rubber parts and replacing with new bushes complete of any make/size/type all as directed including dismantling upto 300 KVA, complete all as specified and as directed.
M&L for replacement of HT porcelain bushings set complete of distribution transformer including metal and rubber parts and replacing with new bushes complete of any make/size/type all as directed including dismantling for 300 KVA to 750 KVA, complete all as specified and as directed.
M&L for replacement of LT porcelain bushings set complete of distribution transformer/Isolation Transformer including metal and rubber parts and replacing with new bushes complete of any make/size/type all as directed including dismantling upto 300 KVA, complete all as specified and as directed.
M&L for replacement of LT porcelain bushings set complete of distribution transformer/Isolation Transformer including metal and rubber parts and replacing with new bushes complete of any make/size/type all as directed including dismantling for 300 KVA to 750 KVA, complete all as specified and as directed.
M&L for replacement of HT bushings set rod for distribution transformer made out of gun metal with threads upto suitable length of size all as per existing including metal rings/bolts/washers/rubber rings complete for the transformer capacity upto 300 KVA, complete all as specified and as directed.
M&L for replacement of HT bushings set rod for distribution transformer made out of gun metal with threads upto suitable length of size all as per existing including metal rings/bolts/washers/rubber rings complete for the transformer capacity above 300 KVA to 750, complete all as specified and as directed.
M&L for replacement of LT bushings set rod for transformer/Isolation Transformer made out of gun metal with threads upto suitable length of size all as per existing including metal rings/bolts/washers/rubber rings complete for the transformer capacity upto 315 KVA, complete all as specified and as directed.
M&L for replacement of LT bushings rod for transformer/Isolation Transformer made out of gun metal with threads upto suitable length of size all as per existing including metal rings/bolts/washers/rubber rings complete for the transformer capacity above 400 KVA to 750 KVA, complete all as specified and as directed.
M&L for replacement of silica gel including breather assembly complete for HT/LT distribution transformer of capacity 300 KVA to 750 KVA including dismantling, complete all as specified and as directed. Note:- Colour of the silica gel sholud be deep sky blue only.
M&L for replacement of silica gel including breather assembly complete for HT/LT distribution transformer upto capacity 300 KVA including dismanteling, complete all as specified and as directed. Note:- Colour of the silica gel sholud be deep sky blue only.
M&L for replacement of silica gel for transformer of any make/type for any capacity /make of transformer, complete all as specified and as directed. Note : Colour of silica gel should be deep sky blue only.
Replacement of top cover gasket of transformer/Isolation transformer suitable for any type/make./capacity upto 100 KVA to 300 KVA(make up of cork sheet 5mm thick), complete all as specified and as directed.
Replacement of top cover gasket of transformer suitable for any type/make./capacity above 300 KVA to 750 KVA(make up of cork sheet 5mm thick), complete all as specified and as directed.
M&L for replacement of oil temperature indicator including nuts, bolts and gasket including taking down complete upto 100 KVA, complete all as specified and as directed.
M&L for replacement of oil temperature indicator including nuts, bolts and gasket including taking down complete of capacity 125 KVA to 300 KVA, complete all as specified and as directed.
M&L for replacement of oil temperature indicator including nuts, bolts and gasket including taking down complete of capacity 400 KVA to 750 KVA, complete all as specified and as directed.
M&L for Scrapping/cleaning of outer surfaces of transformer and spray painting (smoke grey colour)with two coats of best quality synthetic enamel paint over one coat of red oxide primer complete including writing of MES No(white colour paint) all as directed by Engineer-in-Charge upto 750 KVA capacity transformer of any make/shape/size.
M&L for periodical testing of entire 66/11 KV substation with all the relays any type voltage, current, earth fault, over current including differential protection of 5 MVA + 5 MVA power transformers 66/11 KV. The progressive fault level setting of the relays should be set as per the PSPCL norms so that all the breakers will arrest the fault locally and fault should not be travell to PSPCL 66 KV substaion Bathinda under any condition.
M&L for periodical testing of all the relays any type voltage, current, earth fault, over current of 11KV HT switch gear panel.The progressive fault level setting of the relays should be set as per the primery substation norms so that all the breakers will arrest the fault locally and fault should not be travell to its primery substation under any condition.
Dismanteling the main power cable from HT 66/11 KV switch gear of any make/type and taking out the breaker trolly(any type) VCBs/RMU/SF6,cleaning from inside and outside by using CRC-26 spray or any other cleaning agent,greasing the moveable parts,complete serving of of switchgear including replacement of defectivesupport insulators of 11 KV bus bar. Including cleaning the fixed/moving contacts of all 3 phases adjusting electrical/electronic/Mechenical components all as per manufacturer instructions manual and the servicing and mantenance of switchgear shall be carried out by professional/competent/service enginer of the manufacturer in this field in the presence of AGE E/M. Note:- Test report of switch gear before and after its service.
Taking down defective transformer upto 500KVA capacity from pole/structure/sub-station after disconnecting the connections and shifting for inspection to sub-station then transporting the same to a manufacturer's workshop for repairs.After repairing the repaired transformer transporting back (including loading and unloading) to the directed location.After installing the transformer connections of LT and HT has to be done as directed by Eng-in-Charge and as specified in tender documents. Note :- (i) Test report of repaired transformer should be provided by the workshop before and after services. (ii) Contractor will provide guarrantee certificate of the repaired transformer that transformer will work trouble free at its full load Capacity minimum one year from the date of installtion at site after repair.
M&L for earthing complete with galvanized steel earth plate electrode 600mm x 600mm x 6mm thick buried directly in ground (earth pit not less than 2.25 meters deep below normal ground level) with top edge of plate not less than 1.5 meter deep below normal ground level connected to galvanized earth strip of size 25 x 4 mm, 7.5m long means of bolts, nuts, check nuts and washers of galvanized iron or steel all as shown in electrical plate No 3 of SSR part I connecting to earthing test point and testing on completion with and including PCC pit in mix 1:3:6 type c1 with PCC cover and, watering arrangement with funnel and wire mesh and 20mm bore light grade GI watering pipe, common salt and charcoal filling, necessary excavation and earth work, complete all as directed. Note : Earth pit should not be slide down.
Repairing and rewinding of transformer from certified company of cap up to 160 KVA incl following repairs : (i) Removing top cover of the transformer and taking out the complete core assembly from the transformer incl drain out the transformer oil from the transformer and clean the conservator and main tank. (ii) Cutting and removing the old burnt HT coil winding from the limbs and rewinding the limbs by new super enamelled copper wire as suitable size/ as per existing gauge and weight with proper insulation and varnishing complete and heating the coil in oven after winding. (iii) Cutting and removing the old burnt LT coil winding from the limbs and rewinding the limbs by new copper wire as suitable size/ as per existing gauge and weight with proper insulation and varnishing complete and heating the coil in oven after winding. (iv) Reassembling the complete core assembly and testing.
Repairing and rewinding of transformer from certified company of cap above 160 KVA and up to 250 KVA incl following repairs : (i) Removing top cover of the transformer and taking out the complete core assembly from the transformer incl drain out the transformer oil from the transformer and clean the conservator and main tank. (ii) Cutting and removing the old burnt HT coil winding from the limbs and rewinding the limbs by new super enamelled copper wire as suitable size/ as per existing gauge and weight with proper insulation and varnishing complete and heating the coil in oven after winding. (iii) Cutting and removing the old burnt LT coil winding from the limbs and rewinding the limbs by new super enamelled copper wire as suitable size/ as per existing gauge and weight with proper insulation and varnishing complete and heating the coil in oven after winding. (iv) Reassembling the complete core assembly and testing .
Repairing and rewinding of transformer from certified company of capacity 500 KVA incl following repairs : (i) Removing top cover of the transformer and taking out the complete core assembly from the transformer incl drain out the transformer oil from the transformer and clean the conservatorand main tank. (ii) Cutting and removing the old burnt HT coil winding from the limbs and rewinding the limbs by new super enamelled copper wire as suitable size/ as per existing gauge and weight with proper insulation and varnishing complete and heating the coil in oven after winding. `(iii) Cutting and remove the old burnt LT coil winding from the limbs and rewinding the limbs by new super enamelled copper wire as suitable size/ as per existing gauge with proper insulation and varnishing complete and heating the coil in oven after winding. (iv) Reassembling the complete core assembly and testing.
Repairing and rewinding of transformer from certified company of capacity 750 KVA incl following repairs : (i) Removing top cover of the transformer and taking out the complete core assembly from the transformer incl drain out the transformer oil from the transformer and clean the conservator and main tank. (ii) Cutting and removing the old burnt HT coil winding from the limbs and rewinding the limbs by new super enamelled copper wire as suitable size/ as per existing gauge and weight with proper insulation and varnishing complete and heating the coil after winding. (iii) Cutting and removing the old burnt LT coil winding from the limbs and rewinding the limbs by new super enamelled copper wire as suitable size/ as per existing gauge and weight with proper insulation and varnishing complete and heating the coil in oven after winding. (iv) Reassembling the complete core assembly and testing.
S & F in replacement digital type volt meter (0-500) volt including taking down of existing unserviceable volt meter, complete all as specified and as directed.
S&F digital type amp meter with CTs upto 0-400 Amp including taking out down existing unserviceable amp meter complete all as specified and as directed.
Taking down deffective Isolation Transformer/Voltage Stablizer upto 400KVA capacity from pole/structure/sub-station after disconnecting the connections and shifting for inspection to sub-station then transporting the same to a reputed work shop for repairs.After repairing, the repaired transformer transporting back (including loading and unloading) to the directed location.After installing the transformer connections of LT has to be done as directed by Engg.-in-Charge Note :- (i) Test report of repaired Isolation Transformer/Voltage Stablizer should be provided by the workshop before and after services. (ii) Contractor will provide guarrantee certificate of the repaired Isolation Transformer/Voltage Stablizer that transformer will work trouble free at its full load Capacity minimum one year from the date of installtion at site after repair.
Supply and fix in replacement of un-serviceable servo motor of voltage stablizer of capacity 10 KVA upto 50 KVA, complete all as specified and as directed.
Supply and fix in replacement of un-serviceable servo motor of voltage stablizer of capacity above 50 KVA to 150 KVA, complete all as specified and as directed.
Supply and fix in replacement of un-serviceable servo motor of voltage stablizer of capacity above 150 KVA to 250 KVA, complete all as specified and as directed.
Supply and fix in replacement of peripheral componenet board of voltage stablizer of capacity above 10 KVA to 50 KVA, complete all as specified and as directed.
Supply and fix in replacement of peripheral componenet board of voltage stablizer of capacity above 50 KVA to 150 KVA, complete all as specified and as directed.
Supply and fix in replacement of peripheral componenet board of voltage stablizer of capacity above 150 KVA to 250 KVA, complete all as specified and as directed.
Opening/stripping off voltage stablizer of capacity 10 KVA to 50 KVA including draining off oil, washing & cleaning duct, dit & sludge deposit etc. from all parts. Removing damaged/deffective parts requiring replacement,making internal connection servicing of bushings and reassembling the voltage stablizer after repair and replacement work including new cork gasket, packing nuts, bolts, washer, etc. complete all as directed. Note : Servicing will be done by reputated company rep at site only. Note :- (i) Test report of repaired voltage stablizer should be provided by the workshop before and after services. (ii) Contractor will provide guarrantee certificate of the repaired voltage stablizer that transformer will work trouble free at its full load Capacity minimum one year from the date of installtion at site after repair.
Opening/stripping off voltage stablizer of capacity 50 KVA to 150 KVA including draining off oil, washing & cleaning duct, dit & sludge deposit etc. from all parts. Removing damaged/deffective parts requiring replacement,making internal connection servicing of bushings and reassembling the voltage stablizer after repair and replacement work including new cork gasket, packing nuts, bolts, washer, etc. Complete all as directed. Note : Servicing will be done by reputated company rep at site only. Note :- (i) Test report of repaired voltage stablizer should be provided by the workshop before and after services. (ii) Contractor will provide guarrantee certificate of the repaired voltage stablizer that transformer will work trouble free at its full load Capacity minimum one year from the date of installtion at site after repair.
Opening/stripping off voltage stablizer of capacity 150 KVA to 250 KVA including draining off oil, washing & cleaning duct, dit & sludge deposit etc. from all parts. Removing damaged/deffective parts requiring replacement,making internal connection servicing of bushings and reassembling the voltage stablizer after repair and replacement work including new cork gasket, packing nuts, bolts, washer, etc. Complete all as directed. Note : Servicing will be done by reputated company rep at site only. Note :- (i) Test report of repaired voltage stablizer should be provided by the workshop before and after services. (ii) Contractor will provide guarrantee certificate of the repaired voltage stablizer that transformer will work trouble free at its full load Capacity minimum one year from the date of installtion at site after repair.
Supply and fix in replacement of dimmer state contact above 10 KVA to 50 KVA voltage stablizer, complete all as specified and as directed.
S&F in replacement of dimmer state contact above 50 KVA to150 KVA voltage stablizer, complete all as specified and as directed.
S&F in replacement of dimmer state contact above 150 KVA to 250 KVA voltage stablizer, complete all as specified and as directed.
S&F in replacement of auto manual switch suitable for any capacity/existing make for voltage stabilizer, complete all as specified and as directed.
S&F in replacement of indication lamp assy suitable for any capacity/existing make for voltage stabilizer, complete all as specified and as directed.
S&F in replacement of carbon set suitable for any capacity/existing make for voltage stabilizer, complete all as specified and as directed.
Repairing and rewinding of isolation transformer from certified company of cap up to 250 KVA incl following repairs : (i) Removing top cover of the isolation transformer and taking out the complete core assembly from the isolation transformer incl drain out the oil from the isolation transformer and clean the conservator. (ii) Cutting and removing the old burnt LT coil winding from the limbs and rewinding the limbs by new copper wire as suitable size/ as per existing gauge with proper insulation and varnishing complete and heating the coil after winding. (iii) Reassembling the complete core assembly and testing . Note :- (i) Test report of repaired isolation transformer should be provided by the workshop before and after services. (ii) Contractor will provide guarrantee certificate of the repaired isolation transformer that transformer will work trouble free at its full load Capacity minimum one year from the date of installtion at site after repair.
Repairing and rewinding of Voltage stablizer from certified company of cap up to 300 KVA incl following repairs : (i) Removing top cover of the Voltage stablizer and taking out the complete core assembly from the stablizer incl drain out the oil from the stablizer and clean the conservator. (ii) Cutting and removing the old burnt coil winding from the limbs and rewinding the limbs by new copper wire as suitable size/ as per existing gauge with proper insulation and varnishing complete and heating the coil after winding. (iii) Reassembling the complete core assembly and testing . Note :- (i) Test report of repaired Voltage stablizer should be provided by the workshop before and after services. (ii) Contractor will provide guarrantee certificate of the repaired Voltage stablizer that transformer will work trouble free at its full load Capacity minimum one year from the date of installtion at site after repair.
M&L for refilling of SF6 gas in 66 kv breakers, complete all as specified and as directed.
M&L for oil testing(OLTC and main chamber) of 5 MVA Power transformer as per IS code 1866-2017 for oil in service. The testing must include following type of tests- 1. Electric strength(BDV with 2.5mm gap) 2. Water content(ppm). 3. Specific resistance(resistivity)at 90 degree C. 4. Dielectric dissipation factor(tan delta) at 90degree C. 5. Neutralization value(total acidity). 6. Interfacial tension at 37 degrre C. 7. Flash Point 8 Sediment & /or sludge. 9. Dissolved gas analysis (DGA) of following gases- methene, ethylene, ethane, acetylene, carbon-dioxide, hydrozen. As per IS 10593-2006 NOTE:-1. ALL SAMPLES OF OIL MUST BE COLLECTED BOROCIL GLASS CONTAINERS OF PROPER SIZE. 2. CONTRACTOR WILL BE SOLELY RESPONSSIBLE FOR ANY DAMAGE HAPPEN TO THE TRANSFORMER AND WILL PAY FOR DAMAGE. 3. THE ALL TYPE OF OIL TESTING MUST BE DONE FROM Incharge OIL TESTING LABORATERY P.S.P.C.L. PATIALA Pin -147001. 4. THE HARD COPY(SIGNED BY GIVEN AUTHORITY) OF RESULTS WILL BE SUBMITTED BY CONTRACTOR.
Dissolved gas analysis (DGA) as per IS 10593-2006, complete all as specified and as directed.
Supply only HT insulation tape 9.1 meter, high voltage, non adhesive, complete all as specified and as directed.
Supply, install, commissioning and testing of outdoor HT feeder pillar box 3.15 mm thick CRCA sheet weather and vermin proof CPRI approved with copper busbar 800 amps suitable for HT cable 11 KV 3 core of size upto 185 sqmm including provision of cable entries with glands locking arrangements and angle iron frame and legs of 90 cm long using 60x60x6 mm size MS angle iron fixed in floor in PCC 1:4: 8 type D2 base of appropriate size including necessary excavation earth work including fincing with lockable gate, complete all as specified and as directed. Note :- All the cable entries should be through proper metallic cable glands only.
M&L for collecting oil samples in borosil sample collecting bottles capacity 1000 ml, complete all as specified and as directed.
M&L for excavating in post holes (or similar holes) each n exc 0.5 cum, getting out, returning, filling in and ramming earth or broken rubble mixed with earth around, in layers not exceeding 25cm, watering, and removing surplus soil to a distance n exc 50m and making good surface (soft/loose soil), complete all as specified and as directed.
M&L for PCC type B-2, 1:2:4( using 40mm graded stone aggregate) for foundation filling, mass concrete and etc, complete all as specified and as directed.
S&F Mild Steel works in: posts and struts in fencing including cutting tops to shape as directed, drilling holes, notching for wire, etc : flat iron fillets (for securing wire mesh etc.) including all necessary drilling, bolting or riveting, etc. and similar work conforming to FE-290 Gde E-165, complete all as specified and as directed
S&F as in repairs Chain link fencing 3.14mm dia and mesh size100mm x100mm complete including line wires of any mesh size and to any type standereds, rails, straining bolts etc including provisioning of binding wire including dismentling old, complete all as specified and as directed.
M&L for Mild steel in flat, round or square bars, in available lengths for secure fencing Fe 410-W (Gde-E-250) quality A, complete all as specified and as directed.
M&Lfor preparation of new steel surfaces of any description not otherwise described over 10cm width or grith and applying two coats of synthetic enamel paint over a coat of red oxide primer over new surfaces, complete all as specified and as directed.
Surface excavation not exc 30 cm deep and averaging 15cm deep and getting out in soft/loose soil, complete all as specified and as directed.
Removing excavated material (Soil) n.exc 50m and depositing where directed at a level n.exc 1.5 m above the starting point, complete all as specified and as directed.
Material and labour 75 mm thick Cement concrete type D-2, 1:4:8(40mm graded aggregate) as in base to flooring, complete all as specified and as directed.
Supply, laying and spreading uniformly 40 mm aggregate at substations inside fencing, complete all as specified and as directed.
M & L for HT cable fault finding with the help of fault finding machine in any type of soil condition, complete all as specified and as directed. Note :- Contractor will restore HT power supply after fault finding within maximum 24 hours after receiving the message from JE E/M or AGE E/M.
Material and labour for colour flex printing of distribution diagrams of HT nerworking upto A0 size colour flex sheet, complete all as specified and as directed.
Material and labour for replacement of defective HT CT's 200/100-5-5 in any type of HT switch gear including replacement of its defective control wiring and Ampere meter, complete all as specified and as directed.
Aman Enterprises
M/s Vee Kay Associates
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .