| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹27.9 CrAccepted-Finance 1 13 16 G KHAPARADEEH KOTHI CAMPUS CIVIL LINES AYODHYA UTTAR PRADESH 224001 | AYODHYA | AYODHYA | UTTAR PRADESH | 224001 | L1 | Accepted-Finance Qualified | |
| 2 | L2₹30.0 Cr+₹2.1 Cr (7.61%)Rejected-Finance NOT AVAILABLE | L2 | Rejected-Finance Disqualified | |
| 3 | L3₹30.3 Cr+₹2.4 Cr (8.64%)Rejected-Finance N A | L3 | Rejected-Finance Disqualified | |
| 4 | Rejected-Technical WATER WORKS ROAD BHIND M P 477001 | BHIND | BHIND | MADHYA PRADESH | 477001 | - | Rejected-Technical Disqualified |
Tender Value
₹32.9 Cr
EMD Value
₹16.4 L
Closing Date
16 Jan 2026, 5:00 pmClosed
COMMISSIONER OF UJJAIN MUNICIPAL CORPORATION
CCHTRAPATI SHIVAJI BHAWAN, AGAR ROAD UJJAIN
ROAD WIDENING WORK FROM MAKODIYA AAM NAKA AGAR ROAD TO KANIPURA ROAD VIA VIRAT NAGAR (UJJAIN)
2025_UAD_468978_1
20/Simhasth Cell/2025
Open Tender
Civil Works - Roads
Percentage
550 days
MAKODIYA AAM NAKA AGAR ROAD TO KANIPURA ROAD VIA
YES PLEASE REFER TENDER DOCUMENT
3 documents required · 3 mandatory
₹50,000
₹16.4 L
SUPRIDENTENT ENGINEER OFFICE UJJAIN NAGAR NIGAM
16 Mar 2026
17 Dec 2025
19 Jan 2026
17 Dec 2025
16 Jan 2026
29 Dec 2025
22 Dec 2025
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling of cement concrete pavement i/c breaking to pieces not exceeding 0.02 cum in volume and stock piling at designated locations and disposal of dismantled materials up to a lead upto 1000 meter, stacking serviceable and unserviceable materials separately and as per relevant clauses of section-200 | 1,500 | Cum | 749 | ₹11,23,500 |
| 2 | Dismantling stone slab roofing over wooden karries or R.C.C. battens (dismantling karries and battens to be paid for separately) ncluding stacking of serviceable material and disposal of unserviceable material within 50 meters lead. | 12,840 | Sqm | 788 | ₹1,01,17,920 |
| 3 | Dismantling tiled roofing with battens boarding etc. complete including stacking of serviceable material and disposal of unserviceable material within 50 meters lead. | 11,160 | Sqm | 62 | ₹6,91,920 |
| 4 | i) Girth from 300 mm to 600 mm | 50 | EACH | 364 | ₹18,200 |
| 5 | ii) Girth beyond 600 mm to 900 mm | 25 | EACH | 555 | ₹13,875 |
| 6 | iii)Girth beyond 900 mm to 1800 mm | 10 | EACH | 1,178 | ₹11,780 |
| 7 | Clearing and grubbing road land including uprooting rank vegetation, grass, bushes ,shrubs, saplings and trees girth upto 300mm, removal of stumps of trees cut earlier and disposal of unserviceable material sand stacking of serviceable material to be used or auctioned up to a lead of 1000 meter including removal and disposal of top organic soil not exceeding 150 mm in thickness if required and as per relevant clauses of section-200. (a) In area of light jungle | 2.5 | Hectare | 98,718 | ₹2,46,795 |
| 8 | Roadwork in soil
Excavation for roadwork in soil with hydraulic excavator including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location with all lifts and lead upto 1000m as per relevent clauses of section-300 of specification. | 8,064.94 | Cum | 122 | ₹9,83,922.07 |
| 9 | Construction of embankment as per provisions of Section 305 with approved materials obtained from borrow pits confirming to requirements given in Table 301-1 of the specifications with all lifts and lead up to 2500 m, including transportation to site, watering, compaction by vibratory roller/heavy pneumatic type roller etc. confirming to requirements given in Table 301 2 of the specifications. | 32,513.91 | Cum | 303 | ₹98,51,714.73 |
| 10 | Construction of Embankment/Sub-grade/Earthen Shoulders with material obtained from other sources, as per provisions of Section 305 of the specifications, with approved materials/soil confirming to
requirements given in Table 301-1 of specifications including all lead and lifts, including cost of watering, compaction by vibratory roller/heavy pneumatic type roller etc. confirming to requirements given in Table 301 2 of the specifications complete. | 14,030 | Cum | 432 | ₹60,60,960 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.73 MB
tenderdocument.pdf
Tender Documents • 1.73 MB
BOQ_551557.xls
BOQ • 0.46 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .