Tender Value
₹16.9 L
EMD Value
₹16,913
Closing Date
16 Jun 2026, 5:00 pm
EXECUTIVE OFFICER
OFFICE OF THE EXECUTIVE OFFICER,NAC RANPUR
CONSTRUCTION OF BOUNDARY AT BACK SIDE OF MCC MRF
2026_ORULB_131019_24
RNPNAC-02/2026-27
Open Tender
Civil Works - Others
90 days
NAC RANPUR
Please refer Tender documents.
2 documents required · 2 mandatory
₹6,000
₹16,913
Yes
5 Jun 2026
5 Jun 2026
17 Jun 2026
5 Jun 2026
16 Jun 2026
5 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1 | Earthwork excavation in foundation in hard soil including rough dressing and levelling the bed by depositing soil within initial lead and lift . | 1 | Cum | 1 | ₹1 | BI01010001010000000000000515BI0100001118 |
| 2 | Supplying and filling Sand in foundation and on Road Surface including watering and ramming with Cost, Conveyance and Royalty of all materials etc.initial lead and lift . | 12.05 | Cum | 1,020.8 | ₹12,300.64 | - |
| 3 | Cement Concrete in (1:3:6) using 40mm size Hard GraniteC.B. metal in foundation Bed and Road including watering, curring with Cost, Conveyance and Royalty of all materials etc. allcomplete . | 14.99 | Cum | 6,326.1 | ₹94,828.24 | - |
| 4 | Fly Ash Brick masonary with Flyash Bricks of 25cm.x 12cm.x 8cm. size having crushing strength not less than 75 Kg/Cm2 in cement mortar (1:6) in F&P including cost, conveyance, taxes & royalties of all materials, labour with T&P etc. complete in all respect.[A/R-2006,Page-71, Item no.03] | 19.22 | Cum | 5,613.6 | ₹1,07,893.39 | - |
| 5 | Reinforced Cement concrete work of M-20 grade with 20mm & down grade black hard granite ( Crusher broken ) stone chips including hoisting & laying including cost, conveyance& royalty of all materials and labour with T&P etc. complete in all respect.
Column Footing | 9.72 | Cum | 6,827.6 | ₹66,364.27 | - |
| 6 | Plinth Beam | 1 | Cum | - | - | - |
| 7 | Column | 8.01 | Cum | 18,641.2 | ₹1,49,316.01 | - |
| 8 | Straightening, cutting, bending, binding tor steel rods, cranking, hooking, tying the grills & placing in proper position for R.C.C work, including cost of binding wires of 18 to 20 gauge, cost, conveyanceof steel and all other materials, cost of all labour with T&P required for the work etc. complete.[A/R-2006,Page-52, Item no.9(A)] | 23.06 | Qtl | 9,574.13 | ₹2,20,779.44 | - |
| 9 | Fly Ash Brick masonary with Flyash Bricks of 25cm.x 12cm.x 8cm. size having crushing strength not less than 75 Kg/Cm2 in cement mortar (1:6) in superstructure including cost, conveyance& royalties of all materials, labour with T&P etc. complete in all respect. | - | Cum | 5,646.97 | - | - |
| 10 | 16mm thick cement plaster in cm (1:6) finished smooth to brick or stone masonry including cost, conveyance, taxes, royalties, labour with T&P etc. complete in all respect.[A/R-2006,Page-105, Item no.14] | 1 | Sqm | 283.1 | ₹282.82 | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 3.51 MB
BOQ_594592.xls
BOQ • 0.25 MB
Download all tender documents and submit your bid