Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.0 LAccepted-AOC | ₹3.0 L | L1 | Accepted-AOC L1 Tender Accept |
| 2 | Rejected-Technical | - | - | Rejected-Technical Tender Reject |
| Sl No | Description | Qty | Unit | Shobana S L2 | V NAVEENKUMAR L1 |
|---|---|---|---|---|---|
| 1.00Providing Cement Concrete Side Drainage with RCC Slab Culvert to JJ Nagar street at Amoor Panchayat @ Thiruporur Panchayat Union in Chengalpattu District for the Year 2025-26 having Package No .3/2025-26 scheme of Panchayat Funds | |||||
| 2.00 | Earth work excavation in hard stiff clay soil with initial lead and lift as per SS20B etc complete. | 19.89 | cum | 300 ₹5,967 | 263 ₹5,231.07 Lowest |
| 3.00 | C.C. 1:4:8. Mix using 40MM ISS HBG metal including cost and conveyance and all other labour charges etc.complete. | 4.42 | cum | 5,356 ₹23,673.52 Lowest | 5,356 ₹23,673.52 Lowest |
| 4.00 | Towards the labour charges for centring the C.C.Works including all other labour charges etc complete. | 31.2 | Sqm | 547 ₹17,066.4 Lowest | 547 ₹17,066.4 Lowest |
| 5.00 | C.C. 1:2:4. Mix using 20MM ISS HBG metal including cost and conveyance and all other labour charges etc.complete. | 5.85 | cum | 6,659 ₹38,955.15 Lowest | 6,659 ₹38,955.15 Lowest |
| 6.00 | Plastering with cm 1:4 20mm thick including cost and conveyance and all other labour charges etc.complete. | 7.8 | Sqm | 600 ₹4,680 | 587 ₹4,578.6 Lowest |
| 7.00 | Painting with Two Coat Plastic Emulsion Paint including cost and conveyance and all other labour charges etc.complete. | 23.4 | Sqm | 262 ₹6,130.8 Lowest | 262 ₹6,130.8 Lowest |
| 8.00 | Earth work excavation in hard stiff clay soil with initial lead and lift as per ss20B etc.Complete. | 26.71 | cum | 263 ₹7,024.73 Lowest | 263 ₹7,024.73 Lowest |
| 9.00 | C.C. 1:4:8. Mix using 40MM ISS HBG metal including cost and conveyance and all other labour charges etc.complete. | 5.72 | cum | 5,356 ₹30,636.32 Lowest | 5,356 ₹30,636.32 Lowest |
| 10.00 | Towards the labour charges for centring the C.C.Works including all other labour charges etc complete. | 32.37 | Sqm | 547 ₹17,706.39 Lowest | 547 ₹17,706.39 Lowest |
Tender Value
₹3 L
EMD Value
₹3,000
Closing Date
27 Dec 2025, 9:00 amClosed
Block Developement Officer BP
Block Developement Office Thiruporur
Providing Cement Concrete Side Drainage with RCC Slab Culvert to JJ Nagar street at Amoor Panchayat at Thiruporur Panchayat Union in Chengalpattu District for the Year 2025-26 having Package No .3/2025-26 scheme of Panchayat Funds
2025_RDTN_636355_1
RCNO 3058/2024/A2/26.5.2025
Open Tender
Civil Works - Others
Item Rate
Amoor
Please refer Tender documents.
1 document required · 1 mandatory
₹0
₹3,000
Yes
Block Developement Office Thiruporur
11 Sept 2026
26 Dec 2025
27 Dec 2025
26 Dec 2025
27 Dec 2025
26 Dec 2025
26 Dec 2025
Providing Cement Concrete Side Drainage with RCC Slab Culvert to JJ Nagar street at Amoor Panchayat @ Thiruporur Panchayat Union in Chengalpattu District for the Year 2025-26 having Package No .3/2025-26 scheme of Panchayat Funds
Earth work excavation in hard stiff clay soil with initial lead and lift as per SS20B etc complete.
C.C. 1:4:8. Mix using 40MM ISS HBG metal including cost and conveyance and all other labour charges etc.complete.
Towards the labour charges for centring the C.C.Works including all other labour charges etc complete.
C.C. 1:2:4. Mix using 20MM ISS HBG metal including cost and conveyance and all other labour charges etc.complete.
Plastering with cm 1:4 20mm thick including cost and conveyance and all other labour charges etc.complete.
Painting with Two Coat Plastic Emulsion Paint including cost and conveyance and all other labour charges etc.complete.
Earth work excavation in hard stiff clay soil with initial lead and lift as per ss20B etc.Complete.
C.C. 1:4:8. Mix using 40MM ISS HBG metal including cost and conveyance and all other labour charges etc.complete.
Towards the labour charges for centring the C.C.Works including all other labour charges etc complete.
C.C. 1:3:6. Mix using 40MM ISS HBG metal including cost and conveyance and all other labour charges etc.complete.
Towards the labour charges for centring the R. C.C.Works including all other labour charges etc complete.
Supply and Fabrication of steel including all labour charges etc.
R.C.C. 1:1.5:3. Mix using 20MM ISS HBG metal including cost and conveyance and all other labour charges etc.complete.
C.C. 1:2:4. Mix using 20MM ISS HBG metal including cost and conveyance and all other labour charges etc.complete.
GST Amount for providing Service to Government Contract Works for the above Construction Works. {GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_761527.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.17 MB
BOQ_761527.xls
BOQ • 0.26 MB
Technical.pdf
Tender Documents • 0.50 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .