CE WR Zone, Kota
CE WR Zone, Kota
Repairing of Sorkhand Talab and Construction of drainage channel at downstream of Sorkhand Talab Tehsil Anta District Baran
2026_WRDAS_602513_1
CE WR Zone Kota NIB NO-17-2026-27
Open Tender
Civil Works
Percentage
180 days
Baran
Please refer Tender documents.
2 documents required · 2 mandatory
₹5,000
EE WR Div-I, Baran
₹6.4 L
Yes
1 Oct 2026
1 Oct 2026
23 Oct 2026
1 Oct 2026
22 Oct 2026
1 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Re-handling of excavated material including loading unloading and dressing within initial lead of 50 m and lift of 1.5m with cost of dewatering wherever required and all applicable taxes and levies etc. complete in all respect Earth / Soil Cum | 2,763 | Cum | 73 | ₹2,01,699 |
| 2 | Watering of earth including cost of carriage of water when source of water is up to 1 Km | 6,126 | Cum | 11 | ₹67,386 |
| 3 | Providing and Laying in position of Cement concrete Design mix M-15 including leads of all construction materials, plasticizers (if required), curing, compaction and finishing with rendering in cement sand mortar 1:3 (1 cement : 3 coarse sand) and making good the joints excluding the cost of centering, shuttering and reinforcement. Well graded crusher broken stone aggregate of maximum size upto; (For mix design Cement content considered 320 kg/ cum of concrete) 20 mm | 3,248.83 | Cum | 5,226 | ₹1,69,78,385.58 |
| 4 | Providing and Laying in position of Cement concrete Nominal mix (1:3:6) including leads of all construction materials, curing, compaction and finishing with rendering in cement sand mortar 1:3 (1 cement : 3 coarse sand) and making good the joints excluding the cost of centering, shuttering and reinforcement. Well graded crusher broken stone aggregate of maximum size upto 40 mm | 655.8 | Cum | 4,624 | ₹30,32,419.2 |
| 5 | Excavation including loading, unloading, disposal and dressing of excavated earth within initial lead of 50m and lift up to 1.5m including dressing of excavated area and dewatering wherever required complete in all respect. Hard soil mixed with Kankar / boulders, Morrum | 6,907.5 | Cum | 99 | ₹6,83,842.5 |
| 6 | Providing, laying and fixing in position RCC spun or hume pipe with collars (ISI 458-2003) in required size packed in gasket for hume or spun yarn and neatly finished with rich grout of cement mortar 1:3 perfectly air tight including testing of joints. (diametre) 600mm ( Excluding Labour Charges ) NP-3 Providing, laying and fixing in position RCC spun or hume pipe with collars (ISI 458-2003) in required size packed in gasket for hume or spun yarn and neatly finished with rich grout of cement mortar 1:3 perfectly air tight including testing of joints. (diametre) 600mm (Labour Charges only) | 37.5 | RM | 3,329 | ₹1,24,837.5 |
| 7 | Extra labour charges for RCC due to obstruction in laying and placing the reinforced cement concrete due to reinforcement. In foundation rafts, beams, columns bases stilling basins, buckets, aprons etc. (non suspended horizontally laid mass concrete) | 3,248.83 | Cum | 140 | ₹4,54,836.2 |
| 8 | Side shuttering including propping etc. complete (to achieve finish F 2 for Retaining wall, counterfort, abutment, wing walls up stream or down- stream slope facings of dams and open faces of construction joints etc. | 4,668 | sqm | 220 | ₹10,26,960 |
| 9 | Plaster in cement sand mortar 1:4 including racking of joints, smooth finishing & curing etc. complete including all leads of all construction materials of thickness: 20 mm | 48 | Sqm | 283 | ₹13,584 |
| 10 | Compaction of earth or highly weathered strata By mechanical equipment such as sheep foot roller/ pneumatic tyred roller/vibro compactor / vibro sheep foot compactor required as per site condition to obtain dry density of. (i) at least 95% of Standard Proctors density | 6,126 | Cum | 33 | ₹2,02,158 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.26 MB
Tendernotice_2.pdf
PDF • 3.54 MB
BOQ_1068090.xls
BOQ • 0.23 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .