| # | Company | Status |
|---|---|---|
| 1 | Accepted-Technical | Accepted-Technical accept |
| 2 | Accepted-Technical 1 306 VISHAL KHAND GOMTI NAGAR LUCKNOW | GHAZIABAD | UTTAR PRADESH | 201001 | Accepted-Technical accept |
| 3 | Accepted-Technical | Accepted-Technical accept |
Tender Value
₹16 L
EMD Value
₹32,300
Closing Date
1 Jul 2026, 5:00 pmClosed
executive director(NIRMAN)
U.P.COOPERATIVE FEDERATION LTD,32 STATION ROAD, LUCKNOW-226001
Construction of Gable wall of 1200 MT Capacity P.C.F. Godown at PAIDA Distt. BASTI
2026_UPPCF_1161308_5
885_UPPCF_2026_15062026
Open Tender
Civil Works
Percentage
90 days
PAIDA Distt. BASTI
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,298
U.P.COOPERATIVE FEDERATION LTD
₹32,300
8 Jul 2026
17 Jun 2026
2 Jul 2026
17 Jun 2026
1 Jul 2026
17 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Construction of Gable wall of 1200 M.T. Capacity P.C.F. Godown at. Paida District. Basti. | |||||
| 1.01 | Dismentelling brick work or stone work in lime or cement, mortorinluding stacking of material as directed by E./I with in a distance of 60 m. | 26.33 | CUM | 1,559.57 | ₹41,063.48 |
| 1.02 | Excavation in foundation of ordinary soil (Loam clay or sand) including lift up to 1.5 M. and lead up to 30M. and including filling watering and ramming of excavated earth into the trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer in charge up to a distance of 30 M from the foundation trenches. | 44.8 | CUM | 134.37 | ₹6,019.78 |
| 1.03 | Concrete with 4Cm. Gauge over burnt brick ballast with fine sand and cement in proportion of 10:5:1 in foundation including supply of all materials, labour, T&P etc. required for proper completion of work. | 12.17 | CUM | 4,934.58 | ₹60,053.84 |
| 1.04 | R.C.C work with cement, approved coarse sand and 2 cm. gauge approved stone ballast in the proportion 1:1.5:3 in foundation and footings excluding supply of reinforcement and its bending but including its fixing and binding the same with 24 B.W.G. binding wire and including necessary centering and shuttering etc. and including supply of all materials, labour, T&P etc. required for proper completion of work. (Binding wire to be supplied by contractor free of cost.) | 15.51 | CUM | 6,847.63 | ₹1,06,206.74 |
| 1.05 | First class brick work in 1:6 cement and coarse sand of 2.20 fineness modulus mortar in foundation and plinth including supply of all materials, labour, T&P etc. required for proper completion of work. | 15.77 | CUM | 5,399.11 | ₹85,143.96 |
| 1.06 | R.C.C work with cement approved coarse and 2 cm. gauge approved stone ballast in the proportion 1:1.5:3 in columns excluding supply of reinforcement and its bending including supply of all materials and T&P etc. required for proper completion of work up to all lead and lift, binding wire to be supplied by the contractor free of cost including necessary centering and shuttering. | 7.77 | CUM | 8,215.68 | ₹63,835.83 |
| 1.07 | First class brick works in 1:6 cement and coarse sand of 2.20 fineness modulus mortar, including necessary cutting and including moulding of brick as required Thickness of walls of all size including supply of all labor, materials for superstructure and T&P etc. required for proper completion of work with all lead and lift. | 54.78 | CUM | 6,893.2 | ₹3,77,609.5 |
| 1.08 | 12 mm. thick plaster in 1:6 cement and coarse sand in (2.20 F.M) mortar in plinth, inside and outside of godown including supply of all materials, labour, T&P etc. required for proper completion of work. | 471.75 | SQM | 270.51 | ₹1,27,613.09 |
| 1.09 | 1- 1/2 (4 cm.) thick 1:2:4 plain cement concrete floor with cement approved coarse sand and (3/4) 2cm. graded approved stone grit laid in pannelswith out base concrete including removing any overlapping mortar at joints of panel including supply of all materials, labour, T&P etc. required for proper completion of work. | 42.7 | SQM | 464.95 | ₹19,853.37 |
stage.html
html • 0.02 MB
tech_bid_open.pdf
tech_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.22 MB
TECHNICAL.pdf
Tender Documents • 1.23 MB
BOQ_2176943.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .