WC-007/2022-23 33 KV LINE Augmentation Ottanatham
2022_EB_233206_3
WC-007/2022-23 33 KV LINE Augmentation Ottanatham
Open Tender
Electrical Works
Item Rate
120 days
Tuticorin
Refer tender document
2 documents required · 2 mandatory
₹0
₹22,000
Yes
23 Jun 2022
8 Jun 2022
16 Jun 2022
8 Jun 2022
15 Jun 2022
8 Jun 2022
8 Jun 2022 - 15 Jun 2022
Amount
Excavation of Stay pit 4.5' to 5' depth by using JCB or manual
Excavation of pole pit upto 9.14 mtr Pole by using JCB or manual
Excavation of RSJ pole pit above 42' by using JCB or manual
Erection of 9 mtr PSC poles by using JCB or maual
Erection of RSJ Rail, fabricated poles above 36'-0' by using JCB or maual
Erection of stay set complete
Fixing of 5" "V" cross arms (all types) / channel cross arms/ guarding Cross arms
Tapping X arm
Fixing of HT/LT TI Fittings
Fixing of pin Insulators with Pin 33 KV
Fixing of 11 KV strain disc.
Painting and numbering of poles (existing & new)
Earthing of pole with pin including burying looping and binding
Paving of Conductor, stringing, binding Jumpering etc., complete with Dog conductor for both HT lines with LC work.
Concreting of Poles as per Board standards (2*2*5). The material such as sand, jelly, etc., have to be supplied by contractor including Cement supplied by Contractor (Cement concrete mix 1:4:8 using 40mm hard broken stone including cost of labour Charges for placing Transporting of Sand, jally, from box and water curing etc,. complete as per field Engineer's instructions.
Transport of poles/Materials/ conductors and other materials from store to site ( for Hired Vehicle) beyond 20KM
Loading/Unloading of poles upto 9 mtr PSC poles & RCC Square Pole
Loading/Unloading of poles above 36'-0' RSJ pole
Dismantling of 7/3.35sq.mm ACSR with LC work
Dismantling of 9 mt Poles
Removing the HT TI fitting
Removing the HT pin Insulators with pin
Alteration of Stay clamp
Erection of D.P. structure with AB switch top channel, cross bracing, HG fuse set, earthing, painting, providing stay and pole concreting as per field Engineer's instructions.
Alteration of Back clamp
Aluminium painting including labour,materials,lead,lift etc., for all types of x arm/channel/clamps/Bolt & Nut Etc., for above works
Cutting of coconut leaves (per tree)
Drilling of hole in channel only 3/4" & 1" etc., per hole
E.P.F. @13 % should be Entered by the Bidder
E.S.I. @3.25 % should be Entered by the Bidder
G.S.T. @18% should be Entered by the Bidder
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .