Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹22.4 LAccepted-AOC | ₹22.4 L | 1 | Accepted-AOC L1 |
| 2 | 2₹24.2 LRejected-Finance SIMDEGA | NA | NA | 835201 | ₹24.2 L | 2 | Rejected-Finance L2 |
Tender Value
₹28.8 L
EMD Value
₹58,000
Closing Date
7 Jan 2026, 2:00 pmClosed
AMC CMC Chas
Office of the Additional Municipal Commissioner Chas municipal corporation, ITI More Chas
CONSTRUCTION OF 16 Nos. SCREENING CHAMBER AND SILT CHAMBER AT DIFFRENT LOCATIONS OF CHAS MUNICIPAL CORPORATION
2025_UDD_108243_1
UDD/CMC/15/2025-26
Open Tender
Civil Works
Percentage
90 days
CHAS
Please refer Tender documents.
2 documents required · 2 mandatory
₹10,000
₹58,000
8 Jun 2026
27 Dec 2025
8 Jan 2026
27 Dec 2025
7 Jan 2026
27 Dec 2025
Earthwork in excavation in foundation trenches in ordinary soil (vide classification of soil item-A) and disposal of excavated earth as obtained to a distance upto 50 M. including all lifts, levelling, ramming the foudation trenches, removing roots of trees, shrubs all complete as per approved design, building specification and direction of E/I.
Providing coarse clean sand in filling in foundation trenches or in plinth including ramming and watering in layers not exceeding 150mm thick with all leads and lifts including' cost of all materials, labour, royalty and taxes all complete as per building specification and direction of E/I (Mode of measurement complacted volume).
Providing designation 75 B one brick flat soling joints filled with local sand including cost of watering taxes royalty all complete as per building specification and direction of E/I.
Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing:1:2:4 (1 Cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mmnominal size)
Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size).
centring and shuttering including strutting, propping etc remove of form for, foundation footing, base of column etc for mass concrete
providing Tor steel reinforcement of 8mm dia rods as per approved design and drawing exclusive carriage of M.S. bars to work site, cutting, bending and binding with annealed wire with cost of the wire, removal of rust, placing the rods in position all complete as per building specification and direction of E/I. TMT Fe 500 (only valid for SAIL & TATA STEEL)
Providing Tor steel reinforcement of 10mm., 12mm & 16mm dia. bars as per approved design and drawing excluding carriage of M.S. bars to work site, cutting, bending and binding with annealed wire with cost of wire, removal of rust placing the rods in position all complete as per building specification and direction of E/I.
Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required in gratings, frames, guard bar, ladder, railings, brackets, gates and similar work.
supplying and fixing C.l. cover without frame for manholes : 455x610 mm rectangular C.I. cover (light duty) the weight of the cover to be not less than 23 kg
Earthwork in excavation in foundation trenches in ordinary soil (vide classification of soil item-A) and disposal of excavated earth as obtained to a distance upto 50 M. including all lifts, levelling, ramming the foudation trenches, removing roots of trees, shrubs all complete as per approved design, building specification and direction of E/I.
Providing coarse clean sand in filling in foundation trenches or in plinth including ramming and watering in layers not exceeding 150mm thick with all leads and lifts including' cost of all materials, labour, royalty and taxes all complete as per building specification and direction of E/I (Mode of measurement complacted volume).
Providing designation 75 B one brick flat soling joints filled with local sand including cost of watering taxes royalty all complete as per building specification and direction of E/I.
Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing:1:2:4 (1 Cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mmnominal size)
Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size).
centring and shuttering including strutting, propping etc remove of form for, foundation footing, base of column etc for mass concrete
providing Tor steel reinforcement of 8mm dia rods as per approved design and drawing exclusive carriage of M.S. bars to work site, cutting, bending and binding with annealed wire with cost of the wire, removal of rust, placing the rods in position all complete as per building specification and direction of E/I. TMT Fe 500 (only valid for SAIL & TATA STEEL)
Providing Tor steel reinforcement of 10mm., 12mm & 16mm dia. bars as per approved design and drawing excluding carriage of M.S. bars to work site, cutting, bending and binding with annealed wire with cost of wire, removal of rust placing the rods in position all complete as per building specification and direction of E/I.
supplying and fixing C.l. cover without frame for manholes : 455x610 mm rectangular C.I. cover (light duty) the weight of the cover to be not less than 23 kg
Laying and Jointing PVC Pipe. Heading
CEMENT (5 KM)
SEND (3 KM)
BRICKS (8 KM)
AGGREGATES (22 KM)
ADD GST
ADD L.CESS
The Total 16 NOS
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_146158.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 6.31 MB
BOQ_146158.xls
BOQ • 0.41 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].