| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹18.1 LAccepted-AOC VILL P O AMJAI BARDHAMAN BARDHAMAN 713203 WEST BENGAL INDIA | BARDHAMAN | BARDHAMAN | WEST BENGAL | 713203 | L1 | Accepted-AOC L1 | |
| 2 | L2₹18.4 L+₹33,305.19 (1.85%)Rejected-Finance | L2 | Rejected-Finance L2 | |
| 3 | L3₹18.7 L+₹68,213.96 (3.78%)Rejected-Finance | L3 | Rejected-Finance L3 |
Tender Value
₹18.1 L
EMD Value
₹22,600
Closing Date
26 Jul 2024, 11:00 amClosed
AREA ENGINEER EnM, JHANJRA AREA
OFFICE OF THE GENERAL MANAGER, JHANJRA AREA, PO-LAUDOHA, BO, DIST. - PASCHIM BARDHAMAN, PIN-713385
Transportation, installation, necessary fabrication, commissioning and trial run including extension of one no. 1000mm width, 2X150KW, 6.6KV, dual drive belt conveyor along 66L from 8R to 16R in R-VII seam at 3n4 Incline, J.P.Colly
2024_ECL_312438_1
ECL/GM/JNR/EnM/A2/24-25/44 dated 08.07.2024
Open Tender
Miscellaneous Works
Item Rate
60 days
JHANJRA UNDERGROUND
Please refer Tender documents.
4 documents required · 4 mandatory
₹22,600
29 Jul 2025
15 Jul 2024
27 Jul 2024
15 Jul 2024
26 Jul 2024
16 Jul 2024
15 Jul 2024 - 22 Jul 2024
Amount
PART A:Transportation, Installation, Commissioning & Trial Run of one 1000mm width, 2X150KW, 6.6KV, dual drive belt conveyor along 66L from 8R to 66L/11R in R-VII seam at 3&4 Incline, J.P. Colly.
Fabrication of loop take up frame of drive head at surface
Fabrication of Tail End Unit for 66L belt
Transportation of the 1000mm width, 2X150KW, 6.6kV, double Drive Head unit Complete with Drive Drum, Driven Drum, Gear Box, Motor, Couplings, Bearing Blocks, baseplate, fencing etc. from surface and installation at 66L/9D (R-VII) with necessary fabrication job.
Transportation of Discharge Unit complete with girders, strike plate, chute plates, scrappers etc. from surface and installation at 66L/8D (R-VII) with necessary fabrication job.
Transportation and Installation of Loop Take-up Unit Complete, with Fencing from surface and install at 66L/9D
Transportation of Tail End Unit complete with fencing from surface and installation at 66L/11D (R-VII) with necessary fabrication job.
Transportation of 103.5mtr. 1000mm belt conveyor structure complete with stringer, foot stool, top bracket, top & bottom roller etc. from surface to 66L belt installation site and installation from 66L/8D to 66L/11D in R-VII seam.
Loading, transportation and unloading of two VCB(6.6KV/30A), starter(6.6KV/2X150kW), LS unit from surface to 73L/8D and 66L/9R (R-VII) with help of haulages & 100 mtr manually. (Distance- approx. 3800mtr.)
Laying-hanging of 250mtr 6.6kV grade 70 sq.mm. PVCDWA cable from 73L/8R ACB to 66L/9R ACB manually.
Transportation of 207mtr. 1000mm width PVC belting from surface to 66L belt installation site with help of haulages & 100mtr manually. (Distance- approx. 3800mtr.)
Laying, lapping, jointing & tensioning of this 207mtr. 1000mm width PVC belting in proposed 66 belt.
Transportation of 500mtr belt sequence cable from surface to 72L/8D (R-VII); then laying-placing them from 72L/8D starter to 66L/9D starter in R-VII seam
Transportation of pull cords with its cable, communication devices with its cable, signaling system (8-SWG GI wire, bobbin insulators & 3/8" X 3" MS bolt-nut) from surface to 66L belt installation site with help of haulages for 103.5mtr. belt and laying-placing them from 66L/8D to 66L/11D in R-VII seam.
Testing, trial run, alignment & commissioning of this belt conveyor from 66L/8D to 66L/11D in R-VII seam.
Supply of DA cylinder
Supply of Oxygen cylinder
Supply of M.S. welding electrode (4 mm x 450 mm)
Supply of M.S. Hex. Nut & Bolt (M 16 x 50)
Supply of M24 x 150 H.T. Hex. nut and bolt
Supply of M20 x 65 H.T. Hex. Bolts with Nuts
Supply of M16 X 50 H.T. Hex. Bolts with Nuts
Supply of M.S. Nut & Bolt (M16x50)
PART B:Five times extension for a length of 172.5mtr. from 66L/11R to 66L/16D in R-VII seam. Each time belt extension will be for a length of 34.5mtr.
Transportation of 1000mm belt structures (i.e. foot stools, channels, brackets, top and bottom rollers etc.) for a length of 172.5mtr. from surface to belt extension site by haulages and installation them from 66L/11D to 66L/16D in R-VII seam during seven times belt extension.
Five times Dismantling, transportation and installation of tail end unit Complete from 66L/11R to 66L/16R for five times 66L belt extension
Transportation of 345mtr. (approx) 1000mm PVC belting from surface through haulages & 100mtr. manually to 66L(R-VII) belt extension site. (Distance- approx. 3900mtr.)
Laying, Lapping, Jointing & Tensioning of this 345 mtr. 1000mm belting from 66L/11R to 66L/16R in R-VII seam during six times belt extension and trial run.
Transportation of pull cords with its cable, communication devices with its cable, signalling system (8-SWG GI wire, bobbin insulators & (3/8"x3") MS Bolt-nut) for 173 mtr. belt from surface to 66L belt extension site and laying & fitting them during five times belt extension.
Shortening of loop take up unit by removing extra belt from loop take up unit
Shortening of loop take up unit by removing extra belt from loop take up unit after every two times extension
Supply of MS NUT BOLT (M16 x 50)
PART C:Civil foundation works for installation of 1000mm wide belt conveyor head, discharge unit, loop take-up unit and platform for VCB, Starter for proposed 66L belt conveyor of 3&4 incline, JPC.
Recess cutting in stone
Muck & debris cleaning & disposal up to 15.0 M
Supplying and filling in plinth with sand under floors, including watering, ramming,consolidating and dressing complete.
Brick work with Fly ash bricks of class desgn 75 in foundation and plinth in: CM 1:6 (1 cement : 6 coarse sand)
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:2:4 (1 cement : 2 coarse sand(zone-III) : 4 graded stone aggregate 20 mm nominal size)
12 mm cement plaster of mix : 1:6 (1 cement: 6 fine sand)
Loading of materials into Tub,lowering & unloading at site(Tubs)
PART D:Roof heightening by drilling blasting in stone, cleaning, roof bolting including cost of drill rod, drill bit for installation of proposed 66L belt conveyor in R-VII seam of 3&4 incline under JPC
Roof heightening by drilling blasting in stone including dressing & Cleaning with cost of drill rod and drill bit
Roof bolting including carrying of materials from surface to u/g side, drilling, grouting & cost of drill rod and drill bit.
Total impact of GST for the purpose of CTC
K R ENTERPRISE
N.K. ENTERPRISE
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .