| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹14.4 LAccepted-AOC | ₹14.4 L | L1 | Accepted-AOC Accept |
| 2 | L2₹14.5 LRejected-AOC | ₹14.5 L | L2 | Rejected-AOC Reject |
| Sl No | Description | Qty | Unit | K.Mohamed Hanifa L2 | S.Arockiyasamy L1 |
|---|---|---|---|---|---|
| 1.01 | Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,complete 10 cum | 245 | M3 | 200 ₹49,000 | 197.5 ₹48,387.50 |
| 2.01 | Cement Concrete 1:4:8 (One Cement, Four crushed stone sand and Eight hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick well rammed, consolidated and including curing etc. complete complying with standard specification and as directed by the departmental officers -Mixing by mechanical means | 38 | M3 | 5,565 ₹2.1 L | 5,562 ₹2.1 L |
| 3.01Supplying and errecting centering to sides and soffits inculding supports and strtting for drainage sides and culvertbody wall sides using 90cm x 60cm and B.G 10stifened with welded mild steel angles of size 25mm x 25mm x 3mm for boarding laid over(silver oak joists) of size 10cm x 6.50cm spaced at about 90cm including all labour charges and cost and conveyance of all materials to site etc. complete complying with standard specification. TNDSS NO. 30 & 86 | |||||
| 3.02 | Side wall | 549 | M2 | 715 ₹3.9 L | 710.5 ₹3.9 L |
| 3.03 | Culvert | 27 | M2 | 940 ₹25,380 | 937 ₹25,299 |
| 4.01Providing granolithic floor finish of the following thickness with plain cement concrete 1:2:4 (One Cement, Two M.sand and Four aggregate) using 10 to 12mm gauge hard broken stone jelly including laying, finishing and the top rubbed smooth with power trawl, thread lining, curing etc. complete complying with standard specification and as directed by the departmental officers. (The rate is inclusive of necessary planking for panelling wherever necessary and as directed by the departmental officers) | |||||
| 4.02 | For 25mm thick | 140 | M2 | 175 ₹24,500 | 174 ₹24,360 |
| 5.01 | Plain Cement Concrete 1:2:4 (one cement, two crushed stone sand and four hard broken stone jelly) using 20mm jelly for wearing coat including laying, compacting, finishing and curing, etc., complete as per standard specificatins and as directed by the departmental officers.-Mixing by mechanical means (S.No:135-SD Book Vol-I ). | 89 | M3 | 7,000 ₹6.2 L | 6,995 ₹6.2 L |
| 6.01 | Supplying, fabricating and placing in position Mild Steel / Ribbed Tor Steel reinforcement grills of all variety like HYSD/CTD/TMTand all grade like Fe 500, Fe550D, Fe 500 D etc., for all RCC works as per design given including cost of steel reinforcement and G.I. binding wire, wastage etc. complete complying with standard specification and as directed by the departmental officers.(Contractor has to make his own arrangements for the supply of steel reinforcement and binding wire) (S.No:168-SD Book Vol-I ) | 700 | kg | 93 ₹65,100 | 92.75 ₹64,925 |
| 7.01 | Providing and laying in position, standardised concrete Mix M-20 Grade by insitu machine mix concrete adopting weighing batch method in accordance with IS 456 using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement content of 325 kg/m3 and maximum water cement ratio of 0.55, including admixture (plasticiser / super plasticiser) in recommended proportions as per IS:9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability with about (5 Cu.m) 7730 kg. of 20mm machine crushed stone jelly and with about (3.3 Cu.m) 5156 kg. of 10-12mm machine crushed stone jelly and with about (4.79 cu.m) 7670 kg. of crushed stone sand, but excluding cost of reinforcement grill and fabricating charges, centering and shuttering and also including laying, vibrating with mechanical vibrators, finishing, curing, etc. and providing fixtures like fan clamps in the RCC floor/ roof slabs wherever necessary without claiming extra, etc., complete complying with standard specification and as directed by the departmental officers. The coarse and fine aggregates to be used should comply with the requirements of IS standards. | 7 | M3 | 8,088 ₹56,616 | 8,085 ₹56,595 |
Tender Value
₹17.3 L
EMD Value
₹17,300
Closing Date
11 Sept 2025, 3:00 pmClosed
The Executive Officer
Town Panchayat Office, Uthamapalayam, Theni Dist
15th FC -2025-26-Tied Grant and Untied Grant-Construction of Storm water drain at ward-1 Puthur road, Muthukaruppanasamy kovil street and ward-12 Seenivasan House street,Mariyamman kovil(madurai road) in Uthamapalayam Town Panchayat.
2025_DTP_599955_1
114/2025
Open Tender
Civil Works
180 days
Uthamapalayam Town Limit
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹17,300
5 May 2026
3 Sept 2025
11 Sept 2025
3 Sept 2025
11 Sept 2025
3 Sept 2025
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_717115.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.20 MB
BOQ_717115.xls
BOQ • 0.34 MB
Download all tender documents and submit your bid