| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹11.2 LAccepted-AOC 1 338 BX 1ST STREET UTHUKULI ROAD GOLDEN NAGAR CHENGAPPALLI TIRUPPUR 638 812 | TIRUPPUR | TIRUPPUR | TAMIL NADU | 638812 | 1 | Accepted-AOC L1 | |
| 2 | Not Admitted-Fee/PreQual/Technical NO 1 2370 MOTHER TERESA STR SIVANTHI ADHITHTAN NAGAR REDHILLS CHENNAI 600052 | THIRUVALLUR | TAMIL NADU | 600052 | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹10.0 L
EMD Value
₹10,000
Closing Date
25 Nov 2023, 2:00 pmClosed
SE/CEDC/S/CBE
Office of the SE/CEDC/S/CBE
Providing protection wall to the East and North side of Sub Store at 110 33 11 KV Kurichi Sub Station Premises
2023_EB_389064_1
SE/CEDC/S/C/No.20/23-24
Open Tender
Civil Works
Works
90 days
Kurichi SS
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹10,000
2 Apr 2024
15 Nov 2023
25 Nov 2023
15 Nov 2023
25 Nov 2023
15 Nov 2023
Amount
Earth work excavation in hard gravelly soil. Stiff black cotton soil, hard red earth, shales, Murram, gravel, stoney earth mixed with small sized boulders etc., complete as per standard specification.
Filling with M sand for foundation and consolidation with water inclduing cost of all materials, all lead and lift labour etc., complete.
Plain cement concrete in CC 1:3 :6 using 40mm HBG metal, including cost of cement, all materials, labour charges including consolidation, curing, all leads, lifts, as per standard specification etc., complete.
Brick work in CM 1:5 using Fly ash Bricks, including cost of all materials, labour charges, curing scaffolding charges, curing all leads and lifts etc., complete and as directed by Engineer incharge.
Plastering 1:5, 12 mm thick on both sides of brick wall including the cost of all material, scaffolding charges, cement, labour charges, scafolding charges, all leads, lifts, as per standard specification.
Colour washing two coats using cement paint over one coat of white cement of best quality for inside wall including cost of all materials, labour, curing, all leads & lifts etc., complete, as per standard specification.
PCC 1:2:4 using 20mm to 12mm metal for coping concrete for including cost of all materials,labour curing all lead and lift etc., complete.
RCC 1:1.5:3, using 12 to 20 mm HBG machine crushed metal for column, plinth beam and grade beam including cost of cement and all lead, lift , curing etc., complete but excluding cost of steel reinforcement. -column and footing below ground level
RCC 1:1.5:3, using 12 to 20 mm HBG machine crushed metal for column, plinth beam and grade beam including cost of cement and all lead, lift, curing etc., complete but excluding cost of steel reinforcement.- column above ground level
Supplying and fabricating and placing in position of MS/RTS steel reinforcement for RCC works including labour for cutting, bending, tying and fixing in position as per specification including cost of all materials, lead, lift,labour, cost of binding wire, etc., complete.
Supplying of 5 Mtrs wide MS grill gate and 0.90m wide MS wicket gate as Per drawing and as per direction of Engineer at site cost including all materials,T&P lead,lift Painting with two coats of approved enamel paint over one coat of red oxide primer paint etc complete
Supply and fixing of Entrance gate light with CFL bulb fittings including cost of all materials,labour etc., complete
SGST to be quoted in Percentage (value alone) Ex. 9%, it should be entered as 9 only
CGST to be quoted in Percentage (value alone) Ex. 9%, it should be entered as 9 only
Inter-state GST @18% for other than Tamil Nadu supplier. If the contractor is within Tamil Nadu may be quoted as "0" only
Description of Work / Item(s)
Amount
Dismantling of existing barbed wire fencing and CR stone including removing, rolling and stacking at site including cost of labour charges etc., complete.
Earth work excavation in hard gravelly soil. Stiff black cotton soil, hard red earth, shales, Murram, gravel, stoney earth mixed with small sized boulders etc., complete as per standard specification.
Filling with M sand for foundation and consolidation with water inclduing cost of all materials, all lead and lift labour etc., complete.
Plain cement concrete in CC 1:3 :6 using 40mm HBG metal, including cost of cement, all materials, labour charges including consolidation, curing, all leads, lifts, as per standard specification etc., complete.
Brick work in CM 1:5 using Fly ash Bricks, including cost of all materials, labour charges, curing scaffolding charges, curing all leads and lifts etc., complete and as directed by Engineer incharge.
Plastering 1:5, 12 mm thick on both sides of brick wall including the cost of all material, scaffolding charges, cement, labour charges, scafolding charges, all leads, lifts, as per standard specification.
SGST to be quoted in Percentage (value alone) Ex. 9%, it should be entered as 9 only
CGST to be quoted in Percentage (value alone) Ex. 9%, it should be entered as 9 only
Inter-state GST @18% for other than Tamil Nadu supplier. If the contractor is within Tamil Nadu may be quoted as "0" only
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .