Loading…
Loading…
Tender Value
₹2.0 Cr
EMD Value
₹4 L
Closing Date
16 Aug 2026, 5:00 pmClosed
Rajesh Kumar
Project Director
WTP Campus Barari Bhagalpur
Rajesh Kumar
Project Director
Construction of PCC Road and Drain from Raju Pan Dukan to Falmandi,Subjee Mandi,Vending Zone, Machhalipatti Road & Hari Sah Lodge via Radhey Colony in Ward No-08,Under Bhagalpur Nagar Nigam Area
137981
23/2025-26/BUIDCO/BHAGALPUR/01
Open Tender
CIVIL
Bhagalpur
• EMD Document as per NIT
• Affidavit as per NIT
• Details of Tools and Plants as per NIT
• Character Certificate
• Legal Status as per NIT Document
• Details of GST and PAN
• Certificate of Registration
• Detail of Key Personnel as per NIT
• Similar Nature of Work
CIVIL
PERCENTAGE
L1
1
10 documents required · 10 mandatory
₹17,700
Processing Fee: 5900
₹4 L
REFER NIT
13 Aug 2026
13 Aug 2026
17 Aug 2026
13 Aug 2026
16 Aug 2026
13 Aug 2026
14 Aug 2026
Abstract of Cost
1 Cost of RCC Drain Rs. #REF!
2 Cost of PCC Road Rs. #REF!
3 Cost of Sign Board, Quality test and Photography Rs. 6,000.00
Total Rs. #REF!
4 Add 5.36% GST Rs. #REF!
5 Add 7% Centage Rs. #REF!
Asst. Project Director Deputy Project Director Project Director
BUIDCo., Bhagalpur BUIDCo., Bhagalpur BUIDCo., Bhagalpur
Office of The Project Director
BUIDCo. Bhagalpur
Bill of Quantity (BOQ)
योजना का नाम :- भागलपुर नगर निगम के क्षेत्रान्तर्गत वार्ड नं०-08, में राजू पान की दुकान से लेकर फलमंडी, सब्जीमंडी, वेंडिंगजोन, मछलीपट्टी रोड एवं राधे कॉलोनी होते हुए हरि शाह के लॉज के आगे तक पीo सीo सीo पथ एवं नाला का निर्माण कार्य|
Sl. No SOR Particular Unit Qty Rate Amount
1 BCD/15.2.1 Demolishing cement concrete including disposal of material within 50m lead 1:3:6 or richer mix M³ 162.00 970.90 157286.00
2 BCD/2.8.1 Earth work in excavation in foundation trenches or drains(not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m . including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m M³ 2064.07 360.70 744512.00
3 BCD/2.28 Supplying and Filling in plinth with local sand and under floors including, watering, ramming consolidating and dressing complete M³ 829.65 287.30 238358.00
4 BCD/11.72 Providing 100A Brick flat soling joints filled with local sand including cost of watering, taxes, royalty all complete as per building specification and direction of E/l, M² 1131.00 283.30 320412.00
5 BCD/11.73 Providing designation 100A one brick on edge soling joints filled with local sand including cost of watering taxes,royalty all complete as per building specification and direction of E/l, M² 2200.00 444.80 978560.00
6 BCD/5.1.2 Providing and laying in position 1:1:5:3(1 cement: 1.5 coarse sand:3 graded stone aggregate 20 mm nominal size) reinforced cement concrete excluding the cost of centring, M³ 795.60 4688.30 3730011.00
7 BCD/4.1.2 Providing and laying in position cement concrete of specified grade excluding cost of centering and shuttering-all work upto plinth level 1:1.5:3(1 cement: 1.5 coarse sand:3 graded stone aggregate 20 mm nominal size) M³ 440.00 4420.80 1945152.00
8 BCD/5.22.7B Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all completeThermo-Mechanically Treated bars TMTC-500 MT 71.60 92600.00 6630530.00
9 BCD/5.9.1 Centring and shuttering including strutting,propping etc. and removal or form work for Foundation, footing, bases, column M² 5109.00 211.60 1081064.00
10 BCD/4.3.1 Centring and shuttering including strutting,propping etc. and removal or form work for Foundation, footing, bases, column M² 220.00 211.10 46442.00
11 RCD/3.11 Removal of unserviceable soil including excavation, loading and disposal upto 1000 metres lead but excluding replacement by suitable soil which shall be paid separately as M³ 1651.26 122.09 201602.00
12 Carriage of Materials
(i) Cement MT 494.24 0.00 0.00
(ii) Coarse Sand M³ 525.13 414.75 217798.00
(iv) Bricks Per tho 154758.00 936.04 144860.00
(vi) Steel MT 71.60 0.00 0.00
13 Difference cost of materials
(ii) Bricks Per tho 154758 421.25 65192.00
14 Add seigniorage fee
i Coarse Sand M³ 525.13 17.58 9232.00
ii Stone Chips M³ 1050.26 62.66 65809.00
iii Bricks Per tho 154758 512.80 79360.00
iv Local Sand M³ 912.62 14.19 12950.00
Sub Total 18960282.00
Total Rs.- 19976553.00
Asst. Project Director Deputy Project Director Project Director
BUIDCo., Bhagalpur BUIDCo., Bhagalpur BUIDCo., Bhagalpur
Sl. No. SOR ref Particulars Unit Quantity Rate Amount in Rs.
Nos L in m B in m H in m
1 BCD/2.8.1 Earth work in excavation in foundation trenches or drains(not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m . including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m
2 BCD/2.28 Supplying and Filling in plinth with local sand and under floors including, watering, ramming consolidating and dressing complete
3 BCD/11.72 Providing 100A Brick flat soling joints filled with local sand including cost of watering, taxes, royalty all complete as per building specification and direction of E/l,
4 BCD/5.1.2 Providing and laying in position 1:1:5:3(1 cement: 1.5 coarse sand:3 graded stone aggregate 20 mm nominal size) reinforced cement concrete excluding the cost of centring,
5 BCD/5.22.7B Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all completeThermo-Mechanically Treated bars TMTC-500
Qty vide item no. 4 9
6 BCD/5.9.1 Centring and shuttering including strutting,propping etc. and removal or form work for Foundation, footing, bases, column
7 RCD/3.11 Removal of unserviceable soil including excavation, loading and disposal upto 1000 metres lead but excluding replacement by suitable soil which shall be paid separately as
Qty vide item no. 1 @ 80% m3 12.6 122.09 1538
8 Carriage of Materials-
i Cement MT 3.6 466.92 1681
ii Coarse Sand m3 3.83 406.87 1558
iii Stone Chips m3 7.65 2067.34 15815
iv Bricks Nos 677 918.24 621648
v Local Sand m3 1.89 310.14 586
vi Steel MT 0.675 466.92 315
9 Difference cost of Materials
i Cement MT 3.6 251.59 906
ii Bricks Nos 677 365.61 247518
10 Add Seignorage Fee
i Coarse Sand m3 3.83 17.58 67
ii Stone Chips m3 7.65 62.66 479
iii Bricks Nos 677 512.8 347166
iv Local Sand m3 1.89 14.19 27
Total Rs. 1372908
Junior Engineer Assistant Engineer Executive Engineer
UDHD Bhagalpur UDHD Bhagalpur UDHD Bhagalpur
Statement of Materials for CD work
Sl No. Particulars Quantity Cement C- Sand Chips Bricks L- Sand Steel
4 Steel 0.675 MT 0.675
MT m3 m3 Nos m3 MT
Junior Engineer Assistant Engineer Executive Engineer
UDHD Bhagalpur UDHD Bhagalpur UDHD Bhagalpur
NAGAR NIGAM BHAGALPUR
Name of Work/Bill of Quantity for :- #REF!
Estimated Cost (in Rs.) :- #REF!
Earnest Money (in Rs.) :- #REF!
Time of Completion (in months) :- 04 Months
Cost of BOQ (in Rs.) :-
Sl. No Particular Unit Qty Rate Amount
1. B.C.D 2.8.1 Earth work in excavation in all kinds of soil in foundation trenches or drains (not exceeding 1.5m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5m including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 M (All kinds of soil) M³ #REF! 360.70 #REF!
2. B.C.D 2.28 Supplying and filling in plinth with local and under floors including watering, ramming, consolidation and dressing complete job as per E/I. M³ #REF! 287.30 #REF!
3. B.C.D 11.72 Providing designation 100 A one brick flat soling joints filled with local sand including cost of watering, taxes, royalty all complete as per building specification and direction of E/I M² #REF! 283.30 #REF!
4. B.C.D 5.1.2 Providing and laying in position specified grade of reinforced cement concrete excluding the cost of centering, shuttering, finishing and reinforcement. All work up to plinth level. 1:1.5:3 (1 Cement: 1.5 Coarse sand : 3 graded stone aggregate of 20 mm nominal size) M³ #REF! 4688.30 #REF!
5. B.C.D 5.22.7B Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete. Thermo-Mechanically Treated bars TMTC-500-10mm dia. MT #REF! 92600.00 #REF!
6. B.C.D 5.9.1 Centering and Shuttering including strutting, propping etc.and removal or form work for foundation, footings, bases Columns M² #REF! 211.60 #REF!
7. R.C.D 3.11.1 Removal of unserviceable soil with disposal upto1000 meters (Removal of unserviceable soil including excavation, loading and disposal upto 1000 meters lead but excluding replacement by suitable soil which shall be paid separately as per clause 305) M³ #REF! 122.09 #REF!
8. B.C.D 15.2.1 Demolishing cement concrete including disposal of material within 50m lead 1:3:6 or richer mix M³ #REF! 970.90 #REF!
9. B.C.D 4.1.8 Providing PCC 1:4:8(1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size) M³ #REF! 2975.20 #REF!
10. B.C.D 4.1.2 Providing and laying in position cement concrete of specified grade exluding the cost of centring and shuttering-all work upto plinth level.1:1.5:3(1 Cement :1.5 coarse sand:3 graded stone aggregate 20 mm nominal size) M³ #REF! 4420.80 #REF!
11. B.C.D 4.3.1 Centering and Shuttering including strutting, propping etc.and removal or form work for foundation, footings, bases Columns M³ #REF! 211.10 #REF!
12 Carriage of Materials
(i) Cement MT #REF! 466.92 #REF!
(ii) Coarse Sand M³ #REF! 406.87 #REF!
(iii) Stone Chips M³ #REF! 2067.34 #REF!
(iv) Bricks Per tho #REF! 918.24 #REF!
(v) Local Sand M³ #REF! 310.14 #REF!
(v) Steel mt #REF! 466.92 #REF!
13 Difference cost of materials
(i) Cement MT #REF! 251.69 #REF!
(ii) Bricks Per tho #REF! 365.61 #REF!
14 Add seigniorage fee
i Coarse Sand M³ #REF! 17.58 #REF!
ii Stone Chips M³ #REF! 62.66 #REF!
iii Bricks Per tho #REF! 512.80 #REF!
iv Local Sand M³ #REF! 14.19 #REF!
15 Cost of Sign Board, Quality Test and Photography (Payment as per actual voucher) LS 1.00 6000.00 6000
Sub Total #REF!
16 Add 5.36% GST #REF!
Total :- Rs.- #REF!
Junior Engineer Assistant Engineer
UDHD Bhagalpur UDHD Bhagalpur
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
NIT-23.pdf
NIT • 1.33 MB
NIT-23-2.pdf
NIT • 1.33 MB
Raju Paan.xlsx
NIT • 0.05 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .