Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹19.2 LAccepted-AOC 0 AHAMADPUR AHAMADPUR AHAMADPUR JAUNPUR UTTAR PRADESH 222180 | JAUNPUR | UTTAR PRADESH | 222180 | L1 | Accepted-AOC accepted | |
| 2 | L2₹20.2 L+₹1.0 L (5.31%)Rejected-AOC | L2 | Rejected-AOC rejected | |
| 3 | L3₹21.1 L+₹1.8 L (9.55%)Rejected-AOC | L3 | Rejected-AOC rejected | |
| 4 | L4₹21.1 L+₹1.8 L (9.60%)Rejected-AOC | L4 | Rejected-AOC rejected | |
| 5 | L5₹22.3 L+₹3.1 L (15.9%)Rejected-AOC | L5 | Rejected-AOC rejected |
Tender Value
₹27.4 L
EMD Value
₹54,800
Closing Date
6 Mar 2024, 3:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
E.E. Belan Canal Division Prayagraj
E.E. Office of the Belan Canal Division Sichai Colony Prayagraj
Reconstruction of V.R.B. at km. 3.107 of Hardiya Dy.
2024_UPIDC_907515_1
07/EE/2023-24
Open Tender
Civil Works
Item Wise
45 days
Prayagraj
Please refer Tender documents.
2 documents required · 2 mandatory
₹854
₹54,800
5 Apr 2024
29 Feb 2024
6 Mar 2024
29 Feb 2024
6 Mar 2024
29 Feb 2024
Amount
Dismentaling of stone masonry in CM with proper stacking & disposal of dismentaled materials with all lead & lift including labour, material, T&P etc. as per direction of egineer in charge.
Dismentaling of RCC work its proper disposal & stacking of dismentaled material with all lead & lift including labour, material, T&P etc. as per direction of egineer in charge.
Dismentaling of CC work its proper disposal of dismentaled material with lead & lift including labour, material, T&P etc. as per direction of egineer in charge.
Excavation of foundation and its back filling with all type of soil including labour, T&P etc. for proper compeltion of work as per direction of Engineer-in-Charge.
Laying C.C. M-10 (1:3:6) one part of cement three part of coarse sand F.M.>2.00 & six part of stone ballast (size 20 mm to 40 mm) including cost of labour, material, T&P etc. for proper completion of work as per direction of Engineer-in-charge.
C.R.S masonary in 1:3CM (one part of cement, three Part of coarse sand F.M.>2.00) including cost of labour, materials, T&P etc. for proper completion of work as per direction of Engineer-in-charge.
Centering and shuttering of R.C.C. work including cost of all labour, material, T&P etc. for proper completion of work as per direction of Engineer-in-Charge.
Supplying & fixing 20mm thick joint filler board including cost of labour, material, T&P etc. for proper completion of work as per direction of Engineer-in-Charge.
S/L 3mm thick multi-plast poly Plus Tar paper including cost of labour, material, T&P etc. for proper completion of work as per direction of Engineer-in-Charge.
Reinforcement of R.C.C. work including cost of steel, cutting, bending, placing in position & binding with 16 gauge binding wire including cost of labour, material, T&P etc. for proper completion of work as per direction of Engineer-in-Charge.
Laying R.C.C. M-20 (1:1.5:3) A-20, M-20 with cement, crushed grit size 10mm to 20mm well graded including cost of labour, material, T&P etc. for proper completion of work as per direction of Engineer-in-Charge.
Laying C.C. M-20 (1:1.5:3) A-20, M-20 with cement, crushed grit size 10mm to 20mm well graded including cost of labour, material, T&P etc. for proper completion of work as per direction of Engineer-in-Charge.
Cement pointing 1:2 C.M. including cost of labour, material, T&P etc. for proper completion of work as per direction of Engineer-in-Charge.
E/w in filling for making approach path & diversion including all lead & lift etc. including cost of labour, material, T&P etc. for proper completion of work as per direction of Engineer-in-Charge. f Engineer-in-Charge.
E/w Dismentaling of diversion including all lead & lift, cost of labour, material, T&P etc. for proper completion of work as per direction of Engineer-in-Charge. f Engineer-in-Charge.
Dry stone boulder Pitching 200mm thick, filling joint with sand including cost of labour, material, T&P etc. for proper completion of work as per direction of Engineer-in-Charge.
Colour washing of two coat of parapet including cost of all materials, labour and T&P etc.
Fixing wheel guard stone including cost of all materials, labour and T&P etc.
M/S GUFRAN CONSTRUCTION
M/S RAM ASAREY PATEL
ASHWANI SINGH
R.P. SINGH
M/S ADITYA CONSTRUCTION COMPANY
M/S NAGENDRA SINGH
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .