| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.7 LAccepted-AOC JHIRKEY KATHARA BOKARO JHARKHAND 829116 | KATHARA | BOKARO | JHARKHAND | 829116 | ₹3.7 L | L1 | Accepted-AOC Awarded as Techno commercially accepted being as L1 bidder |
| 2 | L2₹3.9 LRejected-Finance JHIRKEY KATHARA BOKARO JHARKHAND 829116 | KATHARA | BOKARO | JHARKHAND | 829116 | ₹3.9 L | L2 | Rejected-Finance Techno commercially rejected not being as L1 bidder |
| 3 | L3₹3.9 LRejected-Finance JHIRKEY KATHARA BOKARO JHARKHAND 829116 | KATHARA | BOKARO | JHARKHAND | 829116 | ₹3.9 L | L3 | Rejected-Finance Techno commercially rejected not being as L1 bidder |
| Sl No | Description | Qty | Unit | M/S GENERAL ENGINEERING CONSTRUCTION L2 | AASHIQUE ANSARI L3 | M/S SHABIR ANSARI L1 |
|---|---|---|---|---|---|---|
| 1.01 | A)Dismantling and shifting for motor of unit no. 934
Rigger (2 head x 2 shift x 4 days) | 16 | Manshift | 630 ₹10,080 | 650 ₹10,400 | 610 ₹9,760 |
| 1.02 | Welder (1 head x 2 shift x 4 days) | 8 | Manshift | 750 ₹6,000 | 760 ₹6,080 | 734 ₹5,872 |
| 1.03 | Fitter (1 head x 2 shift x 4 days) | 8 | Manshift | 750 ₹6,000 | 760 ₹6,080 | 734 ₹5,872 |
| 1.04 | Helper (4 head x 2 shift x 4 days) | 32 | Manshift | 550 ₹17,600 | 560 ₹17,920 | 522 ₹16,704 |
| 1.05 | Supervisor (1 head x 2 shift x 4 days) | 8 | Manshift | 630 ₹5,040 | 650 ₹5,200 | 610 ₹4,880 |
| 1.06 | B) Fabrication and erection of Tail drum structure of unit no. 949
Rigger (2 head x 2 shift x 8 days) | 32 | Manshift | 630 ₹20,160 | 650 ₹20,800 | 610 ₹19,520 |
| 1.07 | Welder (2 head x 2 shift x 8 days) | 32 | Manshift | 750 ₹24,000 | 760 ₹24,320 | 734 ₹23,488 |
| 1.08 | Fitter (1 head x 2 shift x 8 days) | 16 | Manshift | 750 ₹12,000 | 760 ₹12,160 | 734 ₹11,744 |
| 1.09 | Helper (3 head x 2 shift x 8 days) | 48 | Manshift | 550 ₹26,400 | 550 ₹26,400 | 522 ₹25,056 |
| 1.10 | Supervisor (1 head x 2 shift x 8 days) | 16 | Manshift | 630 ₹10,080 | 650 ₹10,400 | 610 ₹9,760 |
Tender Value
₹4.5 L
EMD Value
₹5,600
Closing Date
16 Aug 2025, 11:00 amClosed
Anant Paswan
Office of Project Officer, Kathara Washery, Kathara Area
Fabrication and erection of A)Tail drum structure of unit no. 949 and B)Dismantling/shifting for motor of unit no. 934 in RLB section C)Fabrication and erection of payjama chute of washed coal belt conveyor and discharge chute of new bunker belt conv
2025_CCL_340901_1
PO/KTW/EnM/eTen/25-26/57 Dated-04.08.2025
Open Tender
Electrical and Maintenance Works
26 days
Kathara Washery
As per NIT
4 documents required · 4 mandatory
₹5,600
23 Jan 2026
4 Aug 2025
18 Aug 2025
5 Aug 2025
16 Aug 2025
5 Aug 2025
5 Aug 2025 - 11 Aug 2025
Amount
A)Dismantling and shifting for motor of unit no. 934 Rigger (2 head x 2 shift x 4 days)
Welder (1 head x 2 shift x 4 days)
Fitter (1 head x 2 shift x 4 days)
Helper (4 head x 2 shift x 4 days)
Supervisor (1 head x 2 shift x 4 days)
B) Fabrication and erection of Tail drum structure of unit no. 949 Rigger (2 head x 2 shift x 8 days)
Welder (2 head x 2 shift x 8 days)
Fitter (1 head x 2 shift x 8 days)
Helper (3 head x 2 shift x 8 days)
Supervisor (1 head x 2 shift x 8 days)
Tools & tackles
Contractor profit
Oxygen Gas
D.A. Gas
Electrode
C) Fabrication and erection of payjama chute of washed coal belt conveyor and discharge chute of new bunker belt conveyor Rigger (1 head x 2 shift x 14 days)
Welder (2 head x 2 shift x 14 days)
Fitter (1 head x 2 shift x 14 days)
Helper (4 head x 2 shift x 14 days)
Supervisor (1 head x 2 shift x 14 days)
Tools & tackles
Contractor profit
Oxygen Gas
D.A. Gas
Electrode
Total impact of GST for the purpose of CTC
M/S GENERAL ENGINEERING CONSTRUCTION (BID ID -1174913)
AASHIQUE ANSARI (BID ID -1174914)
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx