Loading…
Loading…
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹83.8 L
EMD Value
₹83,800
Closing Date
21 Oct 2026, 4:00 pm3d left
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
SuperintendingEngineer Ganjam RandB DivNoIBAM
O/O SuperintendingEngineer Ganjam RandB DivNoIBAM
Improvement of Casualty Front Internal Road cum Drain Starting from M.K.C.G. Main Road to OandG Building at MKCG Medical College and Hospital at Berhampur Buildings.
2026_EICCL_143422_1
SE (R and B) Divn. I BAM No.20/2026-27
Open Tender
Civil Works - Roads
Percentage
150 days
Ganjam
2 documents required · 2 mandatory
₹10,000
₹83,800
Yes
13 Oct 2026
13 Oct 2026
22 Oct 2026
13 Oct 2026
21 Oct 2026
13 Oct 2026
13 Oct 2026 - 21 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing road land in area of light jungle including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth upto 300mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned upto a lead of 1000metres including removal and disposal of top organic soil not exceeding 150mm in thickness as per Clause 201 of MoRT&H Specifications for Road & Bridge works (5th Revision)and as per direction of Engineer-in-Charge. | 980 | sqm | 8.63 | ₹8,457.4 |
| 2 | Earthwork in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work as per Clause 304 of MoRT&H Specifications for Road & Bridge works (5th Revision) and as per direction of Engineer-in-Charge. | 784.74 | cum | 93.01 | ₹72,988.67 |
| 3 | Scarifying and removing the existing bituminous road surface to the required depth as per approved drawing and technical specifications and disposal of scarified materials within all lifts and lead upto 1000mtr. complete in all respect as per Section 900, Clause 305.4.3, 305.8, 305.9.5, 501.8.3.2, 501.8.7.2 and 501.8.8.1 of MoRT&H Specifications for Road & Bridge works (5th Revision) & including cost of all labour, T&P, royalty etc complete and as per direction of Engineer-in-Charge. | 1,037.3 | sqm | 6.06 | ₹6,286.04 |
| 4 | Reworking the scarified bituminous surface suitably after supplementing the base materials with sand and compacting finished surface as per approved drawing and technical specifications as per Section 900, Clause 501.8.3.2 and 501.8.8.1 of MoRT&H Specifications for Road & Bridge works (5th Revision) and as per direction of Engineer-in-Charge. | 1,037.3 | sqm | 16.2 | ₹16,804.26 |
| 5 | Loosening to a depth of 150mm, leveling and compacting original ground supporting embankment /sub-grade as per approved drawing and technical specifications complete in all respect as per Section 900 and Clause 305, 305.3.4 of MoRT&H Specification for Road & Bridge works (5th Revision) & including cost of all labour, T&P, royalty etc complete and as per direction of Engineer-in-Charge. | 294.28 | cum | 36.09 | ₹10,620.57 |
| 6 | Construction of Granular sub-base by providing Grading -IV material spreading in uniform layers with motor grade on prepared surface, mixing by mix in place method with rotavator at OMC and compacting with vibratory roller to achieve the desired density complete as per clause 401 | 436.34 | cum | 2,336.15 | ₹10,19,355.69 |
| 7 | Providing Wet Mix Macadam using crushed stone aggregates as per approved drawing and technical specifications complete in all respect as per Section 900 and Clause 406 of MoRT&H Specifications for Road & Bridge works (5th Revision) & including cost & conveyance of all materials, labour, T&P, royalty etc complete and as per direction of Engineer-in-Charge. | 385.15 | cum | 2,463.05 | ₹9,48,643.71 |
| 8 | Providing and applying primer coat with slow setting bitumen emulsion on prepared surface of granular base, including clearing road surface and spraying primer using mechanical means as per approved drawing and technical specifications complete in all respect as per Section 900, Clause 501.5.2 & 502 of MoRT&H Specifications for Road & Bridge works (5th Revision) & including cost & conveyance of all materials, labour, T&P, royalty etc complete and as per direction of Engineer-in-Charge. | 1,657.43 | sqm | 59.47 | ₹98,567.36 |
| 9 | Providing and applying tack coat with rapid setting bitumen emulsion on the prepared bituminous/ granular surface including cleaning with mechanical broom and spraying bitumen emulsion using mechanical means as per approved drawing and technical specifications complete in all respect as per Section 900, Clause 501.5.2 & 503 of MoRT&H Specifications for Road & Bridge works (5th Revision) & including cost & conveyance of all materials, labour, T&P, royalty etc complete and as per direction of Engineer-in-Charge. | 1,657.43 | sqm | 20.43 | ₹33,861.29 |
| 10 | Providing & laying compacted Bituminous Macadam (Grading-II ) using 60/70 grade Bitumen with Hot Mix Plant using crusher broken hard granite aggregates of specified grading premixed with bituminous binder @ 3.3 % by weight of total mix and filler, transporting the hot mix to works site, lying with Hydrostatic Paver Finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled vibratory and tandem rollers to achieve the desired compacting as per Clause No.106, 108, 111, 112, 501, 503 , 504 and section 900 of specifications for Road and Bridge works of Ministry of Road Transport & Highways (5th Revision) &including cost of all materials, labour, T&P, taxes, royalty etc complete in all respect and as per direction of the Engineer-in-charge. | 81.27 | cum | 9,871.68 | ₹8,02,274.4 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_2.pdf
PDF • 1.96 MB
Tendernotice_1.pdf
PDF • 0.44 MB
BOQ_613807.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .