Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹23.2 L
EMD Value
₹46,500
Closing Date
24 Oct 2026, 5:00 pm6d left
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
E.E. R.D.Spl. Division, Sahibganj
E.E. R.D.Spl. Division, Bikas bhawan, Sahibganj
Construction of R.C.C Drain Along with P.C.C Road from Main Road to Kabristhan in Vill-Aahutgram of Panchayat Aahutgram Block Barharwa District Sahibganj.
2026_RDSPL_119932_1
RDSpl/SAHIBGANJ/09/2026-27 GR5
Open Tender
Civil Works
Percentage
90 days
Block Barharwa District Sahibganj.
Please refer Tender documents.
2 documents required · 2 mandatory
₹5,000
₹46,500
15 Oct 2026
15 Oct 2026
26 Oct 2026
15 Oct 2026
24 Oct 2026
15 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Jungle clearance in borrow area, building premises, flanks and slopes on the roads, canals and embankment by removing the grass and the jungle bushes from the top including weeding out shrubs including roots and levelling etc. complete as per direction of E/I. | 0.03 | Ha | 19,760.3 | ₹652.09 |
| 2 | Earth work in excavation in foundation trenches in ordinary soil ( vide classification of soil item A) and disposal of excavated earth as obtained to a distance upto 50M including all lifts leveling ramming the foundation treanches, removing roots of trees, and shrubs all complete as per approved design, building specification and direction of E/I. | 122.41 | M3 | 151.82 | ₹18,584.29 |
| 3 | Extra for earth work in hard soil as per specification and direction of E/I | 122.41 | M3 | 15.51 | ₹1,898.58 |
| 4 | Providing coarse clean sand in filling in in foundation trenches or in plinth including ramming and watering in layers not exceeding 150mm thick with all leads and lifts including cost of all materials labour, royalty and taxes all complete as per building specification and direction of E/I (Mode of measurement compacted volume) | 51.04 | M3 | 589.51 | ₹30,088.59 |
| 5 | Supplying and laying (Properly as per design and drawing) rip rap with good quality boulder duly packed including the cost of material, roylity all taxes but excluding the cost of carriage. All complete as per specification and direction of E/I. | 51.04 | M3 | 1,756.4 | ₹89,646.66 |
| 6 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:1.5.3(1 cement : 1.5 coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size) | 122.54 | M3 | 4,961.73 | ₹6,08,010.39 |
| 7 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:2:4 (1 cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size) | 2.29 | M3 | 4,598.23 | ₹10,529.95 |
| 8 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level. 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size) | 43.31 | M3 | 5,218 | ₹2,25,991.58 |
| 9 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size). | 16.47 | M3 | 6,308.87 | ₹1,03,907.09 |
| 10 | providing Tor steel reinforcement of 10mm,12mm,& 16mm. dia bars as per approved design and drawing inclusive carriage of M.S. bars to work site, cutting, bending and binding with annealed wire with cost of the wire, removal of rust, placing the rods in position all complete as per building specification and direction of E/I.(b) 12mm (TMT coil Fe 500) (only valid for Tata (Tiscon), SAIL, JSPL,Electrosteel Steels Ltd. Bokaro and Vizag (RINL)}) | 5.94 | MT | 82,096.54 | ₹4,87,817.64 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 3.02 MB
BOQ_162256.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .